We can review the summons, agency record, correction status and available evidence; define the hearing strategy; prepare the authorized submission or appearance; and coordinate the underlying violation-resolution work separately where needed. Because hearing deadlines are fixed, substantive work begins after scope, authorization and payment.

Property / Hearing Identifiers

Primary hearing issue: Failure to Maintain

BoroughManhattan
BIN1009382
Block / Lot00570 / 0017
October Records3
Official violation location: Loading from NYC OATH public records…
Address is resolved from the OATH Hearings Division Case Status record for OATH ticket 039198834X (source ECB number 39198834X). BIN and block/lot remain shown below for verification.

October 2026 Hearing Records

OATH/ECB #HearingSeverityHearing statusBalanceAlleged conditionCode / section
39198835H
ACTIVE
October 8, 2026
10:30 AM
CLASS - 1 PENDING $2,500.00 ATOI APPROX. 9AM, OBSERVED FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING THROUGHOUT CONSTRUCTION SITE: 1ST -3RD FLOOR. OBSERVED PILES OF CONSTRUCTION DEBRI BAGS, PILE OF CONSTRUCTION DEBRI, STACKS 2X4S, DEMOED MATE 181 — BC 3303.4 & 27-1018 FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS
39198836J
ACTIVE
October 8, 2026
8:30 AM
CLASS - 1 PENDING $10,000.00 ATOI APPROX. 9:05AM OBSERVED FAILURE TO SAFEGUARD PROPERLY. EXPOSED FLOORING AT MEZZANINE LEVEL TO LOWER FLOOR, WHERE WORKERS WERE OBSERVED ACTIVELY PERFORMING TASKS UNDERNEATH EXPOSED OPENING AREA. UNDER JOB# 109 — BC 3301.2,27-1009(A) FAIL TO SAFEGUARD PERS/PROPERTY AFFECTED BY CONSTRUCTION OP
39198834X
ACTIVE
October 8, 2026
9:30 AM
CLASS - 2 PENDING $1,250.00 ATOI OBSERVED CONSTRUCTION WORK BEING PERFORMED( 1ST THROUGH 3RD FL) AT APPROX. 9:30AM FAILURE TO POST TPP NOTICES THROUGHOUT THE OCCUPIED FLOORS 4 THROUGH 6 IN BUILDING. WHILE WORK IS BEING DONE ON THE BELOW F 2L5

What DOB is alleging at this property

This October hearing page is not just a schedule entry. The supplied DOB extract contains 3 summons records for this property identifier. The charge mix is: Failure to Maintain; Site Safety / Safeguarding; Other Building / Code Compliance. The hearing date is October 8, 2026; the source issue date(s) are August 3, 2026.

Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.

Failure to Maintain — Summons 39198835H

CLASS - 1 · Issued August 3, 2026; hearing October 8, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ATOI APPROX. 9AM, OBSERVED FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING THROUGHOUT CONSTRUCTION SITE: 1ST -3RD FLOOR. OBSERVED PILES OF CONSTRUCTION DEBRI BAGS, PILE OF CONSTRUCTION DEBRI, STACKS 2X4S, DEMOED MATE

Cited provision(s): 181 — BC 3303.4 & 27-1018 FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS

How this type of condition is typically resolved

Failure-to-maintain charges are fact-specific. The owner should identify the exact building component or service equipment cited, repair the condition, and document the repair with evidence tied to the inspection location/date.

Hearing issues to verify

  • Does the description accurately identify the component, location and condition?
  • Was the condition already repaired or not present when the summons was issued?
  • Was another party responsible for maintenance under facts that are legally relevant to the respondent's liability?

Evidence that may matter

  • Dated before/after photographs
  • Repair invoices and contractor statements
  • Professional inspection/report when structural or technical conditions are involved
  • Maintenance logs and prior inspection records

Site Safety / Safeguarding — Summons 39198836J

CLASS - 1 · Issued August 3, 2026; hearing October 8, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ATOI APPROX. 9:05AM OBSERVED FAILURE TO SAFEGUARD PROPERLY. EXPOSED FLOORING AT MEZZANINE LEVEL TO LOWER FLOOR, WHERE WORKERS WERE OBSERVED ACTIVELY PERFORMING TASKS UNDERNEATH EXPOSED OPENING AREA. UNDER JOB#

Cited provision(s): 109 — BC 3301.2,27-1009(A) FAIL TO SAFEGUARD PERS/PROPERTY AFFECTED BY CONSTRUCTION OP

How this type of condition is typically resolved

These charges focus on protection of workers, occupants, neighboring property or the public during construction. Correction normally requires fixing the specific unsafe condition, documenting required safety measures and keeping the required site records current.

Hearing issues to verify

  • What precise safety measure does the summons say was missing or inadequate?
  • Was the condition temporary and corrected before or during the inspection?
  • Did an approved site-safety plan or required site document address the cited condition?

Evidence that may matter

  • Site Safety Plan / logistics drawings
  • Daily safety logs and competent-person/site-safety records
  • Photographs taken around the inspection time
  • Contractor or safety-manager statements and correction records

Other Building / Code Compliance — Summons 39198834X

CLASS - 2 · Issued August 3, 2026; hearing October 8, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ATOI OBSERVED CONSTRUCTION WORK BEING PERFORMED( 1ST THROUGH 3RD FL) AT APPROX. 9:30AM FAILURE TO POST TPP NOTICES THROUGHOUT THE OCCUPIED FLOORS 4 THROUGH 6 IN BUILDING. WHILE WORK IS BEING DONE ON THE BELOW F

Cited provision(s): 2L5

How this type of condition is typically resolved

The first step is to read the inspector's narrative together with every cited code section and determine exactly what act, condition or missing filing DOB alleges. The correction and hearing strategy should then be built around that specific charge rather than a generic violation-removal checklist.

Hearing issues to verify

  • Does the summons identify the correct property, respondent, date and observed condition?
  • Do agency records support or contradict the inspector's description?
  • Was the condition corrected, permitted or otherwise resolved before the hearing?

Evidence that may matter

  • Official DOB/OATH property and summons records
  • Dated photographs and videos
  • Permits, approved plans and inspection results
  • Contracts, receipts, professional letters or witness statements tied to the cited condition

Case-specific next step

For this property, the first paid review should reconcile the 3 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.

Submit These Summonses for Review

What to do before the hearing

1. Verify the summons

Confirm the scheduled date, respondent, violation location, charges and current OATH status.

2. Preserve evidence

Gather permits, photographs, contracts, inspection records, professional letters and proof of correction that actually relate to the cited condition.

3. Separate hearing from correction

A hearing result and physical/agency correction are not always the same task. Plan both tracks where required.

Official Hearing Record

Verify the current hearing status and violation location in the NYC OATH Hearings Division Case Status data before relying on any public directory.

NYC OATH Case Status Data →

OATH evidence and DOB correction records

OATH advises respondents to bring or submit the evidence needed to prove their case, including legal or official records, photographs, documents and witnesses. For a DOB Certificate of Correction, DOB may require supporting material such as photographs, receipts, permits and inspection results in addition to the required correction information and applicable civil-penalty documentation.