BuildingViolation.com

October 2026 NYC DOB / OATH Hearing — BIN 1033683

Manhattan property record with 7 OATH/ECB summons records in the supplied October 2026 hearing extract. Hearing date: October 8, 2026.

Need representation for this October hearing?

We can review the summons, agency record, correction status and available evidence; define the hearing strategy; prepare the authorized submission or appearance; and coordinate the underlying violation-resolution work separately where needed. Because hearing deadlines are fixed, substantive work begins after scope, authorization and payment.

Property / Hearing Identifiers

Primary hearing issue: Work Without a Permit

BoroughManhattan
BIN1033683
Block / Lot01242 / 0039
October Records7
Official violation location: Loading from NYC OATH public records…
Address is resolved from the OATH Hearings Division Case Status record for OATH ticket 039198808M (source ECB number 39198808M). BIN and block/lot remain shown below for verification.

October 2026 Hearing Records

OATH/ECB #HearingSeverityHearing statusBalanceAlleged conditionCode / section
39198809Y
ACTIVE
October 8, 2026
10:30 AM
CLASS - 1 ADMIT/IN-VIO $0.00 ELECTRICAL WORK WITHOUT A PERMIT. OBSERVED ON THE ROOF NEW A/C CONDENSERS INSTALLED NEW OUTDOOR PANELS AND PIPPING ALL FLOORS NEW ELECTRICAL PANELS, ALSO IN THE GROUND FLOOR NEW HUNG ELECTRIC HEATERS INSTALLED. 1C9 — 27-3018(B) ELECTRICAL WORK WITHOUT A PERMIT
39198788Y
ACTIVE
October 8, 2026
8:30 AM
CLASS - 2 PENDING $625.00 CLASS 2: TOP OF CAR LIGHT IS DAMAGED, AS PER ASME A17.1-2013, SEC. 2.7.9.2. REMEDY: REPAIR OR REPLACE THE LIGHT. COUNTERWEIGHT RUNBY SIGN IS MISSING A REQUIRED NUMERICAL DESIGNATION, AS PER ASME A17.1-2013, SEC 251 — 28-301.1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLAINT MANNER:SERVICE EQUIPMEN
39198807K
ACTIVE
October 8, 2026
8:30 AM
CLASS - 1 ADMIT/IN-VIO $0.00 ATOI OBSERVED IN THE MAIN BOILER ROOM 2 OUT OF THE 5 GAS BOILERS REMOVED CHECKED BIS/DOBNOW NO PERMIT ON FILE FOR REMOVAL OF GAS BOILERS. ALL WORK MUST BE APPROVED AND DONE BY A LICENSED MASTER PLUMBER., OBTAIN 101 — 28-105.1 WORK WITHOUT A PERMIT
39198810L
ACTIVE
October 8, 2026
8:30 AM
CLASS - 2 PENDING $250.00 UNAPPROVED/UNSAFE/UNSUITABLE ELECTRICAL EQUIPMENT, APPARATUS, MATERIALS, DEVICES, APPLIANCES OR WIRING IN USE. OBSERVED THRU OUT ALL FLOORS THAT THE EXIT / EMERGENCY LIGHTS ARE INSTALLED IMPROPERLY. ALL LIGHTIN 2E8 — EC 410.30 LUMINAIRES AND LAMPHOLDERS NOT INSTALLED IN AN APPROVED MANNER
39198789X
ACTIVE
October 8, 2026
9:30 AM
CLASS - 1 PENDING $1,250.00 CLASS 1: CLASS 1: DROP CEILING PANEL LEADING TO THE EMERGENCY ESCAPE HATCH AND THE ESCAPE HATCH ARE UNSECURED, PROVIDING UNRESTRICTED ACCESS TO THE TOP OF THE ELEVATOR CAR, AS PER ASME A17.1-2013, SECS. 2.14.1. 151 — 28-301.1 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER: SERVICE EQUIPME
39198808M
ACTIVE
October 8, 2026
9:30 AM
CLASS - 1 PENDING $2,500.00 AT THE TIME OF INSPECTION OBSERVED LACK OF COVERAGE AND OBSTRUCTED SPRINKLER HEADS LOCATED THROUGH OUT THE BUILDING CONTRARY TO FGC 903.3.3 OBSTRUCTED LOCATIONS IN AUTOMATIC FIRE SPRINKLER SYSTEMS. IT MANDATES 102 — 28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER
39198811N
ACTIVE
October 8, 2026
9:30 AM
CLASS - 1 PENDING $1,200.00 ELECTRICAL CLOSET NOT DEDICATED TO ELECTRICAL DISTRIBUTION EQUIPMENT ONLY. OBSERVED ON THE 4TH FL ELECTRICAL CLOSET NOT DEDICATED TO PANEL ONLY SHELVES ARE INSTALLED FOR STORAGE, AND CARTS, ALSO ON THE SECOND F 1D3 — EC 110.25 ELECTRIACAL CLOSET NOT DEDICATEDE TO ELECTRICAL DISTRIBUTION EQUIP ONL

What DOB is alleging at this property

This October hearing page is not just a schedule entry. The supplied DOB extract contains 7 summons records for this property identifier. The charge mix is: 2 Work Without a Permit summonses; 2 Elevator / Vertical Transportation summonses; 2 Electrical Work / Electrical Permit summonses; Failure to Maintain. The hearing date is October 8, 2026; the source issue date(s) are August 3, 2026.

Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.

Work Without a Permit — Summons 39198809Y

CLASS - 1 · Issued August 3, 2026; hearing October 8, 2026. · Hearing status: ADMIT/IN-VIO

DOB allegation in the source extract: ELECTRICAL WORK WITHOUT A PERMIT. OBSERVED ON THE ROOF NEW A/C CONDENSERS INSTALLED NEW OUTDOOR PANELS AND PIPPING ALL FLOORS NEW ELECTRICAL PANELS, ALSO IN THE GROUND FLOOR NEW HUNG ELECTRIC HEATERS INSTALLED.

Cited provision(s): 1C9 — 27-3018(B) ELECTRICAL WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Elevator / Vertical Transportation — Summons 39198788Y

CLASS - 2 · Issued August 3, 2026; hearing October 8, 2026. · Hearing status: PENDING

DOB allegation in the source extract: CLASS 2: TOP OF CAR LIGHT IS DAMAGED, AS PER ASME A17.1-2013, SEC. 2.7.9.2. REMEDY: REPAIR OR REPLACE THE LIGHT. COUNTERWEIGHT RUNBY SIGN IS MISSING A REQUIRED NUMERICAL DESIGNATION, AS PER ASME A17.1-2013, SEC

Cited provision(s): 251 — 28-301.1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLAINT MANNER:SERVICE EQUIPMEN

How this type of condition is typically resolved

Elevator charges often require licensed-elevator maintenance or repair, the required periodic inspection/test filing, an affirmation of correction where applicable, and reinspection for hazardous conditions.

Hearing issues to verify

  • Does the device number/location on the summons match the building's elevator record?
  • Was the cited defect repaired or the device removed from service before the inspection?
  • Were the required CAT/periodic inspection filings timely and accepted?

Evidence that may matter

  • Elevator device record and inspection/test reports
  • Maintenance contractor logs and repair tickets
  • Affirmation of Correction / reinspection result
  • Photographs or controller/service records

Work Without a Permit — Summons 39198807K

CLASS - 1 · Issued August 3, 2026; hearing October 8, 2026. · Hearing status: ADMIT/IN-VIO

DOB allegation in the source extract: ATOI OBSERVED IN THE MAIN BOILER ROOM 2 OUT OF THE 5 GAS BOILERS REMOVED CHECKED BIS/DOBNOW NO PERMIT ON FILE FOR REMOVAL OF GAS BOILERS. ALL WORK MUST BE APPROVED AND DONE BY A LICENSED MASTER PLUMBER., OBTAIN

Cited provision(s): 101 — 28-105.1 WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Electrical Work / Electrical Permit — Summons 39198810L

CLASS - 2 · Issued August 3, 2026; hearing October 8, 2026. · Hearing status: PENDING

DOB allegation in the source extract: UNAPPROVED/UNSAFE/UNSUITABLE ELECTRICAL EQUIPMENT, APPARATUS, MATERIALS, DEVICES, APPLIANCES OR WIRING IN USE. OBSERVED THRU OUT ALL FLOORS THAT THE EXIT / EMERGENCY LIGHTS ARE INSTALLED IMPROPERLY. ALL LIGHTIN

Cited provision(s): 2E8 — EC 410.30 LUMINAIRES AND LAMPHOLDERS NOT INSTALLED IN AN APPROVED MANNER

How this type of condition is typically resolved

Electrical charges generally require determining whether the cited installation was permitted and performed under the required licensed-electrical process, then correcting unsafe or unapproved work and obtaining any required inspection/acceptance.

Hearing issues to verify

  • Was there an active electrical application/permit covering the cited wiring or equipment?
  • Was the condition already corrected or disconnected before the inspection date?
  • Does the cited equipment/location match the permitted scope and electrical inspection record?

Evidence that may matter

  • Electrical permit/application and inspection records
  • Licensed electrician invoice, letter or work order
  • Photographs of wiring/equipment before and after correction
  • Testing, certification or utility documentation where relevant

Elevator / Vertical Transportation — Summons 39198789X

CLASS - 1 · Issued August 3, 2026; hearing October 8, 2026. · Hearing status: PENDING

DOB allegation in the source extract: CLASS 1: CLASS 1: DROP CEILING PANEL LEADING TO THE EMERGENCY ESCAPE HATCH AND THE ESCAPE HATCH ARE UNSECURED, PROVIDING UNRESTRICTED ACCESS TO THE TOP OF THE ELEVATOR CAR, AS PER ASME A17.1-2013, SECS. 2.14.1.

Cited provision(s): 151 — 28-301.1 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER: SERVICE EQUIPME

How this type of condition is typically resolved

Elevator charges often require licensed-elevator maintenance or repair, the required periodic inspection/test filing, an affirmation of correction where applicable, and reinspection for hazardous conditions.

Hearing issues to verify

  • Does the device number/location on the summons match the building's elevator record?
  • Was the cited defect repaired or the device removed from service before the inspection?
  • Were the required CAT/periodic inspection filings timely and accepted?

Evidence that may matter

  • Elevator device record and inspection/test reports
  • Maintenance contractor logs and repair tickets
  • Affirmation of Correction / reinspection result
  • Photographs or controller/service records

Failure to Maintain — Summons 39198808M

CLASS - 1 · Issued August 3, 2026; hearing October 8, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF INSPECTION OBSERVED LACK OF COVERAGE AND OBSTRUCTED SPRINKLER HEADS LOCATED THROUGH OUT THE BUILDING CONTRARY TO FGC 903.3.3 OBSTRUCTED LOCATIONS IN AUTOMATIC FIRE SPRINKLER SYSTEMS. IT MANDATES

Cited provision(s): 102 — 28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER

How this type of condition is typically resolved

Failure-to-maintain charges are fact-specific. The owner should identify the exact building component or service equipment cited, repair the condition, and document the repair with evidence tied to the inspection location/date.

Hearing issues to verify

  • Does the description accurately identify the component, location and condition?
  • Was the condition already repaired or not present when the summons was issued?
  • Was another party responsible for maintenance under facts that are legally relevant to the respondent's liability?

Evidence that may matter

  • Dated before/after photographs
  • Repair invoices and contractor statements
  • Professional inspection/report when structural or technical conditions are involved
  • Maintenance logs and prior inspection records

Electrical Work / Electrical Permit — Summons 39198811N

CLASS - 1 · Issued August 3, 2026; hearing October 8, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ELECTRICAL CLOSET NOT DEDICATED TO ELECTRICAL DISTRIBUTION EQUIPMENT ONLY. OBSERVED ON THE 4TH FL ELECTRICAL CLOSET NOT DEDICATED TO PANEL ONLY SHELVES ARE INSTALLED FOR STORAGE, AND CARTS, ALSO ON THE SECOND F

Cited provision(s): 1D3 — EC 110.25 ELECTRIACAL CLOSET NOT DEDICATEDE TO ELECTRICAL DISTRIBUTION EQUIP ONL

How this type of condition is typically resolved

Electrical charges generally require determining whether the cited installation was permitted and performed under the required licensed-electrical process, then correcting unsafe or unapproved work and obtaining any required inspection/acceptance.

Hearing issues to verify

  • Was there an active electrical application/permit covering the cited wiring or equipment?
  • Was the condition already corrected or disconnected before the inspection date?
  • Does the cited equipment/location match the permitted scope and electrical inspection record?

Evidence that may matter

  • Electrical permit/application and inspection records
  • Licensed electrician invoice, letter or work order
  • Photographs of wiring/equipment before and after correction
  • Testing, certification or utility documentation where relevant

Case-specific next step

For this property, the first paid review should reconcile the 7 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.

Submit These Summonses for Review

What to do before the hearing

1. Verify the summons

Confirm the scheduled date, respondent, violation location, charges and current OATH status.

2. Preserve evidence

Gather permits, photographs, contracts, inspection records, professional letters and proof of correction that actually relate to the cited condition.

3. Separate hearing from correction

A hearing result and physical/agency correction are not always the same task. Plan both tracks where required.

Official Hearing Record

Verify the current hearing status and violation location in the NYC OATH Hearings Division Case Status data before relying on any public directory.

NYC OATH Case Status Data →

OATH evidence and DOB correction records

OATH advises respondents to bring or submit the evidence needed to prove their case, including legal or official records, photographs, documents and witnesses. For a DOB Certificate of Correction, DOB may require supporting material such as photographs, receipts, permits and inspection results in addition to the required correction information and applicable civil-penalty documentation.