We can review the summons, agency record, correction status and available evidence; define the hearing strategy; prepare the authorized submission or appearance; and coordinate the underlying violation-resolution work separately where needed. Because hearing deadlines are fixed, substantive work begins after scope, authorization and payment.

Property / Hearing Identifiers

Primary hearing issue: Other Building / Code Compliance

BoroughManhattan
BIN1038775
Block / Lot01338 / 7503
October Records6
Official violation location: Loading from NYC OATH public records…
Address is resolved from the OATH Hearings Division Case Status record for OATH ticket 039557047Z (source ECB number 39557047Z). BIN and block/lot remain shown below for verification.

October 2026 Hearing Records

OATH/ECB #HearingSeverityHearing statusBalanceAlleged conditionCode / section
39557121H
ACTIVE
October 1, 2026
10:30 AM
CLASS - 2 PENDING $1,250.00 AT THE TIME OF INSPECTION OF A 13 STORY BUILDING I OBSERVED INADEQUATE HOUSEKEEPING ON MULTIPLE FLOORS OF THE CONSTRUCTION SITE. CONSTRUCTION DEBRIS AND MISCELLANEOUS MATERIALS WERE ACCUMULATED THROUGHOUT WORK 212 — BC 3303.4,27-1018 FAIL TO MAINTAIN ADEQUATE HSEKEEPING PER SECTIONS REQUIREMENTS
39557040X
ACTIVE
October 1, 2026
8:30 AM
CLASS - 2 PENDING $1,250.00 AT THE TIME OF INSPECTION OF THE 13-STORY BUILDING, ACTIVE CONSTRUCTION WAS OBSERVED WITH EXTERIOR STRUCTURAL WORK AND WINDOW INSTALLATION ON THE 12TH FLOOR. A REVIEW OF APPLICATION #M01330252 FOUND THAT THE ST 201 — 28-105.1 WORK WITHOUT A PERMIT
39557047Z
ACTIVE
October 1, 2026
9:30 AM
CLASS - 1 PENDING $5,000.00 AT THE TIME OF INSPECTION OF THE 13-STORY BUILDING, ACTIVE CONSTRUCTION WAS OBSERVED THROUGHOUT THE SITE. A REVIEW OF RECORDS REVEALED THAT THE GENERAL CONTRACTOR'S GENERAL LIABILITY INSURANCE HAD EXPIRED ON FE 147 — 28-401.9 FAILURE TO FILE EVIDENCE OF LIABILITY &/OR PROPERTY DAMAGE INSURANCE.
39557054R
ACTIVE
October 1, 2026
9:30 AM
CLASS - 1 PENDING $5,000.00 AT THE TIME OF INSPECTION OF THE 13-STORY BUILDING, ACTIVE CONSTRUCTION WAS OBSERVED ON FLOORS 5-9 AND THE 12TH FLOOR. A REVIEW OF RECORDS REVEALED THAT THE GENERAL CONTRACTOR'S DISABILITY INSURANCE HAD EXPIRED 148 — 28-401.9 FAILURE TO FILE EVIDENCE OF COMPLIANCE WITH WORKERS COMP, LAW AND/OR D
39557120X
ACTIVE
October 1, 2026
9:30 AM
CLASS - 2 PENDING $2,500.00 AT THE TIME OF INSPECTION OF A 13 STORY BUILDING I OBSERVED CONSTRUCTION MATERIALS STORED IN THE PUBLIC ROADWAY WITHOUT JERSEY BARRIERS, FENCING, OR OTHER APPROVED PROTECTIVE MEASURES. MATERIALS WERE READILY AC 2P7
39557124N
ACTIVE
October 1, 2026
9:30 AM
CLASS - 2 PENDING $1,250.00 AT THE TIME OF INSPECTION OF THE 13-STORY BUILDING, WORKERS WERE PERFORMING FACADE WORK AND WINDOW INSTALLATION ON THE 12TH FLOOR, ALONG WITH WIRE INSTALLATION, INTERIOR RENOVATIONS, AND HOUSEKEEPING ON FLOORS 201 — 28-105.1 WORK WITHOUT A PERMIT

What DOB is alleging at this property

This October hearing page is not just a schedule entry. The supplied DOB extract contains 6 summons records for this property identifier. The charge mix is: 2 Other Building / Code Compliance summonses; 2 Work Without a Permit summonses; 2 Crane / Hoist / Derricks summonses. The hearing date is October 1, 2026; the source issue date(s) are July 24, 2026.

Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.

Other Building / Code Compliance — Summons 39557121H

CLASS - 2 · Issued July 24, 2026; hearing October 1, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF INSPECTION OF A 13 STORY BUILDING I OBSERVED INADEQUATE HOUSEKEEPING ON MULTIPLE FLOORS OF THE CONSTRUCTION SITE. CONSTRUCTION DEBRIS AND MISCELLANEOUS MATERIALS WERE ACCUMULATED THROUGHOUT WORK

Cited provision(s): 212 — BC 3303.4,27-1018 FAIL TO MAINTAIN ADEQUATE HSEKEEPING PER SECTIONS REQUIREMENTS

How this type of condition is typically resolved

The first step is to read the inspector's narrative together with every cited code section and determine exactly what act, condition or missing filing DOB alleges. The correction and hearing strategy should then be built around that specific charge rather than a generic violation-removal checklist.

Hearing issues to verify

  • Does the summons identify the correct property, respondent, date and observed condition?
  • Do agency records support or contradict the inspector's description?
  • Was the condition corrected, permitted or otherwise resolved before the hearing?

Evidence that may matter

  • Official DOB/OATH property and summons records
  • Dated photographs and videos
  • Permits, approved plans and inspection results
  • Contracts, receipts, professional letters or witness statements tied to the cited condition

Work Without a Permit — Summons 39557040X

CLASS - 2 · Issued July 24, 2026; hearing October 1, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF INSPECTION OF THE 13-STORY BUILDING, ACTIVE CONSTRUCTION WAS OBSERVED WITH EXTERIOR STRUCTURAL WORK AND WINDOW INSTALLATION ON THE 12TH FLOOR. A REVIEW OF APPLICATION #M01330252 FOUND THAT THE ST

Cited provision(s): 201 — 28-105.1 WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Crane / Hoist / Derricks — Summons 39557047Z

CLASS - 1 · Issued July 24, 2026; hearing October 1, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF INSPECTION OF THE 13-STORY BUILDING, ACTIVE CONSTRUCTION WAS OBSERVED THROUGHOUT THE SITE. A REVIEW OF RECORDS REVEALED THAT THE GENERAL CONTRACTOR'S GENERAL LIABILITY INSURANCE HAD EXPIRED ON FE

Cited provision(s): 147 — 28-401.9 FAILURE TO FILE EVIDENCE OF LIABILITY &/OR PROPERTY DAMAGE INSURANCE.

How this type of condition is typically resolved

Crane/hoist matters are specialized safety and licensing cases. Resolution generally requires the correct equipment permit/notification, licensed operator/equipment records, inspections and compliance with site-specific lifting/safety requirements.

Hearing issues to verify

  • Did the cited equipment and activity require the permit/notification alleged?
  • Was the operator/equipment authorization current on the inspection date?
  • Do logs and inspection records contradict the unsafe condition described?

Evidence that may matter

  • Equipment permit / CD filing
  • Operator license and equipment certification
  • Inspection / maintenance / lift-plan records
  • Dated site photographs and safety logs

Crane / Hoist / Derricks — Summons 39557054R

CLASS - 1 · Issued July 24, 2026; hearing October 1, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF INSPECTION OF THE 13-STORY BUILDING, ACTIVE CONSTRUCTION WAS OBSERVED ON FLOORS 5-9 AND THE 12TH FLOOR. A REVIEW OF RECORDS REVEALED THAT THE GENERAL CONTRACTOR'S DISABILITY INSURANCE HAD EXPIRED

Cited provision(s): 148 — 28-401.9 FAILURE TO FILE EVIDENCE OF COMPLIANCE WITH WORKERS COMP, LAW AND/OR D

How this type of condition is typically resolved

Crane/hoist matters are specialized safety and licensing cases. Resolution generally requires the correct equipment permit/notification, licensed operator/equipment records, inspections and compliance with site-specific lifting/safety requirements.

Hearing issues to verify

  • Did the cited equipment and activity require the permit/notification alleged?
  • Was the operator/equipment authorization current on the inspection date?
  • Do logs and inspection records contradict the unsafe condition described?

Evidence that may matter

  • Equipment permit / CD filing
  • Operator license and equipment certification
  • Inspection / maintenance / lift-plan records
  • Dated site photographs and safety logs

Other Building / Code Compliance — Summons 39557120X

CLASS - 2 · Issued July 24, 2026; hearing October 1, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF INSPECTION OF A 13 STORY BUILDING I OBSERVED CONSTRUCTION MATERIALS STORED IN THE PUBLIC ROADWAY WITHOUT JERSEY BARRIERS, FENCING, OR OTHER APPROVED PROTECTIVE MEASURES. MATERIALS WERE READILY AC

Cited provision(s): 2P7

How this type of condition is typically resolved

The first step is to read the inspector's narrative together with every cited code section and determine exactly what act, condition or missing filing DOB alleges. The correction and hearing strategy should then be built around that specific charge rather than a generic violation-removal checklist.

Hearing issues to verify

  • Does the summons identify the correct property, respondent, date and observed condition?
  • Do agency records support or contradict the inspector's description?
  • Was the condition corrected, permitted or otherwise resolved before the hearing?

Evidence that may matter

  • Official DOB/OATH property and summons records
  • Dated photographs and videos
  • Permits, approved plans and inspection results
  • Contracts, receipts, professional letters or witness statements tied to the cited condition

Work Without a Permit — Summons 39557124N

CLASS - 2 · Issued July 24, 2026; hearing October 1, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF INSPECTION OF THE 13-STORY BUILDING, WORKERS WERE PERFORMING FACADE WORK AND WINDOW INSTALLATION ON THE 12TH FLOOR, ALONG WITH WIRE INSTALLATION, INTERIOR RENOVATIONS, AND HOUSEKEEPING ON FLOORS

Cited provision(s): 201 — 28-105.1 WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Case-specific next step

For this property, the first paid review should reconcile the 6 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.

Submit These Summonses for Review

What to do before the hearing

1. Verify the summons

Confirm the scheduled date, respondent, violation location, charges and current OATH status.

2. Preserve evidence

Gather permits, photographs, contracts, inspection records, professional letters and proof of correction that actually relate to the cited condition.

3. Separate hearing from correction

A hearing result and physical/agency correction are not always the same task. Plan both tracks where required.

Official Hearing Record

Verify the current hearing status and violation location in the NYC OATH Hearings Division Case Status data before relying on any public directory.

NYC OATH Case Status Data →

OATH evidence and DOB correction records

OATH advises respondents to bring or submit the evidence needed to prove their case, including legal or official records, photographs, documents and witnesses. For a DOB Certificate of Correction, DOB may require supporting material such as photographs, receipts, permits and inspection results in addition to the required correction information and applicable civil-penalty documentation.