What DOB is alleging at this property
This October hearing page is not just a schedule entry. The supplied DOB extract contains 2 summons records for this property identifier. The charge mix is: Certificate of Correction / Commissioner Order; Sidewalk Shed / Scaffold. The hearing date is October 29, 2026; the source issue date(s) are August 19, 2026, August 21, 2026.
Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.
Certificate of Correction / Commissioner Order — Summons 39201035Y
CLASS - 2 · Issued August 19, 2026; hearing October 29, 2026. · Hearing status: PENDING
DOB allegation in the source extract: AT TIME OF INSPECTION OBSERVED CORNICE WAS DETACHED BUT NOW REPAIRED ON ROOF LEVEL ON EXP # 1 BUT FAILURE TO SUBMIT CERTIFICATE OF CORRECTION OF VIOLATION #39093170L ISSUED ON 08-23-2023, FILE A CERTIFICATE OF
Cited provision(s): 263 — AC 28-204.4 FAIL TO COMPLY W/COMMISSIONER ORDER TO FILE CERT OF CORRECTION W/DOB
How this type of condition is typically resolved
This charge focuses on failure to complete or document the DOB correction process for an earlier summons. The practical task is usually to identify the underlying summons, confirm that its physical condition was actually corrected, and complete the current DOB Certificate of Correction requirements with the supporting proof and any applicable civil-penalty documentation.
Hearing issues to verify
- Was a Certificate of Correction already submitted or approved for the underlying summons before this charge was issued?
- Does DOB's record identify the same underlying summons number and correction deadline described in this citation?
- Was the physical condition actually corrected, and can that correction be tied to the cited condition rather than a different job or location?
Evidence that may matter
- DOB NOW / AEU Certificate of Correction submission or approval record
- Before-and-after photographs tied to the cited condition
- Permits, inspection results, contractor receipts or professional statements supporting the correction
- Proof of applicable DOB civil-penalty payment or waiver, if required
Sidewalk Shed / Scaffold — Summons 39558241R
CLASS - 2 · Issued August 21, 2026; hearing October 29, 2026. · Hearing status: PENDING
DOB allegation in the source extract: OBSERVED 5 STORY OCCUPIED BUILDING WITH SIDEWALK SHED ERECTED AT EXP 1. SIDEWALK SHED PERMIT IS EXPIRED 3/24/26, NO ACTIVE PERMIT ON FILE.
Cited provision(s): 2P8
How this type of condition is typically resolved
The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.
Hearing issues to verify
- Was the equipment covered by an active permit on the inspection date?
- Did the installed dimensions/protection match the approved design?
- Was a cited defect already corrected before the summons was issued or served?
Evidence that may matter
- DOB NOW equipment permit and approved drawings
- Engineer/contractor inspection logs
- Dated site photographs
- Renewal or removal records
Case-specific next step
For this property, the first paid review should reconcile the 2 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.
Submit These Summonses for Review