October 2026 NYC DOB / OATH Hearing — BIN 1064219

Manhattan property record with 5 OATH/ECB summons records in the supplied October 2026 hearing extract. Hearing date: October 22, 2026.

Need representation for this October hearing?

We can review the summons, agency record, correction status and available evidence; define the hearing strategy; prepare the authorized submission or appearance; and coordinate the underlying violation-resolution work separately where needed. Because hearing deadlines are fixed, substantive work begins after scope, authorization and payment.

Property / Hearing Identifiers

Primary hearing issue: Work Without a Permit

BoroughManhattan
BIN1064219
Block / Lot02175 / 0010
October Records5
Official violation location: Loading from NYC OATH public records…
Address is resolved from the OATH Hearings Division Case Status record for OATH ticket 039200644P (source ECB number 39200644P). BIN and block/lot remain shown below for verification.

October 2026 Hearing Records

OATH/ECB #HearingSeverityHearing statusBalanceAlleged conditionCode / section
39200637R
ACTIVE
October 22, 2026
10:30 AM
CLASS - 1 PENDING $2,500.00 ATOI AT EXPO #1 & #4, ELECTRICAL WORK WAS OBSERVED SERVING WALL-MOUNTED A/C UNIT. ELECTRICAL CONNECTIONS/SWITCHES WERE OBSERVED, INCLUDING AN ELECTRICAL CONNECTION SERVING A HOOD EXHAUST FAN. NO CORRESPONDING E 1C9 — 27-3018(B) ELECTRICAL WORK WITHOUT A PERMIT
39200635N
ACTIVE
October 22, 2026
8:30 AM
CLASS - 1 PENDING $2,500.00 ATOI OBSERVED FAIL TO MAINTAIN BUILDING #1, 5TH FLOOR: DAMAGED AND NON-OPERATIONAL EMERGENCY LIGHT OBSERVED. BUILDING #4672 1ST FLOOR: MISSING EMERGENCY LIGHT OBSERVED. EMERGENCY LIGHTING IS REQUIRED TO REMAIN 138 — 28-301.1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: LACK OF EMERGEN
39200638Z
ACTIVE
October 22, 2026
8:30 AM
CLASS - 1 PENDING $2,500.00 ATOI AT EXPO #1, AN UNAPPROVED/UNPERMITTED DAIKIN A/C CONDENSING UNIT WAS OBSERVED. REFRIGERANT LINES WERE OBSERVED PENETRATING THE WALL THROUGH A WINDOW OPENING WITHOUT EVIDENCE OF THE REQUIRED APPROVAL/PERMIT 101 — 28-105.1 WORK WITHOUT A PERMIT
39200636P
ACTIVE
October 22, 2026
9:30 AM
CLASS - 2 PENDING $1,250.00 ATO SEVERAL A/C WINDOW UNITS WERE OBSERVED AT EXPO #1 AND THE INNER COURTS THAT WERE UNSUPPORTED AND/OR UNSECURED. THIS CONDITION CREATES A FALL HAZARD TO PEDESTRIANS, TENANTS, AND ANYONE BELOW., REPAIR AND/OR 202 — 28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER
39200644P
ACTIVE
October 22, 2026
9:30 AM
CLASS - 1 PENDING $2,500.00 ATOI (2)ILLUMINATED SIGNS WERE OBSERVED AT EXPO #1 AND EXPO #4. "SANTOS GOURMET , DELI GROCERY" APPROX 20X2 FT EACH , DOB RECORDS INDICATE DISAPPROVED APPLICATIONS JOB #100448712 AND JOB #100448516 FOR SIGN INS 101 — 28-105.1 WORK WITHOUT A PERMIT

What DOB is alleging at this property

This October hearing page is not just a schedule entry. The supplied DOB extract contains 5 summons records for this property identifier. The charge mix is: 3 Work Without a Permit summonses; Public Assembly; Failure to Maintain. The hearing date is October 22, 2026; the source issue date(s) are August 14, 2026.

Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.

Work Without a Permit — Summons 39200637R

CLASS - 1 · Issued August 14, 2026; hearing October 22, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ATOI AT EXPO #1 & #4, ELECTRICAL WORK WAS OBSERVED SERVING WALL-MOUNTED A/C UNIT. ELECTRICAL CONNECTIONS/SWITCHES WERE OBSERVED, INCLUDING AN ELECTRICAL CONNECTION SERVING A HOOD EXHAUST FAN. NO CORRESPONDING E

Cited provision(s): 1C9 — 27-3018(B) ELECTRICAL WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Public Assembly — Summons 39200635N

CLASS - 1 · Issued August 14, 2026; hearing October 22, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ATOI OBSERVED FAIL TO MAINTAIN BUILDING #1, 5TH FLOOR: DAMAGED AND NON-OPERATIONAL EMERGENCY LIGHT OBSERVED. BUILDING #4672 1ST FLOOR: MISSING EMERGENCY LIGHT OBSERVED. EMERGENCY LIGHTING IS REQUIRED TO REMAIN

Cited provision(s): 138 — 28-301.1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: LACK OF EMERGEN

How this type of condition is typically resolved

Public-assembly charges can require confirming lawful occupancy and capacity, obtaining or renewing the applicable Place of Assembly Certificate of Operation / FDNY permit, and correcting egress or life-safety deficiencies.

Hearing issues to verify

  • What occupancy/capacity was actually present on the cited date?
  • Was a valid Place of Assembly approval or permit already in effect?
  • Did the inspector cite a record defect or a physical life-safety condition?

Evidence that may matter

  • PACO / FDNY public-assembly permit
  • Certificate of Occupancy / floor plan
  • Occupant-count or event records
  • Egress/fire-protection inspection documentation

Work Without a Permit — Summons 39200638Z

CLASS - 1 · Issued August 14, 2026; hearing October 22, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ATOI AT EXPO #1, AN UNAPPROVED/UNPERMITTED DAIKIN A/C CONDENSING UNIT WAS OBSERVED. REFRIGERANT LINES WERE OBSERVED PENETRATING THE WALL THROUGH A WINDOW OPENING WITHOUT EVIDENCE OF THE REQUIRED APPROVAL/PERMIT

Cited provision(s): 101 — 28-105.1 WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Failure to Maintain — Summons 39200636P

CLASS - 2 · Issued August 14, 2026; hearing October 22, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ATO SEVERAL A/C WINDOW UNITS WERE OBSERVED AT EXPO #1 AND THE INNER COURTS THAT WERE UNSUPPORTED AND/OR UNSECURED. THIS CONDITION CREATES A FALL HAZARD TO PEDESTRIANS, TENANTS, AND ANYONE BELOW., REPAIR AND/OR

Cited provision(s): 202 — 28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER

How this type of condition is typically resolved

Failure-to-maintain charges are fact-specific. The owner should identify the exact building component or service equipment cited, repair the condition, and document the repair with evidence tied to the inspection location/date.

Hearing issues to verify

  • Does the description accurately identify the component, location and condition?
  • Was the condition already repaired or not present when the summons was issued?
  • Was another party responsible for maintenance under facts that are legally relevant to the respondent's liability?

Evidence that may matter

  • Dated before/after photographs
  • Repair invoices and contractor statements
  • Professional inspection/report when structural or technical conditions are involved
  • Maintenance logs and prior inspection records

Work Without a Permit — Summons 39200644P

CLASS - 1 · Issued August 14, 2026; hearing October 22, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ATOI (2)ILLUMINATED SIGNS WERE OBSERVED AT EXPO #1 AND EXPO #4. "SANTOS GOURMET , DELI GROCERY" APPROX 20X2 FT EACH , DOB RECORDS INDICATE DISAPPROVED APPLICATIONS JOB #100448712 AND JOB #100448516 FOR SIGN INS

Cited provision(s): 101 — 28-105.1 WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Case-specific next step

For this property, the first paid review should reconcile the 5 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.

Submit These Summonses for Review

What to do before the hearing

1. Verify the summons

Confirm the scheduled date, respondent, violation location, charges and current OATH status.

2. Preserve evidence

Gather permits, photographs, contracts, inspection records, professional letters and proof of correction that actually relate to the cited condition.

3. Separate hearing from correction

A hearing result and physical/agency correction are not always the same task. Plan both tracks where required.

Official Hearing Record

Verify the current hearing status and violation location in the NYC OATH Hearings Division Case Status data before relying on any public directory.

NYC OATH Case Status Data →

OATH evidence and DOB correction records

OATH advises respondents to bring or submit the evidence needed to prove their case, including legal or official records, photographs, documents and witnesses. For a DOB Certificate of Correction, DOB may require supporting material such as photographs, receipts, permits and inspection results in addition to the required correction information and applicable civil-penalty documentation.