What DOB is alleging at this property
This October hearing page is not just a schedule entry. The supplied DOB extract contains 3 summons records for this property identifier. The charge mix is: 3 Sidewalk Shed / Scaffold summonses. The hearing dates are October 16, 2026, October 2, 2026, October 23, 2026; the source issue date(s) are August 11, 2026, February 26, 2026.
Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.
Sidewalk Shed / Scaffold — Summons 35726412R
CLASS - 2 · Issued February 26, 2026; hearing October 2, 2026. · Hearing status: PENDING
DOB allegation in the source extract: TEMPORARY CONSTRUCTION EQUIPMENT OR INSTALLATION ON SITE-EXPIRED PERMIT. NOTE: AT TIME OF INSPECTION, I OBSERVED ELECTRICAL PERMIT FOR SIDEWALK SHED EXPIRED #Y158454 EXPIRED 08-22-2025(ABANDONED) OBSERVED NO VA
Cited provision(s): 207 — BC 105.8.2 TEMPORARY CONSTRUCTION EQUIPMENT ON SITE-EXPIRED PERMIT
How this type of condition is typically resolved
The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.
Hearing issues to verify
- Was the equipment covered by an active permit on the inspection date?
- Did the installed dimensions/protection match the approved design?
- Was a cited defect already corrected before the summons was issued or served?
Evidence that may matter
- DOB NOW equipment permit and approved drawings
- Engineer/contractor inspection logs
- Dated site photographs
- Renewal or removal records
Sidewalk Shed / Scaffold — Summons 39557787Y
CLASS - 2 · Issued August 11, 2026; hearing October 16, 2026. · Hearing status: PENDING
DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED 11-STORY BUILDING WITH SIDEWALK SHED AT EXPOSURES 1, 2, AND 4. NO WORK WAS OBSERVED. SHED PANELS WERE DETERIORATED AND LOOSE PANEL PIECES WERE OBSERVED ON THE GROUND. SHED POSTS
Cited provision(s): 223 — BC 3307.6,27-1021 SIDEWALK SHED DOES NOT MEET CODE SPECIFICATIONS
How this type of condition is typically resolved
The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.
Hearing issues to verify
- Was the equipment covered by an active permit on the inspection date?
- Did the installed dimensions/protection match the approved design?
- Was a cited defect already corrected before the summons was issued or served?
Evidence that may matter
- DOB NOW equipment permit and approved drawings
- Engineer/contractor inspection logs
- Dated site photographs
- Renewal or removal records
Sidewalk Shed / Scaffold — Summons 35726411P
CLASS - 2 · Issued February 26, 2026; hearing October 23, 2026. · Hearing status: PENDING
DOB allegation in the source extract: TEMP CONSTRUCTION EQUIP/INSTALLATION ON SITE EXPIRED PERMIT(SHED). NOTE: AT TIME OF INSPECTION, I OBSERVED SIDEWALK SHED PERMIT EXPIRED ON BISWEB RECORD #220161278-01-EQ-SH EXPIRED 10-11-2025 AND OBSERVED NO VA
Cited provision(s): 2P8
How this type of condition is typically resolved
The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.
Hearing issues to verify
- Was the equipment covered by an active permit on the inspection date?
- Did the installed dimensions/protection match the approved design?
- Was a cited defect already corrected before the summons was issued or served?
Evidence that may matter
- DOB NOW equipment permit and approved drawings
- Engineer/contractor inspection logs
- Dated site photographs
- Renewal or removal records
Case-specific next step
For this property, the first paid review should reconcile the 3 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.