What DOB is alleging at this property
This October hearing page is not just a schedule entry. The supplied DOB extract contains 2 summons records for this property identifier. The charge mix is: 2 Sidewalk Shed / Scaffold summonses. The hearing dates are October 2, 2026, October 30, 2026; the source issue date(s) are August 14, 2026, July 28, 2026.
Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.
Sidewalk Shed / Scaffold — Summons 39557132N
CLASS - 2 · Issued July 28, 2026; hearing October 2, 2026. · Hearing status: PENDING
DOB allegation in the source extract: 3 STORY BUILDING UNDER DEMOLITION CLOSED SITE OBSERVED JOBSITE FENCE X01193997 NOT PROPERLY MAINTAINED PER CODE EXP#1,2. MISSING PLEXI-GLASS ON MULTIPLE VIEWING PANELS 3307.7.3, ADVERTISING POSTERS, FENCE LEANI
Cited provision(s): 211 — BC 3307.7,27-1021(C) JOB SITE FENCE NOT CONSTRUCTED PURSUANT TO SUBSECTION
How this type of condition is typically resolved
The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.
Hearing issues to verify
- Was the equipment covered by an active permit on the inspection date?
- Did the installed dimensions/protection match the approved design?
- Was a cited defect already corrected before the summons was issued or served?
Evidence that may matter
- DOB NOW equipment permit and approved drawings
- Engineer/contractor inspection logs
- Dated site photographs
- Renewal or removal records
Sidewalk Shed / Scaffold — Summons 39557918P
CLASS - 2 · Issued August 14, 2026; hearing October 30, 2026. · Hearing status: PENDING
DOB allegation in the source extract: OBSERVED PORTIONS OF JOB SITE FENCE AT VACANT LOT FOR PROPOSED NEW BUILDING NOT MAINTAINED. SECTIONS LEANING INTO SIDEWALK OBSTRUCTING PEDESTRIAN PASSAGE. REQUIRED VIEWING/PLEXIGLASS PANELS MISSING, CREATING OP
Cited provision(s): 211 — BC 3307.7,27-1021(C) JOB SITE FENCE NOT CONSTRUCTED PURSUANT TO SUBSECTION
How this type of condition is typically resolved
The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.
Hearing issues to verify
- Was the equipment covered by an active permit on the inspection date?
- Did the installed dimensions/protection match the approved design?
- Was a cited defect already corrected before the summons was issued or served?
Evidence that may matter
- DOB NOW equipment permit and approved drawings
- Engineer/contractor inspection logs
- Dated site photographs
- Renewal or removal records
Case-specific next step
For this property, the first paid review should reconcile the 2 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.
Submit These Summonses for Review