Demolition — Summons 39558326X
DOB allegation in the source extract: AT THE TIME OF INSPECTION FOR DEMOLITION SIGN OFF OF THE ONE STORY BUILDING, DEMOLITION WORK WAS OBSERVED COMPLETE. UPON REVIEW OF DOB NOW NO DEMOLITION NOTIFICATION WAS FILED, FAILURE TO PROVIDE NOTIFICATION P
Cited provision(s): 116 — BC 3306.3,27-195 FAILURE TO PROVIDE REQUIRED NOTIFICATION PRIOR TO THE COMMENCEMENT OF
How this type of condition is typically resolved
Demolition charges can involve missing permits, missing notifications, unsafe demolition practices or work outside approved scope. Resolution requires identifying the exact procedural/safety failure and completing the missing filing or corrective work.
Hearing issues to verify
- Was a demolition permit or required notification in effect before work began?
- Did the cited activity constitute demolition under the applicable filing, or another permitted scope?
- Do contractor and agency records show the required notice was timely?
Evidence that may matter
- Demolition permit and DOB NOW filing history
- Required notification confirmation / timestamp
- Asbestos/environmental documents
- Contractor logs, photographs and demolition sequence records