What DOB is alleging at this property
This October hearing page is not just a schedule entry. The supplied DOB extract contains 2 summons records for this property identifier. The charge mix is: Construction Fence; Sidewalk Shed / Scaffold. The hearing date is October 30, 2026; the source issue date(s) are August 26, 2026.
Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.
Construction Fence — Summons 39201856L
CLASS - 2 · Issued August 26, 2026; hearing October 30, 2026. · Hearing status: PENDING
DOB allegation in the source extract: TEMPORARY CONSTRUCTION EQUIPMENT ON SITE- EXPIRED PERMIT. I OBSERVED A PERIMETER CONSTRUCTION FENCE ERECTED UNDER FENCE PERMIT #220530780-01-EQ-FN. THE PERMIT EXPIRED ON 04/10/2025., RENEW PERMIT; SUBMIT THE CE
Cited provision(s): 207 — BC 105.8.2 TEMPORARY CONSTRUCTION EQUIPMENT ON SITE-EXPIRED PERMIT
How this type of condition is typically resolved
Construction-fence charges generally require bringing the fence, gates, viewing panels, height and site protection into compliance with the approved construction-safety setup and maintaining it for the required duration.
Hearing issues to verify
- Did the fence configuration on the inspection date match the approved/logistics plan?
- Was the cited opening or defect temporary and promptly corrected?
- Was a permit or construction-fence filing active where required?
Evidence that may matter
- Approved construction-fence/site logistics documents
- Dated photographs
- Contractor logs and correction invoice
- Permit/filing record
Sidewalk Shed / Scaffold — Summons 39201863J
CLASS - 2 · Issued August 26, 2026; hearing October 30, 2026. · Hearing status: PENDING
DOB allegation in the source extract: JOB SITE FENCE NOT CONSTRUCTED OR MAINTAINED PURSUANT TO SUBSECTION. I OBSERVED THE PERIMETER CONSTRUCTION FENCE UNDER PERMIT #220530780-01-EQ-FN DEFECTIVE WITH HOLES IN THE PANELS, BROKEN SECTIONS ON TOP AND B
Cited provision(s): 211 — BC 3307.7,27-1021(C) JOB SITE FENCE NOT CONSTRUCTED PURSUANT TO SUBSECTION
How this type of condition is typically resolved
The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.
Hearing issues to verify
- Was the equipment covered by an active permit on the inspection date?
- Did the installed dimensions/protection match the approved design?
- Was a cited defect already corrected before the summons was issued or served?
Evidence that may matter
- DOB NOW equipment permit and approved drawings
- Engineer/contractor inspection logs
- Dated site photographs
- Renewal or removal records
Case-specific next step
For this property, the first paid review should reconcile the 2 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.
Submit These Summonses for Review