What DOB is alleging at this property
This October hearing page is not just a schedule entry. The supplied DOB extract contains 2 summons records for this property identifier. The charge mix is: 2 Construction Fence summonses. The hearing date is October 16, 2026; the source issue date(s) are August 12, 2026.
Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.
Construction Fence — Summons 39200267Z
CLASS - 2 · Issued August 12, 2026; hearing October 16, 2026. · Hearing status: PENDING
DOB allegation in the source extract: TEMPORARY CONSTRUCTION EQUIPMENT OR INSTALLATION ON SITE AE" EXPIRES PERMIT. ATOI I OBSERVED AT EXPOSURE#1,2,4 CONSTRUCTION FENCE, PERMIT#X00821568-I1-FN EXPIRES ON O7/19/2024 STILL ERECTED, NEED TO RENEW PERMI
Cited provision(s): 207 — BC 105.8.2 TEMPORARY CONSTRUCTION EQUIPMENT ON SITE-EXPIRED PERMIT
How this type of condition is typically resolved
Construction-fence charges generally require bringing the fence, gates, viewing panels, height and site protection into compliance with the approved construction-safety setup and maintaining it for the required duration.
Hearing issues to verify
- Did the fence configuration on the inspection date match the approved/logistics plan?
- Was the cited opening or defect temporary and promptly corrected?
- Was a permit or construction-fence filing active where required?
Evidence that may matter
- Approved construction-fence/site logistics documents
- Dated photographs
- Contractor logs and correction invoice
- Permit/filing record
Construction Fence — Summons 39200293M
CLASS - 1 · Issued August 12, 2026; hearing October 16, 2026. · Hearing status: PENDING
DOB allegation in the source extract: FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. ATOI AT EXPOSURE#2,4, THE CONSTRUCTION FENCE IS LEANING OUTWARD ON TO THE ADJACENT PROPERTY, THE PLYWOOD IS WARPED IN VARIOUS AREA IN DANGER OF FULLING, NE
Cited provision(s): 102 — 28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER
How this type of condition is typically resolved
Construction-fence charges generally require bringing the fence, gates, viewing panels, height and site protection into compliance with the approved construction-safety setup and maintaining it for the required duration.
Hearing issues to verify
- Did the fence configuration on the inspection date match the approved/logistics plan?
- Was the cited opening or defect temporary and promptly corrected?
- Was a permit or construction-fence filing active where required?
Evidence that may matter
- Approved construction-fence/site logistics documents
- Dated photographs
- Contractor logs and correction invoice
- Permit/filing record
Case-specific next step
For this property, the first paid review should reconcile the 2 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.
Submit These Summonses for Review