What DOB is alleging at this property
This October hearing page is not just a schedule entry. The supplied DOB extract contains 4 summons records for this property identifier. The charge mix is: 2 Stop Work Order summonses; 2 Certificate of Correction / Commissioner Order summonses. The hearing date is October 26, 2026; the source issue date(s) are June 8, 2026, May 15, 2025.
Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.
Stop Work Order — Summons 39148145P
CLASS - 1 · Issued May 15, 2025; hearing October 26, 2026. · Hearing status: PENDING
DOB allegation in the source extract: ATOI OBSERVED PSWO STICKER REMOVED FROM FRONT DOOR WITHOUT GETTING RESCINDED, COMPLY WITH CODE
Cited provision(s): 1F8 — 28-207.2.5 TAMPERED WITH, REMOVED OR DEFACED A WRITTEN STOP WORK ORDER
How this type of condition is typically resolved
An active Stop Work Order has to be treated separately from the underlying summons. The cited unsafe or unpermitted condition must be corrected or legalized, required permits/penalties addressed, and the issuing agency must formally rescind or modify the order before prohibited work resumes.
Hearing issues to verify
- What exact work was covered by the Stop Work Order: all work or only part of the project?
- Was the activity observed after the order actually prohibited work, or was it authorized safety / emergency / corrective work?
- Was the Stop Work Order already rescinded or modified before the activity alleged in the summons?
Evidence that may matter
- Copy of the Stop Work Order and any rescission/modification notice
- DOB permit records and inspector correspondence
- Daily logs, photographs and contractor records showing when work stopped or resumed
- Evidence identifying any limited corrective/safety work performed
Stop Work Order — Summons 39148146R
CLASS - 1 · Issued May 15, 2025; hearing October 26, 2026. · Hearing status: PENDING
DOB allegation in the source extract: ACCORDING TO DOB RECORDS COMMERCIAL PROPERTY AT 796B HAD THE PSWO ISSUED ON 10/25/2025 BUT CONTINUED TO WORK AND FINISHED THE PROJECT, COMPLY WITH STOP WORK ORDER
Cited provision(s): 112 — 28-207.2.2 UNLAWFULLY CONTINUED WORK WHILE NOTICE OF A STOP WORK ORDER
How this type of condition is typically resolved
An active Stop Work Order has to be treated separately from the underlying summons. The cited unsafe or unpermitted condition must be corrected or legalized, required permits/penalties addressed, and the issuing agency must formally rescind or modify the order before prohibited work resumes.
Hearing issues to verify
- What exact work was covered by the Stop Work Order: all work or only part of the project?
- Was the activity observed after the order actually prohibited work, or was it authorized safety / emergency / corrective work?
- Was the Stop Work Order already rescinded or modified before the activity alleged in the summons?
Evidence that may matter
- Copy of the Stop Work Order and any rescission/modification notice
- DOB permit records and inspector correspondence
- Daily logs, photographs and contractor records showing when work stopped or resumed
- Evidence identifying any limited corrective/safety work performed
Certificate of Correction / Commissioner Order — Summons 39191665M
CLASS - 2 · Issued June 8, 2026; hearing October 26, 2026. · Hearing status: PENDING
DOB allegation in the source extract: FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPT OF BUILDINGS FOR SUMMONS 39148145P, FILE A CERTIFICATE OF CORRECTION
Cited provision(s): 263 — AC 28-204.4 FAIL TO COMPLY W/COMMISSIONER ORDER TO FILE CERT OF CORRECTION W/DOB
How this type of condition is typically resolved
This charge focuses on failure to complete or document the DOB correction process for an earlier summons. The practical task is usually to identify the underlying summons, confirm that its physical condition was actually corrected, and complete the current DOB Certificate of Correction requirements with the supporting proof and any applicable civil-penalty documentation.
Hearing issues to verify
- Was a Certificate of Correction already submitted or approved for the underlying summons before this charge was issued?
- Does DOB's record identify the same underlying summons number and correction deadline described in this citation?
- Was the physical condition actually corrected, and can that correction be tied to the cited condition rather than a different job or location?
Evidence that may matter
- DOB NOW / AEU Certificate of Correction submission or approval record
- Before-and-after photographs tied to the cited condition
- Permits, inspection results, contractor receipts or professional statements supporting the correction
- Proof of applicable DOB civil-penalty payment or waiver, if required
Certificate of Correction / Commissioner Order — Summons 39191666Y
CLASS - 2 · Issued June 8, 2026; hearing October 26, 2026. · Hearing status: PENDING
DOB allegation in the source extract: FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPT OF BUILDINGS FOR SUMMONS 39148146R, FILE A CERTIFICATE OF CORRECTION
Cited provision(s): 263 — AC 28-204.4 FAIL TO COMPLY W/COMMISSIONER ORDER TO FILE CERT OF CORRECTION W/DOB
How this type of condition is typically resolved
This charge focuses on failure to complete or document the DOB correction process for an earlier summons. The practical task is usually to identify the underlying summons, confirm that its physical condition was actually corrected, and complete the current DOB Certificate of Correction requirements with the supporting proof and any applicable civil-penalty documentation.
Hearing issues to verify
- Was a Certificate of Correction already submitted or approved for the underlying summons before this charge was issued?
- Does DOB's record identify the same underlying summons number and correction deadline described in this citation?
- Was the physical condition actually corrected, and can that correction be tied to the cited condition rather than a different job or location?
Evidence that may matter
- DOB NOW / AEU Certificate of Correction submission or approval record
- Before-and-after photographs tied to the cited condition
- Permits, inspection results, contractor receipts or professional statements supporting the correction
- Proof of applicable DOB civil-penalty payment or waiver, if required
Case-specific next step
For this property, the first paid review should reconcile the 4 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.
Submit These Summonses for Review