Brooklyn property record with 9 OATH/ECB summons records in the supplied October 2026 hearing extract. Hearing date: October 7, 2026.

Need representation for this October hearing?

We can review the summons, agency record, correction status and available evidence; define the hearing strategy; prepare the authorized submission or appearance; and coordinate the underlying violation-resolution work separately where needed. Because hearing deadlines are fixed, substantive work begins after scope, authorization and payment.

Property / Hearing Identifiers

Primary hearing issue: Demolition

BoroughBrooklyn
BIN3057847
Block / Lot02020 / 0001
October Records9
Official violation location: Loading from NYC OATH public records…
Address is resolved from the OATH Hearings Division Case Status record for OATH ticket 039557313M (source ECB number 39557313M). BIN and block/lot remain shown below for verification.

October 2026 Hearing Records

OATH/ECB #HearingSeverityHearing statusBalanceAlleged conditionCode / section
39557310R
ACTIVE
October 7, 2026
10:30 AM
CLASS - 1 PENDING $5,000.00 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE, LARGE AMOUNT OF DEMOLITION DEBRIS WITH SHEETROCK, WOOD PLANKS, INSTALLATION AND PAPERS WERE ALL PILE UP. FAILURE TO REMOVE 1P7
39557313M
ACTIVE
October 7, 2026
10:30 AM
CLASS - 1 PENDING $2,500.00 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS, FIRE HYDRANT AT EXPOSURE #2 WITH HOSE CONNECTED TO JOBSITE, UPON REQUEST FOR DEP PERMIT TO USED FIRE HYDRANT 106 — 27-/28-/BC-MISC MISCELLANEOUS VIOLATIONS
39557339K
ACTIVE
October 7, 2026
10:30 AM
CLASS - 1 PENDING $5,000.00 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS ON SITE, 2 WORKERS ON SUPPORTED PIPE SCAFFOLD WITH NO GUARDRAILS, NO SCREW JACKS NO BASEPLATES AND THEY WERE 1P7
39557311Z
ACTIVE
October 7, 2026
8:30 AM
CLASS - 1 PENDING $5,000.00 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, FULL DEMOLITION, I OBSERVED SIDEWALK SHED AND CONSTRUCTION FENCE INSTALLED AT EXPOSURE #1 AND 2, UPON REQUEST FOR DOT PERMIT TO OCCUPY AND CROSS SIDEWALK NONE 1P7
39557314Y
ACTIVE
October 7, 2026
8:30 AM
CLASS - 1 PENDING $5,000.00 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS ON SITE. OXYGEN AND ACETYLENE TANKS WITH HOSE WAS NOT SECURED, UPON REQUEST FOR FDNY PERMIT NONE WAS PRESENTE 1P7
39557337R
ACTIVE
October 7, 2026
8:30 AM
CLASS - 2 PENDING $5,000.00 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS ON SITE AND AT EXPOSURE #3 A FREE STANDING WALL WAS LEFT IN PLACE IN DANGER OF COLLAPSING. FAILURE TO REMOVED 209 — BC 3301.2,27-1009(A) FAIL TO SAFEGUARD PERS/PROPERTY AFFECTED BY CONSTRUCTION OP
39557290Z
ACTIVE
October 7, 2026
9:30 AM
CLASS - 1 PENDING $2,500.00 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING FOR FULL DEMOLITION AND 1ST FLOOR PARTIALLY DEMO, I OBSERVED LARGE EXCAVATOR ON FOOT PRINT OF BUILDING ON TOP OF BASEMENT/CELLAR, UPON REVIEW OF THE DEPARTMENT 101 — 28-105.1 WORK WITHOUT A PERMIT
39557312K
ACTIVE
October 7, 2026
9:30 AM
CLASS - 1 PENDING $5,000.00 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS ON SITE. UPON REQUEST FOR SITE SAFETY ORIENTATION AND REFRESHER NONE WAS PRESENTED OR AT JOBSITE. FAILURE TO 1J4 — BC 3301.11.1 AND 2 PERMIT HOLDER FAILED TO ENSURE WORKERS RECEIVE SITE SAFETY ORIENTATION
39557338Z
ACTIVE
October 7, 2026
9:30 AM
CLASS - 1 PENDING $2,500.00 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS ON SITE AND LARGE EXCAVATOR IN USED, UPON REQUEST FOR CERTIFICATION TO OPERATE IT WAS EXPIRED. FAILURE TO PRO 1F1 — BC 3301.1.3 (2014 CODE) FAILURE TO COMPLY WITH MANUFACTURER SPECIFICATIONS

What DOB is alleging at this property

This October hearing page is not just a schedule entry. The supplied DOB extract contains 9 summons records for this property identifier. The charge mix is: 4 Demolition summonses; 2 Sidewalk Shed / Scaffold summonses; 2 Site Safety / Safeguarding summonses; Work Without a Permit. The hearing date is October 7, 2026; the source issue date(s) are July 30, 2026.

Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.

Demolition — Summons 39557310R

CLASS - 1 · Issued July 30, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE, LARGE AMOUNT OF DEMOLITION DEBRIS WITH SHEETROCK, WOOD PLANKS, INSTALLATION AND PAPERS WERE ALL PILE UP. FAILURE TO REMOVE

Cited provision(s): 1P7

How this type of condition is typically resolved

Demolition charges can involve missing permits, missing notifications, unsafe demolition practices or work outside approved scope. Resolution requires identifying the exact procedural/safety failure and completing the missing filing or corrective work.

Hearing issues to verify

  • Was a demolition permit or required notification in effect before work began?
  • Did the cited activity constitute demolition under the applicable filing, or another permitted scope?
  • Do contractor and agency records show the required notice was timely?

Evidence that may matter

  • Demolition permit and DOB NOW filing history
  • Required notification confirmation / timestamp
  • Asbestos/environmental documents
  • Contractor logs, photographs and demolition sequence records

Demolition — Summons 39557313M

CLASS - 1 · Issued July 30, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS, FIRE HYDRANT AT EXPOSURE #2 WITH HOSE CONNECTED TO JOBSITE, UPON REQUEST FOR DEP PERMIT TO USED FIRE HYDRANT

Cited provision(s): 106 — 27-/28-/BC-MISC MISCELLANEOUS VIOLATIONS

How this type of condition is typically resolved

Demolition charges can involve missing permits, missing notifications, unsafe demolition practices or work outside approved scope. Resolution requires identifying the exact procedural/safety failure and completing the missing filing or corrective work.

Hearing issues to verify

  • Was a demolition permit or required notification in effect before work began?
  • Did the cited activity constitute demolition under the applicable filing, or another permitted scope?
  • Do contractor and agency records show the required notice was timely?

Evidence that may matter

  • Demolition permit and DOB NOW filing history
  • Required notification confirmation / timestamp
  • Asbestos/environmental documents
  • Contractor logs, photographs and demolition sequence records

Sidewalk Shed / Scaffold — Summons 39557339K

CLASS - 1 · Issued July 30, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS ON SITE, 2 WORKERS ON SUPPORTED PIPE SCAFFOLD WITH NO GUARDRAILS, NO SCREW JACKS NO BASEPLATES AND THEY WERE

Cited provision(s): 1P7

How this type of condition is typically resolved

The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.

Hearing issues to verify

  • Was the equipment covered by an active permit on the inspection date?
  • Did the installed dimensions/protection match the approved design?
  • Was a cited defect already corrected before the summons was issued or served?

Evidence that may matter

  • DOB NOW equipment permit and approved drawings
  • Engineer/contractor inspection logs
  • Dated site photographs
  • Renewal or removal records

Sidewalk Shed / Scaffold — Summons 39557311Z

CLASS - 1 · Issued July 30, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, FULL DEMOLITION, I OBSERVED SIDEWALK SHED AND CONSTRUCTION FENCE INSTALLED AT EXPOSURE #1 AND 2, UPON REQUEST FOR DOT PERMIT TO OCCUPY AND CROSS SIDEWALK NONE

Cited provision(s): 1P7

How this type of condition is typically resolved

The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.

Hearing issues to verify

  • Was the equipment covered by an active permit on the inspection date?
  • Did the installed dimensions/protection match the approved design?
  • Was a cited defect already corrected before the summons was issued or served?

Evidence that may matter

  • DOB NOW equipment permit and approved drawings
  • Engineer/contractor inspection logs
  • Dated site photographs
  • Renewal or removal records

Demolition — Summons 39557314Y

CLASS - 1 · Issued July 30, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS ON SITE. OXYGEN AND ACETYLENE TANKS WITH HOSE WAS NOT SECURED, UPON REQUEST FOR FDNY PERMIT NONE WAS PRESENTE

Cited provision(s): 1P7

How this type of condition is typically resolved

Demolition charges can involve missing permits, missing notifications, unsafe demolition practices or work outside approved scope. Resolution requires identifying the exact procedural/safety failure and completing the missing filing or corrective work.

Hearing issues to verify

  • Was a demolition permit or required notification in effect before work began?
  • Did the cited activity constitute demolition under the applicable filing, or another permitted scope?
  • Do contractor and agency records show the required notice was timely?

Evidence that may matter

  • Demolition permit and DOB NOW filing history
  • Required notification confirmation / timestamp
  • Asbestos/environmental documents
  • Contractor logs, photographs and demolition sequence records

Site Safety / Safeguarding — Summons 39557337R

CLASS - 2 · Issued July 30, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS ON SITE AND AT EXPOSURE #3 A FREE STANDING WALL WAS LEFT IN PLACE IN DANGER OF COLLAPSING. FAILURE TO REMOVED

Cited provision(s): 209 — BC 3301.2,27-1009(A) FAIL TO SAFEGUARD PERS/PROPERTY AFFECTED BY CONSTRUCTION OP

How this type of condition is typically resolved

These charges focus on protection of workers, occupants, neighboring property or the public during construction. Correction normally requires fixing the specific unsafe condition, documenting required safety measures and keeping the required site records current.

Hearing issues to verify

  • What precise safety measure does the summons say was missing or inadequate?
  • Was the condition temporary and corrected before or during the inspection?
  • Did an approved site-safety plan or required site document address the cited condition?

Evidence that may matter

  • Site Safety Plan / logistics drawings
  • Daily safety logs and competent-person/site-safety records
  • Photographs taken around the inspection time
  • Contractor or safety-manager statements and correction records

Work Without a Permit — Summons 39557290Z

CLASS - 1 · Issued July 30, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING FOR FULL DEMOLITION AND 1ST FLOOR PARTIALLY DEMO, I OBSERVED LARGE EXCAVATOR ON FOOT PRINT OF BUILDING ON TOP OF BASEMENT/CELLAR, UPON REVIEW OF THE DEPARTMENT

Cited provision(s): 101 — 28-105.1 WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Site Safety / Safeguarding — Summons 39557312K

CLASS - 1 · Issued July 30, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS ON SITE. UPON REQUEST FOR SITE SAFETY ORIENTATION AND REFRESHER NONE WAS PRESENTED OR AT JOBSITE. FAILURE TO

Cited provision(s): 1J4 — BC 3301.11.1 AND 2 PERMIT HOLDER FAILED TO ENSURE WORKERS RECEIVE SITE SAFETY ORIENTATION

How this type of condition is typically resolved

These charges focus on protection of workers, occupants, neighboring property or the public during construction. Correction normally requires fixing the specific unsafe condition, documenting required safety measures and keeping the required site records current.

Hearing issues to verify

  • What precise safety measure does the summons say was missing or inadequate?
  • Was the condition temporary and corrected before or during the inspection?
  • Did an approved site-safety plan or required site document address the cited condition?

Evidence that may matter

  • Site Safety Plan / logistics drawings
  • Daily safety logs and competent-person/site-safety records
  • Photographs taken around the inspection time
  • Contractor or safety-manager statements and correction records

Demolition — Summons 39557338Z

CLASS - 1 · Issued July 30, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED ACTIVE DEMOLITION SITE WITH 6 WORKERS ON SITE AND LARGE EXCAVATOR IN USED, UPON REQUEST FOR CERTIFICATION TO OPERATE IT WAS EXPIRED. FAILURE TO PRO

Cited provision(s): 1F1 — BC 3301.1.3 (2014 CODE) FAILURE TO COMPLY WITH MANUFACTURER SPECIFICATIONS

How this type of condition is typically resolved

Demolition charges can involve missing permits, missing notifications, unsafe demolition practices or work outside approved scope. Resolution requires identifying the exact procedural/safety failure and completing the missing filing or corrective work.

Hearing issues to verify

  • Was a demolition permit or required notification in effect before work began?
  • Did the cited activity constitute demolition under the applicable filing, or another permitted scope?
  • Do contractor and agency records show the required notice was timely?

Evidence that may matter

  • Demolition permit and DOB NOW filing history
  • Required notification confirmation / timestamp
  • Asbestos/environmental documents
  • Contractor logs, photographs and demolition sequence records

Case-specific next step

For this property, the first paid review should reconcile the 9 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.

Submit These Summonses for Review

What to do before the hearing

1. Verify the summons

Confirm the scheduled date, respondent, violation location, charges and current OATH status.

2. Preserve evidence

Gather permits, photographs, contracts, inspection records, professional letters and proof of correction that actually relate to the cited condition.

3. Separate hearing from correction

A hearing result and physical/agency correction are not always the same task. Plan both tracks where required.

Official Hearing Record

Verify the current hearing status and violation location in the NYC OATH Hearings Division Case Status data before relying on any public directory.

NYC OATH Case Status Data →

OATH evidence and DOB correction records

OATH advises respondents to bring or submit the evidence needed to prove their case, including legal or official records, photographs, documents and witnesses. For a DOB Certificate of Correction, DOB may require supporting material such as photographs, receipts, permits and inspection results in addition to the required correction information and applicable civil-penalty documentation.