We can review the summons, agency record, correction status and available evidence; define the hearing strategy; prepare the authorized submission or appearance; and coordinate the underlying violation-resolution work separately where needed. Because hearing deadlines are fixed, substantive work begins after scope, authorization and payment.

Property / Hearing Identifiers

Primary hearing issue: Other Building / Code Compliance

BoroughBrooklyn
BIN3073452
Block / Lot03230 / 0013
October Records10
Official violation location: Loading from NYC OATH public records…
Address is resolved from the OATH Hearings Division Case Status record for OATH ticket 039557126R (source ECB number 39557126R). BIN and block/lot remain shown below for verification.

October 2026 Hearing Records

OATH/ECB #HearingSeverityHearing statusBalanceAlleged conditionCode / section
39557080K
ACTIVE
October 7, 2026
10:30 AM
CLASS - 1 PENDING $5,000.00 AT TIME OF INSPECTION, OBSERVED SUSPENDED SCAFFOLD NOT MAINTAINED IN A SAFE CONDITION. BOLTS WERE UNSECURED, SUSPENSION CABLES AND LIFELINES WERE NOT PROTECTED FROM ABRASION, REQUIRED PARAPET CLAMP DOCUMENTATIO 1P7
39557084H
ACTIVE
October 7, 2026
10:30 AM
CLASS - 2 PENDING $1,250.00 AT TIME OF INSPECTION, OBSERVED A PUMP JACK SCAFFOLD INSTALLED AT EXPOSURE 2. UPON REVIEW OF DEPARTMENT-APPROVED CONSTRUCTION DOCUMENTS AND DOCUMENTS MAINTAINED ON SITE, NO DETAILS FOR THE PUMP JACK SCAFFOLD WE 282 — 28-105.12.2 WRK DOESN'T CONFORM TO APPROV DOCS AND/OR APPROV AMENDMENTS
39557087N
ACTIVE
October 7, 2026
10:30 AM
CLASS - 2 PENDING $2,500.00 AT TIME OF INSPECTION, OBSERVED FAILURE TO ESTABLISH AND MAINTAIN THE REQUIRED CONTROLLED ACCESS ZONE WHERE PERIMETER PROTECTION HAD BEEN REMOVED, CONTRARY TO BC 3308.10. OPEN, UNPROTECTED BALCONIES REMAINED AC 2P7
39557127Z
ACTIVE
October 7, 2026
10:30 AM
CLASS - 1 PENDING $5,000.00 AT TIME OF INSPECTION, OBSERVED NO CONSTRUCTION SUPERINTENDENT ON SITE, AND THE CONSTRUCTION SUPERINTENDENT LOGBOOK CONTAINED NO RECORDED SIGN-IN TIME, NO RECORDED SIGN-OUT TIME, AND NO CONSTRUCTION SUPERINTEND 1P7
39557085J
ACTIVE
October 7, 2026
8:30 AM
CLASS - 1 PENDING $5,000.00 AT TIME OF INSPECTION, OBSERVED WORKERS USING AN INTERIOR SUPPORTED SCAFFOLD ERECTED WITHOUT REQUIRED BASE PLATES, MUDSILLS, FULLY PLANKED PLATFORMS, OR A GUARDRAIL SYSTEM, CONTRARY TO BC 3314.5.3. STOP ALL WOR 1P7
39557125P
ACTIVE
October 7, 2026
8:30 AM
CLASS - 2 PENDING $1,250.00 AT TIME OF INSPECTION, OBSERVED A SUSPENDED SCAFFOLD INSTALLED WITHOUT THE REQUIRED PERMIT AND SITE-SPECIFIC DESIGN DRAWINGS, CONTRARY TO AC 28-105.1 AND BC 3314.2. UPON REQUEST, NO PERMIT OR REQUIRED DESIGN DR 2L1 — 28-105.1 FAILURE TO OBTAIN A TEMPORARY CONSTRUCTION PERMIT PRIOR TO INSTALLATIO
39557082Y
ACTIVE
October 7, 2026
9:30 AM
CLASS - 2 PENDING $800.00 AT TIME OF INSPECTION, OBSERVED AN ADJUSTABLE SUSPENDED SCAFFOLD INSTALLED WITHOUT THE REQUIRED DEPARTMENT NOTIFICATION SUBMITTED PRIOR TO INSTALLATION, CONTRARY TO BC 3314.4.1.5. SUBMIT THE REQUIRED NOTIFICATI 261 — BC 3314.1.1 & 27-1050.1 FAILED TO NOTIFY DEPARTMENT/OBTAIN PERMIT PRIOR TO USE/INST. OFF C-HOO
39557086L
ACTIVE
October 7, 2026
9:30 AM
CLASS - 2 PENDING $5,000.00 AT TIME OF INSPECTION, OBSERVED FAILURE TO ESTABLISH AND MAINTAIN A CONTROLLED ACCESS ZONE AT EXPOSURE 4 IN LIEU OF REQUIRED OVERHEAD PROTECTION, CONTRARY TO BC 3309.1. PERSONS WERE OBSERVED REMOVING GARBAGE AN 2P3
39557126R
ACTIVE
October 7, 2026
9:30 AM
CLASS - 1 PENDING $5,000.00 AT TIME OF INSPECTION, OBSERVED WORKERS PERFORMING WORK AT UNPROTECTED LEADING EDGES AND PLATFORMS EXCEEDING 6 FEET ABOVE A LOWER LEVEL WITHOUT THE REQUIRED GUARDRAIL SYSTEM, CONTRARY TO BC 3315.1.5. THE CONDIT 1P7
39199491H
ACTIVE
October 21, 2026
10:30 AM
CLASS - 1 PENDING $10,000.00 ATOI OBSERVED WORK IN PROGRESS AT EXTERIOR OF PROPERTY EXP 2. 4 MEN WORKING ON SUSPENDED SCAFFOLD DOING EIFS / FACADE WORK. PROPERTY HAS A SWO ISSUED FOR SUSPENDED SCAFFOLD UNDER SUMMON # - 39557125P. PSWO ISSU 112 — 28-207.2.2 UNLAWFULLY CONTINUED WORK WHILE NOTICE OF A STOP WORK ORDER

What DOB is alleging at this property

This October hearing page is not just a schedule entry. The supplied DOB extract contains 10 summons records for this property identifier. The charge mix is: 4 Other Building / Code Compliance summonses; 3 Sidewalk Shed / Scaffold summonses; 2 Work Without a Permit summonses; Stop Work Order. The hearing dates are October 21, 2026, October 7, 2026; the source issue date(s) are August 6, 2026, July 27, 2026.

Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.

Sidewalk Shed / Scaffold — Summons 39557080K

CLASS - 1 · Issued July 27, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED SUSPENDED SCAFFOLD NOT MAINTAINED IN A SAFE CONDITION. BOLTS WERE UNSECURED, SUSPENSION CABLES AND LIFELINES WERE NOT PROTECTED FROM ABRASION, REQUIRED PARAPET CLAMP DOCUMENTATIO

Cited provision(s): 1P7

How this type of condition is typically resolved

The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.

Hearing issues to verify

  • Was the equipment covered by an active permit on the inspection date?
  • Did the installed dimensions/protection match the approved design?
  • Was a cited defect already corrected before the summons was issued or served?

Evidence that may matter

  • DOB NOW equipment permit and approved drawings
  • Engineer/contractor inspection logs
  • Dated site photographs
  • Renewal or removal records

Work Without a Permit — Summons 39557084H

CLASS - 2 · Issued July 27, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED A PUMP JACK SCAFFOLD INSTALLED AT EXPOSURE 2. UPON REVIEW OF DEPARTMENT-APPROVED CONSTRUCTION DOCUMENTS AND DOCUMENTS MAINTAINED ON SITE, NO DETAILS FOR THE PUMP JACK SCAFFOLD WE

Cited provision(s): 282 — 28-105.12.2 WRK DOESN'T CONFORM TO APPROV DOCS AND/OR APPROV AMENDMENTS

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Other Building / Code Compliance — Summons 39557087N

CLASS - 2 · Issued July 27, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED FAILURE TO ESTABLISH AND MAINTAIN THE REQUIRED CONTROLLED ACCESS ZONE WHERE PERIMETER PROTECTION HAD BEEN REMOVED, CONTRARY TO BC 3308.10. OPEN, UNPROTECTED BALCONIES REMAINED AC

Cited provision(s): 2P7

How this type of condition is typically resolved

The first step is to read the inspector's narrative together with every cited code section and determine exactly what act, condition or missing filing DOB alleges. The correction and hearing strategy should then be built around that specific charge rather than a generic violation-removal checklist.

Hearing issues to verify

  • Does the summons identify the correct property, respondent, date and observed condition?
  • Do agency records support or contradict the inspector's description?
  • Was the condition corrected, permitted or otherwise resolved before the hearing?

Evidence that may matter

  • Official DOB/OATH property and summons records
  • Dated photographs and videos
  • Permits, approved plans and inspection results
  • Contracts, receipts, professional letters or witness statements tied to the cited condition

Other Building / Code Compliance — Summons 39557127Z

CLASS - 1 · Issued July 27, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED NO CONSTRUCTION SUPERINTENDENT ON SITE, AND THE CONSTRUCTION SUPERINTENDENT LOGBOOK CONTAINED NO RECORDED SIGN-IN TIME, NO RECORDED SIGN-OUT TIME, AND NO CONSTRUCTION SUPERINTEND

Cited provision(s): 1P7

How this type of condition is typically resolved

The first step is to read the inspector's narrative together with every cited code section and determine exactly what act, condition or missing filing DOB alleges. The correction and hearing strategy should then be built around that specific charge rather than a generic violation-removal checklist.

Hearing issues to verify

  • Does the summons identify the correct property, respondent, date and observed condition?
  • Do agency records support or contradict the inspector's description?
  • Was the condition corrected, permitted or otherwise resolved before the hearing?

Evidence that may matter

  • Official DOB/OATH property and summons records
  • Dated photographs and videos
  • Permits, approved plans and inspection results
  • Contracts, receipts, professional letters or witness statements tied to the cited condition

Sidewalk Shed / Scaffold — Summons 39557085J

CLASS - 1 · Issued July 27, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED WORKERS USING AN INTERIOR SUPPORTED SCAFFOLD ERECTED WITHOUT REQUIRED BASE PLATES, MUDSILLS, FULLY PLANKED PLATFORMS, OR A GUARDRAIL SYSTEM, CONTRARY TO BC 3314.5.3. STOP ALL WOR

Cited provision(s): 1P7

How this type of condition is typically resolved

The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.

Hearing issues to verify

  • Was the equipment covered by an active permit on the inspection date?
  • Did the installed dimensions/protection match the approved design?
  • Was a cited defect already corrected before the summons was issued or served?

Evidence that may matter

  • DOB NOW equipment permit and approved drawings
  • Engineer/contractor inspection logs
  • Dated site photographs
  • Renewal or removal records

Work Without a Permit — Summons 39557125P

CLASS - 2 · Issued July 27, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED A SUSPENDED SCAFFOLD INSTALLED WITHOUT THE REQUIRED PERMIT AND SITE-SPECIFIC DESIGN DRAWINGS, CONTRARY TO AC 28-105.1 AND BC 3314.2. UPON REQUEST, NO PERMIT OR REQUIRED DESIGN DR

Cited provision(s): 2L1 — 28-105.1 FAILURE TO OBTAIN A TEMPORARY CONSTRUCTION PERMIT PRIOR TO INSTALLATIO

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Sidewalk Shed / Scaffold — Summons 39557082Y

CLASS - 2 · Issued July 27, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED AN ADJUSTABLE SUSPENDED SCAFFOLD INSTALLED WITHOUT THE REQUIRED DEPARTMENT NOTIFICATION SUBMITTED PRIOR TO INSTALLATION, CONTRARY TO BC 3314.4.1.5. SUBMIT THE REQUIRED NOTIFICATI

Cited provision(s): 261 — BC 3314.1.1 & 27-1050.1 FAILED TO NOTIFY DEPARTMENT/OBTAIN PERMIT PRIOR TO USE/INST. OFF C-HOO

How this type of condition is typically resolved

The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.

Hearing issues to verify

  • Was the equipment covered by an active permit on the inspection date?
  • Did the installed dimensions/protection match the approved design?
  • Was a cited defect already corrected before the summons was issued or served?

Evidence that may matter

  • DOB NOW equipment permit and approved drawings
  • Engineer/contractor inspection logs
  • Dated site photographs
  • Renewal or removal records

Other Building / Code Compliance — Summons 39557086L

CLASS - 2 · Issued July 27, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED FAILURE TO ESTABLISH AND MAINTAIN A CONTROLLED ACCESS ZONE AT EXPOSURE 4 IN LIEU OF REQUIRED OVERHEAD PROTECTION, CONTRARY TO BC 3309.1. PERSONS WERE OBSERVED REMOVING GARBAGE AN

Cited provision(s): 2P3

How this type of condition is typically resolved

The first step is to read the inspector's narrative together with every cited code section and determine exactly what act, condition or missing filing DOB alleges. The correction and hearing strategy should then be built around that specific charge rather than a generic violation-removal checklist.

Hearing issues to verify

  • Does the summons identify the correct property, respondent, date and observed condition?
  • Do agency records support or contradict the inspector's description?
  • Was the condition corrected, permitted or otherwise resolved before the hearing?

Evidence that may matter

  • Official DOB/OATH property and summons records
  • Dated photographs and videos
  • Permits, approved plans and inspection results
  • Contracts, receipts, professional letters or witness statements tied to the cited condition

Other Building / Code Compliance — Summons 39557126R

CLASS - 1 · Issued July 27, 2026; hearing October 7, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED WORKERS PERFORMING WORK AT UNPROTECTED LEADING EDGES AND PLATFORMS EXCEEDING 6 FEET ABOVE A LOWER LEVEL WITHOUT THE REQUIRED GUARDRAIL SYSTEM, CONTRARY TO BC 3315.1.5. THE CONDIT

Cited provision(s): 1P7

How this type of condition is typically resolved

The first step is to read the inspector's narrative together with every cited code section and determine exactly what act, condition or missing filing DOB alleges. The correction and hearing strategy should then be built around that specific charge rather than a generic violation-removal checklist.

Hearing issues to verify

  • Does the summons identify the correct property, respondent, date and observed condition?
  • Do agency records support or contradict the inspector's description?
  • Was the condition corrected, permitted or otherwise resolved before the hearing?

Evidence that may matter

  • Official DOB/OATH property and summons records
  • Dated photographs and videos
  • Permits, approved plans and inspection results
  • Contracts, receipts, professional letters or witness statements tied to the cited condition

Stop Work Order — Summons 39199491H

CLASS - 1 · Issued August 6, 2026; hearing October 21, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ATOI OBSERVED WORK IN PROGRESS AT EXTERIOR OF PROPERTY EXP 2. 4 MEN WORKING ON SUSPENDED SCAFFOLD DOING EIFS / FACADE WORK. PROPERTY HAS A SWO ISSUED FOR SUSPENDED SCAFFOLD UNDER SUMMON # - 39557125P. PSWO ISSU

Cited provision(s): 112 — 28-207.2.2 UNLAWFULLY CONTINUED WORK WHILE NOTICE OF A STOP WORK ORDER

How this type of condition is typically resolved

An active Stop Work Order has to be treated separately from the underlying summons. The cited unsafe or unpermitted condition must be corrected or legalized, required permits/penalties addressed, and the issuing agency must formally rescind or modify the order before prohibited work resumes.

Hearing issues to verify

  • What exact work was covered by the Stop Work Order: all work or only part of the project?
  • Was the activity observed after the order actually prohibited work, or was it authorized safety / emergency / corrective work?
  • Was the Stop Work Order already rescinded or modified before the activity alleged in the summons?

Evidence that may matter

  • Copy of the Stop Work Order and any rescission/modification notice
  • DOB permit records and inspector correspondence
  • Daily logs, photographs and contractor records showing when work stopped or resumed
  • Evidence identifying any limited corrective/safety work performed

Case-specific next step

For this property, the first paid review should reconcile the 10 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.

Submit These Summonses for Review

What to do before the hearing

1. Verify the summons

Confirm the scheduled date, respondent, violation location, charges and current OATH status.

2. Preserve evidence

Gather permits, photographs, contracts, inspection records, professional letters and proof of correction that actually relate to the cited condition.

3. Separate hearing from correction

A hearing result and physical/agency correction are not always the same task. Plan both tracks where required.

Official Hearing Record

Verify the current hearing status and violation location in the NYC OATH Hearings Division Case Status data before relying on any public directory.

NYC OATH Case Status Data →

OATH evidence and DOB correction records

OATH advises respondents to bring or submit the evidence needed to prove their case, including legal or official records, photographs, documents and witnesses. For a DOB Certificate of Correction, DOB may require supporting material such as photographs, receipts, permits and inspection results in addition to the required correction information and applicable civil-penalty documentation.