We can review the summons, agency record, correction status and available evidence; define the hearing strategy; prepare the authorized submission or appearance; and coordinate the underlying violation-resolution work separately where needed. Because hearing deadlines are fixed, substantive work begins after scope, authorization and payment.

Property / Hearing Identifiers

Primary hearing issue: Work Without a Permit

BoroughBrooklyn
BIN3079782
Block / Lot03436 / 0014
October Records7
Official violation location: Loading from NYC OATH public records…
Address is resolved from the OATH Hearings Division Case Status record for OATH ticket 039200966H (source ECB number 39200966H). BIN and block/lot remain shown below for verification.

October 2026 Hearing Records

OATH/ECB #HearingSeverityHearing statusBalanceAlleged conditionCode / section
39191472X
ACTIVE
October 19, 2026
8:30 AM
CLASS - 2 PENDING $1,250.00 AT TIME OF INSPECTION OBSERVED NEW ELECTRICAL WIRING WITH NEWLY INSTALLED ELECTRICAL PANEL IN CELLAR TO SUPPLY POWER, ALSO NOTED 6 SPLIT A/C UNITS INSTALLED AT ROOF/ REAR OF BUILDING WITH ELECTRICAL WORK NOT AU 2C4 — 27-3018(B) ELECTRICAL WORK WITHOUT A PERMIT
39191478R
ACTIVE
October 19, 2026
8:30 AM
CLASS - 1 PENDING $2,500.00 ATOI OBSERVED IN BASEMENT OIL FED BOILER IS DISCONNECT AND REPLACED WITH GAS WATER HEATERS THAT IS NOT PERMITTED, NEW GAS LINES WERE RAN FROM FRONT TO BACK OF BASEMENT,LAUNDRY ROOM WAS INSTALLED AND NOT PERMITT 101 — 28-105.1 WORK WITHOUT A PERMIT
39191860H
ACTIVE
October 19, 2026
8:30 AM
CLASS - 1 PENDING $2,500.00 ATOI WORK WITHOUT A PERMIT AT EXPO#3 2ND & 3RD FL FIRE ESCAPE OBSERVED UNAPPROVED/ UNPERMITTEDREMOVAL OF ELECTRIC CONNECTION OF CONDENSING UNITS WITHOUT REQUEIRED PERMIT,, OBTAIN PERMIT; STOP ALL ELECTRICAL WOR 101 — 28-105.1 WORK WITHOUT A PERMIT
39200967J
ACTIVE
October 28, 2026
10:30 AM
CLASS - 1 PENDING $2,500.00 AT TIME OF INSPECTION, OBSERVED NEW GAS KITCHEN AND BATHROOM LOCATED IN MIDDLE OF APARTMENTS. SCOPE OF WORK IS UNDOCUMENTED AND HAZARDOUS AS IT CAN LEAD TO LEAKS OR DAMAGE. ECB ISSUED FOR PLUMBING/GAS WORK WITH 101 — 28-105.1 WORK WITHOUT A PERMIT
39200968L
ACTIVE
October 28, 2026
8:30 AM
CLASS - 2 PENDING $1,250.00 AT TIME OF INSPECTION, OBSERVED EGRESS DOOR OF APARTMENT 1R HAS BEEN JAMMED AND CANNOT OPEN DUE TO WATER DAMAGE WARPING FLOOR. ECB ISSUED AS UNSAFE HAZARD FOR OCCUPANTS HAVE BEEN CREATED DUE TO OBSERVED CONDITI 202 — 28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER
39200966H
ACTIVE
October 28, 2026
9:30 AM
CLASS - 1 PENDING $2,500.00 AT TIME OF INSPECTION, OBSERVED NEW LAYOUT OF FLOOR TO CEILING PARTITIONS IN MULTIPLE APARTMENTS. SCOPE OF WORK IS UNDOCUMENTED AND UNPERMITTED. ECB ISSUED FOR CONSTRUCTION WORK WITHOUT A PERMIT., OBTAIN PERMIT 101 — 28-105.1 WORK WITHOUT A PERMIT
39200972Y
ACTIVE
October 28, 2026
9:30 AM
CLASS - 1 PENDING $2,500.00 AT TIME OF INSPECTION, OBSERVED ADDITIONAL ROOM ADDED TO EACH APARTMENT THRU OUT BUILDING. ECB ISSUED AS BUILDING IS NO LONGER MATCHING DOCUMENTED LAYOUT OF EACH FLOOR AND APARTMENTS ARE FOUND TO BE OCCUPANCY C 103 — 28-118.3.2 OCC CONTRARY TO THAT ALLOWED BY THE C OF O OR DOB RECORDS

What DOB is alleging at this property

This October hearing page is not just a schedule entry. The supplied DOB extract contains 7 summons records for this property identifier. The charge mix is: 5 Work Without a Permit summonses; Egress / Exit Obstruction; Illegal Occupancy / Conversion. The hearing dates are October 19, 2026, October 28, 2026; the source issue date(s) are August 18, 2026, June 5, 2026, June 9, 2026.

Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.

Work Without a Permit — Summons 39191472X

CLASS - 2 · Issued June 5, 2026; hearing October 19, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION OBSERVED NEW ELECTRICAL WIRING WITH NEWLY INSTALLED ELECTRICAL PANEL IN CELLAR TO SUPPLY POWER, ALSO NOTED 6 SPLIT A/C UNITS INSTALLED AT ROOF/ REAR OF BUILDING WITH ELECTRICAL WORK NOT AU

Cited provision(s): 2C4 — 27-3018(B) ELECTRICAL WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Work Without a Permit — Summons 39191478R

CLASS - 1 · Issued June 5, 2026; hearing October 19, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ATOI OBSERVED IN BASEMENT OIL FED BOILER IS DISCONNECT AND REPLACED WITH GAS WATER HEATERS THAT IS NOT PERMITTED, NEW GAS LINES WERE RAN FROM FRONT TO BACK OF BASEMENT,LAUNDRY ROOM WAS INSTALLED AND NOT PERMITT

Cited provision(s): 101 — 28-105.1 WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Work Without a Permit — Summons 39191860H

CLASS - 1 · Issued June 9, 2026; hearing October 19, 2026. · Hearing status: PENDING

DOB allegation in the source extract: ATOI WORK WITHOUT A PERMIT AT EXPO#3 2ND & 3RD FL FIRE ESCAPE OBSERVED UNAPPROVED/ UNPERMITTEDREMOVAL OF ELECTRIC CONNECTION OF CONDENSING UNITS WITHOUT REQUEIRED PERMIT,, OBTAIN PERMIT; STOP ALL ELECTRICAL WOR

Cited provision(s): 101 — 28-105.1 WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Work Without a Permit — Summons 39200967J

CLASS - 1 · Issued August 18, 2026; hearing October 28, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED NEW GAS KITCHEN AND BATHROOM LOCATED IN MIDDLE OF APARTMENTS. SCOPE OF WORK IS UNDOCUMENTED AND HAZARDOUS AS IT CAN LEAD TO LEAKS OR DAMAGE. ECB ISSUED FOR PLUMBING/GAS WORK WITH

Cited provision(s): 101 — 28-105.1 WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Egress / Exit Obstruction — Summons 39200968L

CLASS - 2 · Issued August 18, 2026; hearing October 28, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED EGRESS DOOR OF APARTMENT 1R HAS BEEN JAMMED AND CANNOT OPEN DUE TO WATER DAMAGE WARPING FLOOR. ECB ISSUED AS UNSAFE HAZARD FOR OCCUPANTS HAVE BEEN CREATED DUE TO OBSERVED CONDITI

Cited provision(s): 202 — 28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER

How this type of condition is typically resolved

Egress charges are generally corrected by removing the obstruction or restoring the required exit width/path and then documenting that the means of egress is clear and code compliant.

Hearing issues to verify

  • Was the cited passageway actually required egress for the affected occupancy?
  • Did the alleged obstruction exist when the inspector observed it?
  • Was the condition immediately removed and can the timing be documented?

Evidence that may matter

  • Dated photographs showing the exit path
  • Approved floor/egress plans
  • Building or security logs
  • Statements or work records documenting removal of stored items/obstructions

Work Without a Permit — Summons 39200966H

CLASS - 1 · Issued August 18, 2026; hearing October 28, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED NEW LAYOUT OF FLOOR TO CEILING PARTITIONS IN MULTIPLE APARTMENTS. SCOPE OF WORK IS UNDOCUMENTED AND UNPERMITTED. ECB ISSUED FOR CONSTRUCTION WORK WITHOUT A PERMIT., OBTAIN PERMIT

Cited provision(s): 101 — 28-105.1 WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Illegal Occupancy / Conversion — Summons 39200972Y

CLASS - 1 · Issued August 18, 2026; hearing October 28, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED ADDITIONAL ROOM ADDED TO EACH APARTMENT THRU OUT BUILDING. ECB ISSUED AS BUILDING IS NO LONGER MATCHING DOCUMENTED LAYOUT OF EACH FLOOR AND APARTMENTS ARE FOUND TO BE OCCUPANCY C

Cited provision(s): 103 — 28-118.3.2 OCC CONTRARY TO THAT ALLOWED BY THE C OF O OR DOB RECORDS

How this type of condition is typically resolved

The key question is whether the observed occupancy or layout matches the lawful use of the premises. Resolution may require restoring the prior lawful layout/use or, when legally feasible, filing plans and obtaining approvals to legalize the condition.

Hearing issues to verify

  • What use and number of dwelling/occupancy units are shown by the Certificate of Occupancy, Schedule of Occupancy or other lawful-use records?
  • Did the inspector accurately identify how the space was being used on the cited date?
  • Was the cited space actually occupied as alleged, or were the observed beds, kitchens, locks or partitions consistent with another lawful use?
  • Is there an approved filing or historical record supporting the present use?

Evidence that may matter

  • Certificate of Occupancy / Schedule of Occupancy and approved plans
  • Historic occupancy records, permits and prior approved layouts
  • Dated photographs and floor plans
  • Leases, tenant records or sworn statements concerning actual use
  • Permits/inspection records if the condition was legalized or restored

Case-specific next step

For this property, the first paid review should reconcile the 7 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.

Submit These Summonses for Review

What to do before the hearing

1. Verify the summons

Confirm the scheduled date, respondent, violation location, charges and current OATH status.

2. Preserve evidence

Gather permits, photographs, contracts, inspection records, professional letters and proof of correction that actually relate to the cited condition.

3. Separate hearing from correction

A hearing result and physical/agency correction are not always the same task. Plan both tracks where required.

Official Hearing Record

Verify the current hearing status and violation location in the NYC OATH Hearings Division Case Status data before relying on any public directory.

NYC OATH Case Status Data →

OATH evidence and DOB correction records

OATH advises respondents to bring or submit the evidence needed to prove their case, including legal or official records, photographs, documents and witnesses. For a DOB Certificate of Correction, DOB may require supporting material such as photographs, receipts, permits and inspection results in addition to the required correction information and applicable civil-penalty documentation.