BuildingViolation.com

October 2026 NYC DOB / OATH Hearing — BIN 3116662

Brooklyn property record with 3 OATH/ECB summons records in the supplied October 2026 hearing extract. Hearing date: October 21, 2026.

Need representation for this October hearing?

We can review the summons, agency record, correction status and available evidence; define the hearing strategy; prepare the authorized submission or appearance; and coordinate the underlying violation-resolution work separately where needed. Because hearing deadlines are fixed, substantive work begins after scope, authorization and payment.

Property / Hearing Identifiers

Primary hearing issue: Sidewalk Shed / Scaffold

BoroughBrooklyn
BIN3116662
Block / Lot05084 / 0097
October Records3
Official violation location: Loading from NYC OATH public records…
Address is resolved from the OATH Hearings Division Case Status record for OATH ticket 039557927R (source ECB number 39557927R). BIN and block/lot remain shown below for verification.

October 2026 Hearing Records

OATH/ECB #HearingSeverityHearing statusBalanceAlleged conditionCode / section
39557926P
ACTIVE
October 21, 2026
10:30 AM
CLASS - 1 PENDING $5,000.00 AT THE TIME OF MY INSPECTION OF A 6 STORY BUILDING, I OBSERVED DEBRIS CHUTE INSTALLED AT EXPOSURE #1, SUPPORTED PIPE SCAFFOLD AND SUSPENDED SCAFFOLD IN USED, UPON SCANNING 1 WORKER, WORKERS WALLET IT WAS EXPIRE 1K6 — BC 3321.1 FAILURE TO ENSURE EACH WORKER HAS SUCCESSFULLY COMPLETED THE REQUIRED
39557927R
ACTIVE
October 21, 2026
8:30 AM
CLASS - 1 PENDING $10,000.00 AT THE TIME OF MY INSPECTION OF A 6 STORY BUILDING, I OBSERVED DEBRIS CHUTE INSTALLED AT EXPOSURE #1, SUPPORTED PIPE SCAFFOLD AND SUSPENDED SCAFFOLD IN USED AND AT EXPOSURE #4 THERE WERE NO OVERHEAD PROTECTION 1P3
39557925N
ACTIVE
October 21, 2026
9:30 AM
CLASS - 1 PENDING $2,500.00 AT THE TIME OF MY INSPECTION OF A 6 STORY BUILDING, I OBSERVED DEBRIS CHUTE INSTALLED INSIDE OF PIPE SCAFFOLD AT EXPOSURE #1, UPON REVIEW OF THE APPROVED DOCUMENTS IT REVEAL THAT THERE SHOULD BE DEBRIS NETTING 182 — 28-105.12.2 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROV

What DOB is alleging at this property

This October hearing page is not just a schedule entry. The supplied DOB extract contains 3 summons records for this property identifier. The charge mix is: 2 Sidewalk Shed / Scaffold summonses; Work Without a Permit. The hearing date is October 21, 2026; the source issue date(s) are August 14, 2026.

Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.

Sidewalk Shed / Scaffold — Summons 39557926P

CLASS - 1 · Issued August 14, 2026; hearing October 21, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 6 STORY BUILDING, I OBSERVED DEBRIS CHUTE INSTALLED AT EXPOSURE #1, SUPPORTED PIPE SCAFFOLD AND SUSPENDED SCAFFOLD IN USED, UPON SCANNING 1 WORKER, WORKERS WALLET IT WAS EXPIRE

Cited provision(s): 1K6 — BC 3321.1 FAILURE TO ENSURE EACH WORKER HAS SUCCESSFULLY COMPLETED THE REQUIRED

How this type of condition is typically resolved

The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.

Hearing issues to verify

  • Was the equipment covered by an active permit on the inspection date?
  • Did the installed dimensions/protection match the approved design?
  • Was a cited defect already corrected before the summons was issued or served?

Evidence that may matter

  • DOB NOW equipment permit and approved drawings
  • Engineer/contractor inspection logs
  • Dated site photographs
  • Renewal or removal records

Sidewalk Shed / Scaffold — Summons 39557927R

CLASS - 1 · Issued August 14, 2026; hearing October 21, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 6 STORY BUILDING, I OBSERVED DEBRIS CHUTE INSTALLED AT EXPOSURE #1, SUPPORTED PIPE SCAFFOLD AND SUSPENDED SCAFFOLD IN USED AND AT EXPOSURE #4 THERE WERE NO OVERHEAD PROTECTION

Cited provision(s): 1P3

How this type of condition is typically resolved

The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.

Hearing issues to verify

  • Was the equipment covered by an active permit on the inspection date?
  • Did the installed dimensions/protection match the approved design?
  • Was a cited defect already corrected before the summons was issued or served?

Evidence that may matter

  • DOB NOW equipment permit and approved drawings
  • Engineer/contractor inspection logs
  • Dated site photographs
  • Renewal or removal records

Work Without a Permit — Summons 39557925N

CLASS - 1 · Issued August 14, 2026; hearing October 21, 2026. · Hearing status: PENDING

DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 6 STORY BUILDING, I OBSERVED DEBRIS CHUTE INSTALLED INSIDE OF PIPE SCAFFOLD AT EXPOSURE #1, UPON REVIEW OF THE APPROVED DOCUMENTS IT REVEAL THAT THERE SHOULD BE DEBRIS NETTING

Cited provision(s): 182 — 28-105.12.2 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROV

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Case-specific next step

For this property, the first paid review should reconcile the 3 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.

Submit These Summonses for Review

What to do before the hearing

1. Verify the summons

Confirm the scheduled date, respondent, violation location, charges and current OATH status.

2. Preserve evidence

Gather permits, photographs, contracts, inspection records, professional letters and proof of correction that actually relate to the cited condition.

3. Separate hearing from correction

A hearing result and physical/agency correction are not always the same task. Plan both tracks where required.

Official Hearing Record

Verify the current hearing status and violation location in the NYC OATH Hearings Division Case Status data before relying on any public directory.

NYC OATH Case Status Data →

OATH evidence and DOB correction records

OATH advises respondents to bring or submit the evidence needed to prove their case, including legal or official records, photographs, documents and witnesses. For a DOB Certificate of Correction, DOB may require supporting material such as photographs, receipts, permits and inspection results in addition to the required correction information and applicable civil-penalty documentation.