What DOB is alleging at this property
This October hearing page is not just a schedule entry. The supplied DOB extract contains 4 summons records for this property identifier. The charge mix is: 3 Work Without a Permit summonses; Sidewalk Shed / Scaffold. The hearing date is October 28, 2026; the source issue date(s) are August 18, 2026.
Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.
Sidewalk Shed / Scaffold — Summons 39200903K
CLASS - 2 · Issued August 18, 2026; hearing October 28, 2026. · Hearing status: PENDING
DOB allegation in the source extract: ATOI OBSERVED SIDEWALK SHED PROJECT INFORMATION PANEL / PARAPET PANEL / CONSTRUCTION SIGN NOT PROVIDED OR NOT IN COMPLIANCE., COMPLY WITH CODE; POST REQUIERED INFO PANEL AND FILE COC
Cited provision(s): 217 — BC 3301.9,27-10009(C) FAIL TO PROVIDE/POST SIGN(S) AT JB SITE PURSUANT TO SUBSEC
How this type of condition is typically resolved
The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.
Hearing issues to verify
- Was the equipment covered by an active permit on the inspection date?
- Did the installed dimensions/protection match the approved design?
- Was a cited defect already corrected before the summons was issued or served?
Evidence that may matter
- DOB NOW equipment permit and approved drawings
- Engineer/contractor inspection logs
- Dated site photographs
- Renewal or removal records
Work Without a Permit — Summons 39200906X
CLASS - 2 · Issued August 18, 2026; hearing October 28, 2026. · Hearing status: PENDING
DOB allegation in the source extract: ATOI OBSERVED SIDEWALK SHED ON SITE PERMIT #B01413172-I1-SH NOT POSTED ON SITE. POST PERMIT AND FILE COC., POST/PROPERLY POST PERMIT
Cited provision(s): 220 — §28-105.11 FAILURE TO POST PERMIT FOR WORK AT PREMISES
How this type of condition is typically resolved
The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.
Hearing issues to verify
- Did a valid permit already cover the exact work described by the inspector on the issue date?
- Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
- Do the approved drawings, permit scope and inspection history match the condition the inspector described?
- If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?
Evidence that may matter
- Permit and DOB NOW/BIS job records that predate the inspection
- Approved plans and amendments showing the cited work
- Dated photographs of the condition and construction stage
- Contracts, invoices and contractor statements establishing what work was actually performed
- Inspection / sign-off records if the work was subsequently legalized
Work Without a Permit — Summons 39200904M
CLASS - 2 · Issued August 18, 2026; hearing October 28, 2026. · Hearing status: PENDING
DOB allegation in the source extract: ATOI OBSERVED SIDEWALK SHED DOES NOT CONFORM TO APPROVED PLANS; SETBACK FROM BUILDING WALL DOES NOT MATCH; EGRESS PATH FROM FIRE ESCAPE NOT SHOWN; POST TO POST DISTANCES DO NOT MATCH PLAN., CONFORM WORK TO APPR
Cited provision(s): 282 — 28-105.12.2 WRK DOESN'T CONFORM TO APPROV DOCS AND/OR APPROV AMENDMENTS
How this type of condition is typically resolved
The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.
Hearing issues to verify
- Did a valid permit already cover the exact work described by the inspector on the issue date?
- Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
- Do the approved drawings, permit scope and inspection history match the condition the inspector described?
- If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?
Evidence that may matter
- Permit and DOB NOW/BIS job records that predate the inspection
- Approved plans and amendments showing the cited work
- Dated photographs of the condition and construction stage
- Contracts, invoices and contractor statements establishing what work was actually performed
- Inspection / sign-off records if the work was subsequently legalized
Work Without a Permit — Summons 39200905Y
CLASS - 2 · Issued August 18, 2026; hearing October 28, 2026. · Hearing status: PENDING
DOB allegation in the source extract: ATOI OBSERVED THE INSTALLED SIDEWALK SHED LIGHTING ELECTRICAL PERMIT#B01413173-I1-EL NOT POSTED ON SITE. POST PERMIT AND FILE COC., POST/PROPERLY POST PERMIT
Cited provision(s): 220 — §28-105.11 FAILURE TO POST PERMIT FOR WORK AT PREMISES
How this type of condition is typically resolved
The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.
Hearing issues to verify
- Did a valid permit already cover the exact work described by the inspector on the issue date?
- Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
- Do the approved drawings, permit scope and inspection history match the condition the inspector described?
- If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?
Evidence that may matter
- Permit and DOB NOW/BIS job records that predate the inspection
- Approved plans and amendments showing the cited work
- Dated photographs of the condition and construction stage
- Contracts, invoices and contractor statements establishing what work was actually performed
- Inspection / sign-off records if the work was subsequently legalized
Case-specific next step
For this property, the first paid review should reconcile the 4 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.