Demolition — Summons 39558071N
DOB allegation in the source extract: AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED BUILDING DEMO TO GRADE WITH DEMOLITION DEBRIS PILE UP APPROXIMATELY 8 TO 10 FEET IN HEIGHT, DEMOLITION DEBRIS CONSIST OF SHEETROCK, ELECTRICAL WIRE
Cited provision(s): 181 — BC 3303.4 & 27-1018 FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS
How this type of condition is typically resolved
Demolition charges can involve missing permits, missing notifications, unsafe demolition practices or work outside approved scope. Resolution requires identifying the exact procedural/safety failure and completing the missing filing or corrective work.
Hearing issues to verify
- Was a demolition permit or required notification in effect before work began?
- Did the cited activity constitute demolition under the applicable filing, or another permitted scope?
- Do contractor and agency records show the required notice was timely?
Evidence that may matter
- Demolition permit and DOB NOW filing history
- Required notification confirmation / timestamp
- Asbestos/environmental documents
- Contractor logs, photographs and demolition sequence records