Work Without a Permit — Summons 39199323Z
DOB allegation in the source extract: ATOI OBSERVED AT EXP 3 OF THE BUILDING 2ND FLOOR LEVEL ON TOP OF FIRST FLOOR COMMERCIAL SPACE ROOF APX 600 SQUARE FEET FRAMING FOR NEW DECK. AS PER DOB NO PERMIT ON FILE, DECK IS NOT MENTIONED ON LATEST CERTIFI
Cited provision(s): 201 — 28-105.1 WORK WITHOUT A PERMIT
How this type of condition is typically resolved
The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.
Hearing issues to verify
- Did a valid permit already cover the exact work described by the inspector on the issue date?
- Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
- Do the approved drawings, permit scope and inspection history match the condition the inspector described?
- If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?
Evidence that may matter
- Permit and DOB NOW/BIS job records that predate the inspection
- Approved plans and amendments showing the cited work
- Dated photographs of the condition and construction stage
- Contracts, invoices and contractor statements establishing what work was actually performed
- Inspection / sign-off records if the work was subsequently legalized