Site Safety / Safeguarding — Summons 39529288L
DOB allegation in the source extract: SITE SAFETY PLAN PHASES INADEQUATE/CONTRARY AS PER BC 3301.13.1: AT INSPECTION, IT WAS OBSERVED DIESEL TANK FOR CRANE AERIAL FUEL LOADING AT EXP.1 AND PIECES OF CRANE TO BE JUMPED ON VARIOUS FLOORS THAT WERE MI
Cited provision(s): 2P7
How this type of condition is typically resolved
These charges focus on protection of workers, occupants, neighboring property or the public during construction. Correction normally requires fixing the specific unsafe condition, documenting required safety measures and keeping the required site records current.
Hearing issues to verify
- What precise safety measure does the summons say was missing or inadequate?
- Was the condition temporary and corrected before or during the inspection?
- Did an approved site-safety plan or required site document address the cited condition?
Evidence that may matter
- Site Safety Plan / logistics drawings
- Daily safety logs and competent-person/site-safety records
- Photographs taken around the inspection time
- Contractor or safety-manager statements and correction records