What DOB is alleging at this property
This October hearing page is not just a schedule entry. The supplied DOB extract contains 3 summons records for this property identifier. The charge mix is: 2 Work Without a Permit summonses; Stop Work Order. The hearing date is October 27, 2026; the source issue date(s) are August 21, 2026.
Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.
Work Without a Permit — Summons 39201423X
CLASS - 1 · Issued August 21, 2026; hearing October 27, 2026. · Hearing status: PENDING
DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED ADDITIONAL WORK OUTSIDE OF APPROVED DOB PLANS AT ROOF AND EXPO 2 AND 3. NO MENTION OF BRICK REPLACEMENT OR ROOF, BULK HEAD, AND EXPO 2 AND 3 LINTELS WERE ON PLANS. PARTIAL STOP I
Cited provision(s): 182 — 28-105.12.2 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROV
How this type of condition is typically resolved
The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.
Hearing issues to verify
- Did a valid permit already cover the exact work described by the inspector on the issue date?
- Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
- Do the approved drawings, permit scope and inspection history match the condition the inspector described?
- If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?
Evidence that may matter
- Permit and DOB NOW/BIS job records that predate the inspection
- Approved plans and amendments showing the cited work
- Dated photographs of the condition and construction stage
- Contracts, invoices and contractor statements establishing what work was actually performed
- Inspection / sign-off records if the work was subsequently legalized
Stop Work Order — Summons 39201418L
CLASS - 2 · Issued August 21, 2026; hearing October 27, 2026. · Hearing status: PENDING
DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED INSTALLED SUPPORT SCAFFOLD NOT FULLY PLANKED AND MISSING GUARDRAILS. CONDITIONS POSE UNSAFE HAZARD AT SITE. PARTIAL STOP WORK ORDER ISSUED FOR VIOLATION OF BC3314.1; BC3314.1, CO
Cited provision(s): 2P7
How this type of condition is typically resolved
An active Stop Work Order has to be treated separately from the underlying summons. The cited unsafe or unpermitted condition must be corrected or legalized, required permits/penalties addressed, and the issuing agency must formally rescind or modify the order before prohibited work resumes.
Hearing issues to verify
- What exact work was covered by the Stop Work Order: all work or only part of the project?
- Was the activity observed after the order actually prohibited work, or was it authorized safety / emergency / corrective work?
- Was the Stop Work Order already rescinded or modified before the activity alleged in the summons?
Evidence that may matter
- Copy of the Stop Work Order and any rescission/modification notice
- DOB permit records and inspector correspondence
- Daily logs, photographs and contractor records showing when work stopped or resumed
- Evidence identifying any limited corrective/safety work performed
Work Without a Permit — Summons 39201420K
CLASS - 1 · Issued August 21, 2026; hearing October 27, 2026. · Hearing status: PENDING
DOB allegation in the source extract: AT TIME OF INSPECTION, OBSERVED INSTALLED SHED MISSING CROSS BAR FROM BACK TO FRONT POST AND ADDITIONAL SHEDS INSTALLED AT EXPO 2 AND 4. FIELD CONDITIONS DO NOT MATCH APPROVED DOB PLANS. FIELD CONDITIONS POSES
Cited provision(s): 182 — 28-105.12.2 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROV
How this type of condition is typically resolved
The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.
Hearing issues to verify
- Did a valid permit already cover the exact work described by the inspector on the issue date?
- Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
- Do the approved drawings, permit scope and inspection history match the condition the inspector described?
- If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?
Evidence that may matter
- Permit and DOB NOW/BIS job records that predate the inspection
- Approved plans and amendments showing the cited work
- Dated photographs of the condition and construction stage
- Contracts, invoices and contractor statements establishing what work was actually performed
- Inspection / sign-off records if the work was subsequently legalized
Case-specific next step
For this property, the first paid review should reconcile the 3 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.