Work Without a Permit — Summons 39108488K
DOB allegation in the source extract: RCA WAS ISSUED ON 11/1/23 BY INSPECTOR C. CORONA BADGE #3493 FOR WORK WITHOUT PERMIT AT REAR 2 STORY WOOD FRAMED HORIZONTAL & VERTICAL ENLARGEMENT WITH ROOF, CMU FOUNDATION . NO PERMITS WERE ISSUED OR APPOINTME
Cited provision(s): 101 — 28-105.1 WORK WITHOUT A PERMIT
How this type of condition is typically resolved
The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.
Hearing issues to verify
- Did a valid permit already cover the exact work described by the inspector on the issue date?
- Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
- Do the approved drawings, permit scope and inspection history match the condition the inspector described?
- If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?
Evidence that may matter
- Permit and DOB NOW/BIS job records that predate the inspection
- Approved plans and amendments showing the cited work
- Dated photographs of the condition and construction stage
- Contracts, invoices and contractor statements establishing what work was actually performed
- Inspection / sign-off records if the work was subsequently legalized