October 2026 NYC DOB / OATH Hearing — BIN 4211468

Queens property record with 4 OATH/ECB summons records in the supplied October 2026 hearing extract. Hearing date: October 27, 2026.

Need representation for this October hearing?

We can review the summons, agency record, correction status and available evidence; define the hearing strategy; prepare the authorized submission or appearance; and coordinate the underlying violation-resolution work separately where needed. Because hearing deadlines are fixed, substantive work begins after scope, authorization and payment.

Property / Hearing Identifiers

Primary hearing issue: Stop Work Order

BoroughQueens
BIN4211468
Block / Lot09893 / 0001
October Records4
Official violation location: Loading from NYC OATH public records…
Address is resolved from the OATH Hearings Division Case Status record for OATH ticket 039094900Z (source ECB number 39094900Z). BIN and block/lot remain shown below for verification.

October 2026 Hearing Records

OATH/ECB #HearingSeverityHearing statusBalanceAlleged conditionCode / section
39092794P
ACTIVE
October 27, 2026
10:30 AM
CLASS - 1 PENDING $2,530.00 UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A FULL STOP WORK ORDER. AT TIME OF INSPECTION, OBSERVED, WORK IS IN PROGRESS CONTRARY TO THE FULL STOP WORK ORDER# 4827587. SUMMON# 39032929Z ISSUED AT 12/03/2020 BE 1F8 — 28-207.2.5 TAMPERED WITH, REMOVED OR DEFACED A WRITTEN STOP WORK ORDER
39094899K
ACTIVE
October 27, 2026
10:30 AM
CLASS - 1 PENDING $2,530.00 WWAP. INSPECTION TIME, OBSERVED, CONSTRUCTION FENCE ERECTED AT FRONT, ALSO NOTED, AT FRONT & NEAR TO SIDEWALK CREATED A BIG OPENING ON FOUNDATION WALL APPROX. 6' BY 10' WITHOUT A PERMIT. THIS CONDITION PUTS THE 101 — 28-105.1 WORK WITHOUT A PERMIT
39094900Z
ACTIVE
October 27, 2026
10:30 AM
CLASS - 2 PENDING $1,030.00 JOB SITE FENCE IS CONSTRUCTED OR MAINTAINED PURSUANT TO SUBSECTION. AT TIME OF INSPECTION, OBSERVED, CONSTRUCTION FENCE HAS NO VIEWING PANELS AND NOT COLORED HUNTER GREEN AS PER CODE., COMPLY WITH CODE 211 — BC 3307.7,27-1021(C) JOB SITE FENCE NOT CONSTRUCTED PURSUANT TO SUBSECTION
39094901K
ACTIVE
October 27, 2026
10:30 AM
CLASS - 1 PENDING $6,280.00 TEMPERED WITH, REMOVED, OR DEFACED A WRITTEN POSTED STOP WORK ORDER. AT TIME OF INSPECTION, OBSERVED, SWO NOTICE (SUMMON# 39032929Z, ISSUED AT- 12/03/2020) REMOVED FROM THE FRONT DOOR. NOTED, SWO POSTER REPLACE 1F8 — 28-207.2.5 TAMPERED WITH, REMOVED OR DEFACED A WRITTEN STOP WORK ORDER

What DOB is alleging at this property

This October hearing page is not just a schedule entry. The supplied DOB extract contains 4 summons records for this property identifier. The charge mix is: 2 Stop Work Order summonses; Work Without a Permit; Sidewalk Shed / Scaffold. The hearing date is October 27, 2026; the source issue date(s) are August 17, 2023, September 14, 2023.

Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.

Stop Work Order — Summons 39092794P

CLASS - 1 · Issued August 17, 2023; hearing October 27, 2026. · Hearing status: PENDING

DOB allegation in the source extract: UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A FULL STOP WORK ORDER. AT TIME OF INSPECTION, OBSERVED, WORK IS IN PROGRESS CONTRARY TO THE FULL STOP WORK ORDER# 4827587. SUMMON# 39032929Z ISSUED AT 12/03/2020 BE

Cited provision(s): 1F8 — 28-207.2.5 TAMPERED WITH, REMOVED OR DEFACED A WRITTEN STOP WORK ORDER

How this type of condition is typically resolved

An active Stop Work Order has to be treated separately from the underlying summons. The cited unsafe or unpermitted condition must be corrected or legalized, required permits/penalties addressed, and the issuing agency must formally rescind or modify the order before prohibited work resumes.

Hearing issues to verify

  • What exact work was covered by the Stop Work Order: all work or only part of the project?
  • Was the activity observed after the order actually prohibited work, or was it authorized safety / emergency / corrective work?
  • Was the Stop Work Order already rescinded or modified before the activity alleged in the summons?

Evidence that may matter

  • Copy of the Stop Work Order and any rescission/modification notice
  • DOB permit records and inspector correspondence
  • Daily logs, photographs and contractor records showing when work stopped or resumed
  • Evidence identifying any limited corrective/safety work performed

Work Without a Permit — Summons 39094899K

CLASS - 1 · Issued September 14, 2023; hearing October 27, 2026. · Hearing status: PENDING

DOB allegation in the source extract: WWAP. INSPECTION TIME, OBSERVED, CONSTRUCTION FENCE ERECTED AT FRONT, ALSO NOTED, AT FRONT & NEAR TO SIDEWALK CREATED A BIG OPENING ON FOUNDATION WALL APPROX. 6' BY 10' WITHOUT A PERMIT. THIS CONDITION PUTS THE

Cited provision(s): 101 — 28-105.1 WORK WITHOUT A PERMIT

How this type of condition is typically resolved

The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.

Hearing issues to verify

  • Did a valid permit already cover the exact work described by the inspector on the issue date?
  • Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
  • Do the approved drawings, permit scope and inspection history match the condition the inspector described?
  • If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?

Evidence that may matter

  • Permit and DOB NOW/BIS job records that predate the inspection
  • Approved plans and amendments showing the cited work
  • Dated photographs of the condition and construction stage
  • Contracts, invoices and contractor statements establishing what work was actually performed
  • Inspection / sign-off records if the work was subsequently legalized

Sidewalk Shed / Scaffold — Summons 39094900Z

CLASS - 2 · Issued September 14, 2023; hearing October 27, 2026. · Hearing status: PENDING

DOB allegation in the source extract: JOB SITE FENCE IS CONSTRUCTED OR MAINTAINED PURSUANT TO SUBSECTION. AT TIME OF INSPECTION, OBSERVED, CONSTRUCTION FENCE HAS NO VIEWING PANELS AND NOT COLORED HUNTER GREEN AS PER CODE., COMPLY WITH CODE

Cited provision(s): 211 — BC 3307.7,27-1021(C) JOB SITE FENCE NOT CONSTRUCTED PURSUANT TO SUBSECTION

How this type of condition is typically resolved

The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.

Hearing issues to verify

  • Was the equipment covered by an active permit on the inspection date?
  • Did the installed dimensions/protection match the approved design?
  • Was a cited defect already corrected before the summons was issued or served?

Evidence that may matter

  • DOB NOW equipment permit and approved drawings
  • Engineer/contractor inspection logs
  • Dated site photographs
  • Renewal or removal records

Stop Work Order — Summons 39094901K

CLASS - 1 · Issued September 14, 2023; hearing October 27, 2026. · Hearing status: PENDING

DOB allegation in the source extract: TEMPERED WITH, REMOVED, OR DEFACED A WRITTEN POSTED STOP WORK ORDER. AT TIME OF INSPECTION, OBSERVED, SWO NOTICE (SUMMON# 39032929Z, ISSUED AT- 12/03/2020) REMOVED FROM THE FRONT DOOR. NOTED, SWO POSTER REPLACE

Cited provision(s): 1F8 — 28-207.2.5 TAMPERED WITH, REMOVED OR DEFACED A WRITTEN STOP WORK ORDER

How this type of condition is typically resolved

An active Stop Work Order has to be treated separately from the underlying summons. The cited unsafe or unpermitted condition must be corrected or legalized, required permits/penalties addressed, and the issuing agency must formally rescind or modify the order before prohibited work resumes.

Hearing issues to verify

  • What exact work was covered by the Stop Work Order: all work or only part of the project?
  • Was the activity observed after the order actually prohibited work, or was it authorized safety / emergency / corrective work?
  • Was the Stop Work Order already rescinded or modified before the activity alleged in the summons?

Evidence that may matter

  • Copy of the Stop Work Order and any rescission/modification notice
  • DOB permit records and inspector correspondence
  • Daily logs, photographs and contractor records showing when work stopped or resumed
  • Evidence identifying any limited corrective/safety work performed

Case-specific next step

For this property, the first paid review should reconcile the 4 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.

Submit These Summonses for Review

What to do before the hearing

1. Verify the summons

Confirm the scheduled date, respondent, violation location, charges and current OATH status.

2. Preserve evidence

Gather permits, photographs, contracts, inspection records, professional letters and proof of correction that actually relate to the cited condition.

3. Separate hearing from correction

A hearing result and physical/agency correction are not always the same task. Plan both tracks where required.

Official Hearing Record

Verify the current hearing status and violation location in the NYC OATH Hearings Division Case Status data before relying on any public directory.

NYC OATH Case Status Data →

OATH evidence and DOB correction records

OATH advises respondents to bring or submit the evidence needed to prove their case, including legal or official records, photographs, documents and witnesses. For a DOB Certificate of Correction, DOB may require supporting material such as photographs, receipts, permits and inspection results in addition to the required correction information and applicable civil-penalty documentation.