What DOB is alleging at this property
This October hearing page is not just a schedule entry. The supplied DOB extract contains 5 summons records for this property identifier. The charge mix is: 3 Work Without a Permit summonses; Failure to Maintain; Boiler / HVAC / Service Equipment. The hearing date is October 27, 2026; the source issue date(s) are June 11, 2026.
Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.
Work Without a Permit — Summons 39192234P
CLASS - 1 · Issued June 11, 2026; hearing October 27, 2026. · Hearing status: PENDING
DOB allegation in the source extract: NOTED; AT CELLAR LEVEL INSTALLED GAS LINE FOR STOVE WITHOUT OBTAINING REQUIRED PERMITS, OBTAIN PERMIT
Cited provision(s): 101 — 28-105.1 WORK WITHOUT A PERMIT
How this type of condition is typically resolved
The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.
Hearing issues to verify
- Did a valid permit already cover the exact work described by the inspector on the issue date?
- Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
- Do the approved drawings, permit scope and inspection history match the condition the inspector described?
- If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?
Evidence that may matter
- Permit and DOB NOW/BIS job records that predate the inspection
- Approved plans and amendments showing the cited work
- Dated photographs of the condition and construction stage
- Contracts, invoices and contractor statements establishing what work was actually performed
- Inspection / sign-off records if the work was subsequently legalized
Work Without a Permit — Summons 39192235R
CLASS - 2 · Issued June 11, 2026; hearing October 27, 2026. · Hearing status: PENDING
DOB allegation in the source extract: NOTED; AT CELLAR LEVEL INSTALLED ELECTRICAL WIRING FOR HVAC SPLIT UNIT WITHOUT OBTAINING REQUIRED PERMITS., OBTAIN ALL PERMITS
Cited provision(s): 201 — 28-105.1 WORK WITHOUT A PERMIT
How this type of condition is typically resolved
The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.
Hearing issues to verify
- Did a valid permit already cover the exact work described by the inspector on the issue date?
- Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
- Do the approved drawings, permit scope and inspection history match the condition the inspector described?
- If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?
Evidence that may matter
- Permit and DOB NOW/BIS job records that predate the inspection
- Approved plans and amendments showing the cited work
- Dated photographs of the condition and construction stage
- Contracts, invoices and contractor statements establishing what work was actually performed
- Inspection / sign-off records if the work was subsequently legalized
Work Without a Permit — Summons 39192236Z
CLASS - 2 · Issued June 11, 2026; hearing October 27, 2026. · Hearing status: PENDING
DOB allegation in the source extract: NOTED; AT CELLAR LEVEL INSTALLED WATER & WASTE LINES FOR 3 PC BATH (TOILET, SINK, STALL SHOWER) AND RESIDENTIAL SINK WITHOUT OBTAINING REQ PERMITS, OBTAIN ALL PERMITS
Cited provision(s): 201 — 28-105.1 WORK WITHOUT A PERMIT
How this type of condition is typically resolved
The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.
Hearing issues to verify
- Did a valid permit already cover the exact work described by the inspector on the issue date?
- Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
- Do the approved drawings, permit scope and inspection history match the condition the inspector described?
- If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?
Evidence that may matter
- Permit and DOB NOW/BIS job records that predate the inspection
- Approved plans and amendments showing the cited work
- Dated photographs of the condition and construction stage
- Contracts, invoices and contractor statements establishing what work was actually performed
- Inspection / sign-off records if the work was subsequently legalized
Failure to Maintain — Summons 39192237K
CLASS - 2 · Issued June 11, 2026; hearing October 27, 2026. · Hearing status: PENDING
DOB allegation in the source extract: NOTED; AT EXP.3 OF PREMISES STEPS LEADING TO CELLAR MISSING/ NO HANDRAILS FOR 5 STEPS. CREATING A FALL HAZARD. AS PER 28-301.1, REPAIR AND/OR REPLACE
Cited provision(s): 202 — 28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER
How this type of condition is typically resolved
Failure-to-maintain charges are fact-specific. The owner should identify the exact building component or service equipment cited, repair the condition, and document the repair with evidence tied to the inspection location/date.
Hearing issues to verify
- Does the description accurately identify the component, location and condition?
- Was the condition already repaired or not present when the summons was issued?
- Was another party responsible for maintenance under facts that are legally relevant to the respondent's liability?
Evidence that may matter
- Dated before/after photographs
- Repair invoices and contractor statements
- Professional inspection/report when structural or technical conditions are involved
- Maintenance logs and prior inspection records
Boiler / HVAC / Service Equipment — Summons 39192238M
CLASS - 1 · Issued June 11, 2026; hearing October 27, 2026. · Hearing status: PENDING
DOB allegation in the source extract: FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. OBSERVED IN THE BOILER ROOM NO FIRE-RATING; WITH MISSING WALL COVERING AND OPEN CEILING EXPOSING THE FLOOR JOIST OF THE 1ST FLOOR. DOOR TO BOILER ROOM HAS
Cited provision(s): 102 — 28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER
How this type of condition is typically resolved
Service-equipment charges usually require repair, safe shutdown or replacement of the cited equipment, together with any required inspection, testing, annual filing or device-status update.
Hearing issues to verify
- Was the cited device in service at the time alleged?
- Was the equipment already repaired, disconnected or removed?
- Do required annual inspection / filing records show compliance for the relevant cycle?
Evidence that may matter
- Licensed contractor maintenance/repair records
- Inspection and testing results
- Device-status or annual filing records
- Utility/CO testing records and photographs where relevant
Case-specific next step
For this property, the first paid review should reconcile the 5 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.
Submit These Summonses for Review