What DOB is alleging at this property
This October hearing page is not just a schedule entry. The supplied DOB extract contains 4 summons records for this property identifier. The charge mix is: Work Without a Permit; Sidewalk Shed / Scaffold; Other Building / Code Compliance; Site Safety / Safeguarding. The hearing dates are October 20, 2026, October 27, 2026; the source issue date(s) are August 18, 2026, February 1, 2024.
Important: The discussion below identifies correction paths, hearing issues and evidence worth investigating from the summons data. It does not state that a defense will succeed. OATH decides liability from the evidence and law presented in the case.
Work Without a Permit — Summons 39525282M
CLASS - 2 · Issued February 1, 2024; hearing October 20, 2026. · Hearing status: DEFAULT
DOB allegation in the source extract: JOB FENCE.@NB SITE WITH RELATED CONTRACTORS WITHDREW OBSERVE JOB FENCE IN PLACE AT EXPOSURE#1,2,4(153 ST, 89 AVE, 88 AVE)WITH NO VALID PERMIT DUE TO FENCE CONTRACTOR JOB#Q00623665 WITHDREW PER DOB RECORDS ON 02
Cited provision(s): 2L1 — 28-105.1 FAILURE TO OBTAIN A TEMPORARY CONSTRUCTION PERMIT PRIOR TO INSTALLATIO
How this type of condition is typically resolved
The correction path usually starts by determining whether the observed work required a permit and whether the condition can legally remain. If it can remain, legalization may require plans, a filing, permit, inspections and closeout; if it cannot or the owner does not want to legalize it, restoration to a lawful condition may be required.
Hearing issues to verify
- Did a valid permit already cover the exact work described by the inspector on the issue date?
- Was the cited activity actually permit-required work, or was it maintenance / exempt work under the applicable facts?
- Do the approved drawings, permit scope and inspection history match the condition the inspector described?
- If a Stop Work Order was issued, was the work stopped and was any later work performed only after the required authorization?
Evidence that may matter
- Permit and DOB NOW/BIS job records that predate the inspection
- Approved plans and amendments showing the cited work
- Dated photographs of the condition and construction stage
- Contracts, invoices and contractor statements establishing what work was actually performed
- Inspection / sign-off records if the work was subsequently legalized
Sidewalk Shed / Scaffold — Summons 39525283Y
CLASS - 1 · Issued February 1, 2024; hearing October 20, 2026. · Hearing status: DEFAULT
DOB allegation in the source extract: BC 3307.7.7 CONDITION OF FENCES.@NB SITE WITH RELATED CONTRACTORS WITHDREW OBSERVE APPROX.40FT OF JOB FENCE OVERTURNED ON SIDEWALK AT EXPOSURE#1(153 STREET) WITH PROTRUDING NAILS THROUGHOUT, OBSTRUCTING PEDESTR
Cited provision(s): 1P7
How this type of condition is typically resolved
The issue is typically whether the shed/scaffold was permitted, properly installed and maintained, and whether the equipment matched the approved filing and current safety requirements. Correction can involve permit renewal, physical modification, inspection, or removal.
Hearing issues to verify
- Was the equipment covered by an active permit on the inspection date?
- Did the installed dimensions/protection match the approved design?
- Was a cited defect already corrected before the summons was issued or served?
Evidence that may matter
- DOB NOW equipment permit and approved drawings
- Engineer/contractor inspection logs
- Dated site photographs
- Renewal or removal records
Other Building / Code Compliance — Summons 39525284X
CLASS - 1 · Issued February 1, 2024; hearing October 20, 2026. · Hearing status: DEFAULT
DOB allegation in the source extract: BC3303.13 INTERRUPTED OR ABANDONED&DISCONTINUED OPERATIONS.@8STORY NB SITE IN STRUCTURE PHASE W/ RELATED LICENSEES WITHDREW PER DOB RECORDS IN 2023(COMPLAINT#4914422,4914425,4914426,4914427,4915780,4916649)OBSE
Cited provision(s): 1P7
How this type of condition is typically resolved
The first step is to read the inspector's narrative together with every cited code section and determine exactly what act, condition or missing filing DOB alleges. The correction and hearing strategy should then be built around that specific charge rather than a generic violation-removal checklist.
Hearing issues to verify
- Does the summons identify the correct property, respondent, date and observed condition?
- Do agency records support or contradict the inspector's description?
- Was the condition corrected, permitted or otherwise resolved before the hearing?
Evidence that may matter
- Official DOB/OATH property and summons records
- Dated photographs and videos
- Permits, approved plans and inspection results
- Contracts, receipts, professional letters or witness statements tied to the cited condition
Site Safety / Safeguarding — Summons 35729968X
CLASS - 2 · Issued August 18, 2026; hearing October 27, 2026. · Hearing status: PENDING
DOB allegation in the source extract: FAILURE TO PROVIDE PROJECT INFORMATION PANEL AND CONTENTS. AS NOTED: AT TIME OF INSPECTION OF A CONSTRUCTION SITE OF A PROPOSED 8 STORY BUILDING WAS CLOSED. OBSERVED THE ABSENCE OF NON AVAILABILITY OF SITE PROJ
Cited provision(s): 217 — BC 3301.9,27-10009(C) FAIL TO PROVIDE/POST SIGN(S) AT JB SITE PURSUANT TO SUBSEC
How this type of condition is typically resolved
These charges focus on protection of workers, occupants, neighboring property or the public during construction. Correction normally requires fixing the specific unsafe condition, documenting required safety measures and keeping the required site records current.
Hearing issues to verify
- What precise safety measure does the summons say was missing or inadequate?
- Was the condition temporary and corrected before or during the inspection?
- Did an approved site-safety plan or required site document address the cited condition?
Evidence that may matter
- Site Safety Plan / logistics drawings
- Daily safety logs and competent-person/site-safety records
- Photographs taken around the inspection time
- Contractor or safety-manager statements and correction records
Case-specific next step
For this property, the first paid review should reconcile the 4 October summons records against the current OATH/DOB record, identify which alleged conditions remain open, and separate the hearing defense from the DOB correction / certification work. That prevents paying for correction work that does not address the actual charge—or appearing at OATH without the documents needed for the cited condition.