Boiler device inspection and filing: NYC DOB 28-301.1 / OATH summons 35685893Z

Original enforcement allegation, not a proven case outcome. The quotation below is from an inspector-written description in a public-record dataset. Extracts may end mid-sentence. The inspection origin, complete supporting evidence, legal finding, and disposition have not been independently verified. Interpretive explanations below are explicitly analytical possibilities.
Law citation: 28-301.1OATH infraction: 102Summons: 35685893Z

Original inspector allegation — verbatim available export

AT TIME OF INSPECTION OBSERVED AT 1ST FLOOR UNPROTECTED/EXPOSED ELECTRICAL WIRING EXIT PASSAGEWAY TO BACK OF THE BUILDING PARTIALLY OBSTRUCTED BY CEMENT. AT CELLAR LEVEL BOILER ROOM DOOR NOT SELF CLOSING AND MA

Source limit: Source reference: NYC OATH/DOB summons 35685893Z; BIN 3102342; export issue date 07/24/2026. The earlier export status was ACTIVE; obtain current status from DOB or OATH. The CSV contains a respondent mailing address, which is not presumed to identify the inspected property. This is the entire description available in the supplied export, not a certified full summons, inspector notes or evidentiary exhibits. The description is at the export’s approximately 210-character field limit and may terminate mid-word or mid-sentence.

Get the complete, authentic notice: search summons 35685893Z in OATH Summons Finder instructions (download actual summons) and download the actual summons; review DOB records in NYC DOB records search. Never substitute the editorial discussion below for the inspector’s words.

Charge classification: law controls; keywords do not

Recorded citation: 28-301.1; recorded infraction: 102. Primary legal issue: safe building maintenance. Interpretive issue: Owner maintenance obligation. AC 28-301.1 requires buildings, equipment, safeguards and means of egress to be kept safe and maintained. The physical condition, rather than whether a particular permit exists, is normally the central question.

What must be tested: The applicable underlying technical standard and the actual defective component determine a lawful repair. An assertion that the building is generally safe does not rebut a specific defect.

Possible exceptions and legal limitations: An exemption from cyclical façade reporting does not exempt a building from general safe-maintenance duties. Determine whether the special rule actually applies. Eligibility is not established merely because the excerpt uses a word such as “repair”, “permit”, “cellar”, or “occupied”. Refer to NYC DOB construction codes.

Specific conditions mentioned in this inspector wording

1. Boiler device inspection and filing

Investigative test: Determine whether the alleged defect is missing periodic inspection/report, a physical unsafe condition or unpermitted replacement; link the device identifier to the required inspection cycle.

Evidence matched to this issue: Boiler device/installation record, agency filing receipt, inspector qualification, report and any affirmation-of-correction documentation.

Boundary / potential counterexample: A physical tune-up invoice is not a filed annual boiler inspection report, and filing alone does not resolve a real hazard.

2. Electrical installation and permit

Investigative test: Locate the exact wiring or equipment and determine whether the allegation is unsafe installation, unpermitted electrical work, posting, or inspection/permit status.

Evidence matched to this issue: Licensed-electrician site notes, panel/circuit identification, photos, electrical filing/permit history and test results when appropriate.

Boundary / potential counterexample: The evidence for a missing electrical work permit is not identical to proof of defective circuitry or missing display.

3. Authorized use versus observed occupancy

Investigative test: Identify each floor/unit and its claimed function and compare the C of O/authorized plan with actual use on the cited date.

Evidence matched to this issue: C of O and historical building records; dated layout/room photos, use documentation, rent/booking records only where genuinely relevant, and design-professional egress review.

Boundary / potential counterexample: Basement/cellar classification, legal dwelling status and transient-use rules are distinct determinations; do not conflate them.

4. Means of egress and exit protection

Investigative test: Trace the occupant route from the cited point to discharge; check door swing, clear width, obstruction, illumination and the approved layout.

Evidence matched to this issue: Approved egress plan, location-labeled photos and measured clearance, fire/exit inspection records, dated removal or hardware repair evidence.

Boundary / potential counterexample: Do not advise blocking an occupied egress route as a temporary fix; applicability may differ for old and altered buildings.

5. Structural and interior building component

Investigative test: Pin down floor, room and assembly; inspect dimensions, connections, condition and impact on fire separation or egress.

Evidence matched to this issue: Floor plan, measured photos, licensed design-professional report if structural, approved drawings and after-work inspection.

Boundary / potential counterexample: Structural work and cosmetic repair have different approval burdens; the inspector wording alone may not establish the distinction.

Inspector wording mapped to testable facts

Passage 1 — AT TIME OF INSPECTION OBSERVED AT 1ST FLOOR UNPROTECTED/EXPOSED ELECTRICAL WIRING EXIT PASSAGEWAY TO BACK OF THE BUILDING PAR…

This recorded passage identifies a question about electrical installation and permit, not a proven final determination. Locate the exact wiring or equipment and determine whether the allegation is unsafe installation, unpermitted electrical work, posting, or inspection/permit status. The evidence for a missing electrical work permit is not identical to proof of defective circuitry or missing display.

Passage 2 — AT CELLAR LEVEL BOILER ROOM DOOR NOT SELF CLOSING AND MA

This recorded passage identifies a question about boiler device inspection and filing, not a proven final determination. Determine whether the alleged defect is missing periodic inspection/report, a physical unsafe condition or unpermitted replacement; link the device identifier to the required inspection cycle. A physical tune-up invoice is not a filed annual boiler inspection report, and filing alone does not resolve a real hazard.

Identifiers, locations, measurements and chronology to verify

Identified floor: 1ST FLOOR, CELLAR
Tie inspection photographs to the stated level, approved floor plan, egress route, and actual room use.

Case-specific correction decision tree

Branch A — defect remains: assess risk and protection immediately, then undertake an appropriate licensed/engineered repair. Branch B — already repaired: pair before/after photos with scope, inspection and test results that address the *specific* defect. Branch C — inspector misidentified the component: use an elevation/floor key and technical field report; do not rely on an unspecific clean-inspection assertion.

First targeted evidence collection: Boiler device/installation record, agency filing receipt, inspector qualification, report and any affirmation-of-correction documentation. This is an investigative request, not a claim that the work or evidence already exists.

Editorial closure of the shortened allegation — NOT source text

Verbatim excerpt ends: “ OF THE BUILDING PARTIALLY OBSTRUCTED BY CEMENT. AT CELLAR LEVEL BOILER ROOM DOOR NOT SELF CLOSING AND MA”. Non-source editorial completion (conditional reconstruction, not a quotation): “The allegation appears to concern boiler device inspection and filing; whether additional observations, directions, dates, measurements or exceptions followed is unknown and must be checked in the original summons.”

No missing words, dates, measurements, liability conclusion or regulatory remedy have been invented. Even if the final syllable looks obvious, completing it as a purported inspector quotation would misstate an official record.

Response, certification and closing evidence

A hearing defense, correction of the underlying condition, a DOB AEU Certificate of Correction and payment of an imposed penalty are distinct questions. Retrieve the summons and confirm the OATH hearing or outcome and DOB violation status. Under current DOB guidance, Certificate of Correction review requests are made in DOB NOW: Safety → Violations & Notices of Deficiency; submitter/certifier signatures and evidence requirements are case-specific. Refer to Certificate of Correction instructions.

Source record limitations: The dataset does not authenticate who inspected the property, why inspection started, whether a defense succeeded, which contractor made repairs or whether AEU later accepted a correction. Do not turn this example into a claimed client success story or an invented inspection history.

Primary authority and fact-check links

Related library and official records

Official sources: Search DOB records · DOB summonses · Certificate of Correction FAQs · OATH hearing options · Construction codes

Need a resolution plan tied to the full summons?

Building Violation LLC can review the violation wording, permits, drawings, correction evidence and available OATH hearing procedures. A web example is not a determination of compliance for any property.

Call (866) 545-4440