Boiler device inspection and filing: NYC DOB 28-301.1 / OATH summons 39204015K
Original inspector allegation — verbatim available export
AT THE CELLAR OF THE BUILDING, OBSERVED FAILURE TO MAINTAIN. THE PIPING ASSOCIATED WITH THE PLP GAS METER SERVING THE HOT WATER HEATER (HWHS) AND BOILER. A FAINT ODOR OF GAS WAS DETECTED AT AN ELBOW CONNECTION
Source limit: Source reference: NYC OATH/DOB summons 39204015K; BIN 3031447; export issue date 09/14/2026. The earlier export status was ACTIVE; obtain current status from DOB or OATH. The CSV contains a respondent mailing address, which is not presumed to identify the inspected property. This is the entire description available in the supplied export, not a certified full summons, inspector notes or evidentiary exhibits. The description is at the export’s approximately 210-character field limit and may terminate mid-word or mid-sentence.
Get the complete, authentic notice: search summons 39204015K in OATH Summons Finder instructions (download actual summons) and download the actual summons; review DOB records in NYC DOB records search. Never substitute the editorial discussion below for the inspector’s words.
Charge classification: law controls; keywords do not
Recorded citation: 28-301.1; recorded infraction: 202. Primary legal issue: safe building maintenance. Interpretive issue: Owner maintenance obligation. AC 28-301.1 requires buildings, equipment, safeguards and means of egress to be kept safe and maintained. The physical condition, rather than whether a particular permit exists, is normally the central question.
What must be tested: The applicable underlying technical standard and the actual defective component determine a lawful repair. An assertion that the building is generally safe does not rebut a specific defect.
Possible exceptions and legal limitations: An exemption from cyclical façade reporting does not exempt a building from general safe-maintenance duties. Determine whether the special rule actually applies. Eligibility is not established merely because the excerpt uses a word such as “repair”, “permit”, “cellar”, or “occupied”. Refer to NYC DOB construction codes.
Specific conditions mentioned in this inspector wording
1. Boiler device inspection and filing
Investigative test: Determine whether the alleged defect is missing periodic inspection/report, a physical unsafe condition or unpermitted replacement; link the device identifier to the required inspection cycle.
Evidence matched to this issue: Boiler device/installation record, agency filing receipt, inspector qualification, report and any affirmation-of-correction documentation.
Boundary / potential counterexample: A physical tune-up invoice is not a filed annual boiler inspection report, and filing alone does not resolve a real hazard.
2. Gas equipment or fuel piping
Investigative test: Establish affected equipment and gas line route; check whether a licensed plumber and utility coordination are required and document safe isolation if indicated.
Evidence matched to this issue: Licensed-master-plumber assessment, approved gas work plans/permits, utility authorization, pressure/test reports and final inspection if applicable.
Boundary / potential counterexample: Do not recommend turning gas on or modifying piping based on a web excerpt; licensed trades and agency/utility procedures govern.
3. Plumbing fixture and drainage configuration
Investigative test: Map each named fixture/connection to the approved layout and check who installed it and whether the work requires plumbing filing or licensed trade.
Evidence matched to this issue: Fixture schedule, riser drawings, photos, licensed-plumber report, permit history and test/inspection or abandonment proof.
Boundary / potential counterexample: A sink or drain alone does not prove creation of a lawful dwelling unit or justify a particular permit type.
4. Authorized use versus observed occupancy
Investigative test: Identify each floor/unit and its claimed function and compare the C of O/authorized plan with actual use on the cited date.
Evidence matched to this issue: C of O and historical building records; dated layout/room photos, use documentation, rent/booking records only where genuinely relevant, and design-professional egress review.
Boundary / potential counterexample: Basement/cellar classification, legal dwelling status and transient-use rules are distinct determinations; do not conflate them.
Inspector wording mapped to testable facts
Passage 1 — AT THE CELLAR OF THE BUILDING, OBSERVED FAILURE TO MAINTAIN.
This recorded passage identifies a question about authorized use versus observed occupancy, not a proven final determination. Identify each floor/unit and its claimed function and compare the C of O/authorized plan with actual use on the cited date. Basement/cellar classification, legal dwelling status and transient-use rules are distinct determinations; do not conflate them.
Passage 2 — THE PIPING ASSOCIATED WITH THE PLP GAS METER SERVING THE HOT WATER HEATER (HWHS) AND BOILER.
This recorded passage identifies a question about boiler device inspection and filing, not a proven final determination. Determine whether the alleged defect is missing periodic inspection/report, a physical unsafe condition or unpermitted replacement; link the device identifier to the required inspection cycle. A physical tune-up invoice is not a filed annual boiler inspection report, and filing alone does not resolve a real hazard.
Passage 3 — A FAINT ODOR OF GAS WAS DETECTED AT AN ELBOW CONNECTION
Treat this passage as an asserted observation or reference. Check the named location, actor, object and time against contemporaneous photos and official filing records before drawing a regulatory conclusion.
Identifiers, locations, measurements and chronology to verify
- Identified floor: CELLAR
- Tie inspection photographs to the stated level, approved floor plan, egress route, and actual room use.
Case-specific correction decision tree
Branch A — defect remains: assess risk and protection immediately, then undertake an appropriate licensed/engineered repair. Branch B — already repaired: pair before/after photos with scope, inspection and test results that address the *specific* defect. Branch C — inspector misidentified the component: use an elevation/floor key and technical field report; do not rely on an unspecific clean-inspection assertion.
First targeted evidence collection: Boiler device/installation record, agency filing receipt, inspector qualification, report and any affirmation-of-correction documentation. This is an investigative request, not a claim that the work or evidence already exists.
Editorial closure of the shortened allegation — NOT source text
Verbatim excerpt ends: “R SERVING THE HOT WATER HEATER (HWHS) AND BOILER. A FAINT ODOR OF GAS WAS DETECTED AT AN ELBOW CONNECTION”. Non-source editorial completion (conditional reconstruction, not a quotation): “The allegation appears to concern boiler device inspection and filing; whether additional observations, directions, dates, measurements or exceptions followed is unknown and must be checked in the original summons.”
No missing words, dates, measurements, liability conclusion or regulatory remedy have been invented. Even if the final syllable looks obvious, completing it as a purported inspector quotation would misstate an official record.
Response, certification and closing evidence
A hearing defense, correction of the underlying condition, a DOB AEU Certificate of Correction and payment of an imposed penalty are distinct questions. Retrieve the summons and confirm the OATH hearing or outcome and DOB violation status. Under current DOB guidance, Certificate of Correction review requests are made in DOB NOW: Safety → Violations & Notices of Deficiency; submitter/certifier signatures and evidence requirements are case-specific. Refer to Certificate of Correction instructions.
Source record limitations: The dataset does not authenticate who inspected the property, why inspection started, whether a defense succeeded, which contractor made repairs or whether AEU later accepted a correction. Do not turn this example into a claimed client success story or an invented inspection history.
Primary authority and fact-check links
- OATH Summons Finder instructions (download actual summons) — enter summons 39204015K and obtain the signed notice.
- NYC DOB construction codes — verify law wording and any exception.
- BIS / DOB NOW record limitations — older BIS violations may not be in DOB NOW.
- Certificate of Correction instructions — review current COC procedure, signatures and evidence.
Related library and official records
Official sources: Search DOB records · DOB summonses · Certificate of Correction FAQs · OATH hearing options · Construction codes
Need a resolution plan tied to the full summons?
Building Violation LLC can review the violation wording, permits, drawings, correction evidence and available OATH hearing procedures. A web example is not a determination of compliance for any property.