Summons 39202135X — Work not conforming to approved documents
Normalized lookup key: 039202135XWhat DOB alleges
DOB alleges that field work did not conform to the approved construction documents. The inspector's description specifically references first floor and electrical wiring/equipment.
Specific record details: first floor, electrical wiring/equipment.
Full violation description from the source extract
B1C8 - CLASS 1 - ELECTRICAL WORK DOES NOT CONFORM TO APPROVED SUBMITTAL DOCUMENTS/AMENDMENTS. ATOI OBSERVED ELECTRICAL WORK AT 1ST FLR COMMERCIAL SPACE DOES NOT CONFORM TO PERMITTED SCOPE OF WORK. JOB# M0145194
- Issue date
- August 27, 2026
- Served date
- August 27, 2026
- Source violation type
- Unknown
- Severity
- CLASS - 1
- Hearing status in source extract
- PENDING
- 1C8 — 27-3018(B) ELEC. WORK DOES NOT CONFORM TO APPROVED SUBMITTAL DOCUMENTS/AMENDMENTS
Record-specific focus: Before choosing a correction or hearing strategy, verify the source allegation concerning b1c8 - class 1 - electrical work does not conform to approved submittal documents/amendments. atoi observed electrical work at 1st floor commercial space does not conform to permitted scope of work. job# m0145194.
What this violation means
DOB is alleging that work in progress did not match the approved construction documents or amendments. Even permitted work can be cited if the field condition departs materially from the approved plan set.
What may be required to correct the condition
The field condition should be compared line-by-line with the approved plans. Depending on what is found, the project may need to be restored to the approved design or the plans may need to be amended and re-approved before the work continues or is signed off. Because electrical work is mentioned, any correction plan should separately verify whether licensed electrical work, filing or inspection is required.
What the OATH hearing may involve
Hearing evidence can include the approved plan sheets in effect on the inspection date, revision history, photographs of the field condition, professional reports and proof that the discrepancy was corrected or formally amended.
Possible defenses or factual issues worth investigating
Identify the exact plan sheet/detail DOB says was violated, confirm which approved set controlled on the inspection date, and determine whether the field condition was temporary, incomplete, or actually inconsistent with the approval.
Documents and evidence that may be useful
- DOB-approved construction documents and amendments
- field photographs
- architect/engineer field reports
- permit and inspection history
- revised approvals or restoration evidence