November 2026 NYC DOB / ECB / OATH public-record review

308 14 Street, Brooklyn, NY 11215 — November 2026 NYC OATH Hearing & Violation Information

The resolved public-record dataset associates 3 DOB/ECB OATH summonses with 308 14 Street, Brooklyn, NY 11215. The source records identify stop work order compliance, sidewalk shed / temporary construction protection and a hearing date of November 6, 2026. The sections below keep the source allegations separate from explanatory analysis so an owner, buyer, realtor, attorney, lender, property manager or contractor can see what the record says, what still needs verification, and what a practical next review could involve.

Stop Work Order complianceSidewalk shed / temporary construction protection

Property and hearing summary

Actual property address
308 14 Street, Brooklyn, NY 11215
Borough
Brooklyn
BIN
3023718
BBL
3010420037 (3/1042/37)
Hearing month
November 2026
Violations on this page
3
Verified hearing date(s) in source extract
November 6, 2026
Source extract
September 18, 2026
Source information: This page was compiled from NYC DOB/ECB/OATH public-record information contained in the November 2026 resolved-property dataset and the associated DOB/ECB source extract dated September 18, 2026. Agency records may change after the source data was obtained. Hearing dates, status, penalties, correction status and agency records should be verified with NYC OATH and DOB before relying on this page.

November 2026 hearing summary

ECB/OATH summonsHearing date / timeSeverityRecord category
39194591M
Normalized: 039194591M
November 6, 2026
8:30 AM
CLASS - 1 Stop Work Order compliance
39194592Y
Normalized: 039194592Y
November 6, 2026
8:30 AM
CLASS - 1 Sidewalk shed / temporary construction protection
39194593X
Normalized: 039194593X
November 6, 2026
8:30 AM
CLASS - 1 Sidewalk shed / temporary construction protection

How the summonses fit together at this property

These summonses form a construction-site compliance cluster rather than a single generic violation. They address different safety, temporary-protection, approved-plan or work-control obligations at the same property. Site records should be organized by inspection date and cited condition so the correction and hearing response for one summons is not mistakenly used for another.

Violation-by-violation record and analysis

Each section first identifies what comes directly from the source extract, then separates general explanatory and strategic considerations that may require current-record research or professional review.

Violation 1

Summons 39194591M — Stop Work Order compliance

Normalized lookup key: 039194591M
OATH hearingNovember 6, 20268:30 AM

What DOB alleges

DOB alleges work or site activity occurred contrary to an active Stop Work Order or related restriction. The inspector's description specifically references Stop Work Order.

Specific record details: Stop Work Order. The description also references Stop Work Order FOR.

Full violation description from the source extract

UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER. ATOI, OBSERVED WORK HAS CONTINUED WHILE PARTIAL STOP WORK ORDER FOR EXTERIORFRONT RIGHT-SIDE OF THE BUILDING ISSUED ON 3/26/2026, FOR WORK DOES NO

Issue date
July 1, 2026
Served date
July 1, 2026
Source violation type
Construction
Severity
CLASS - 1
Hearing status in source extract
PENDING
Infraction / law references in source extract:
  • 112 — 28-207.2.2 UNLAWFULLY CONTINUED WORK WHILE NOTICE OF A STOP WORK ORDER

Record-specific focus: Before choosing a correction or hearing strategy, verify the source allegation concerning unlawfully continued work while on notice of a stop work order. atoi, observed work has continued while partial stop work order for exteriorfront right-side of the building issued on 3/26/2026, for work does no.

What this violation means

The source record concerns work performed or conditions maintained while a Stop Work Order was in effect, or another violation tied directly to a Stop Work Order. Continuing regulated work under an active order can create separate enforcement exposure.

What may be required to correct the condition

Verify the Stop Work Order's scope and whether it remains active. The underlying reasons for the order may require correction, permits, amended plans, site-safety measures or inspections before DOB will consider rescission or limited work authorization.

What the OATH hearing may involve

Relevant hearing evidence can include the Stop Work Order itself, photographs of the work activity, permits and approvals in effect at the time, DOB inspection history, and any document showing the order had been lifted or modified.

Possible defenses or factual issues worth investigating

Review the exact order number, date, scope, affected work areas, authorized exceptions if any, and whether the activity described by the inspector actually occurred while the order was active. Cross-reference the other order/summons number cited in the inspector narrative rather than reviewing this record in isolation.

Documents and evidence that may be useful

  • Stop Work Order and related DOB inspection records
  • permits and approved plans
  • site photographs and daily logs
  • rescind/partial-rescind correspondence or approvals
  • contractor and site-safety records
Violation 2

Summons 39194592Y — Sidewalk shed / temporary construction protection

Normalized lookup key: 039194592Y
OATH hearingNovember 6, 20268:30 AM

What DOB alleges

DOB alleges a defect or code-compliance problem involving sidewalk-shed/scaffold protection. The inspector's description specifically references brick/masonry condition, scaffold/shoring and exposure 4.

Specific record details: brick/masonry condition, scaffold/shoring, exposure 4.

Full violation description from the source extract

FAILURE TO SAFEGUARD PUBLIC AND PROPERTY AFFECTED BY CONSTRUCTION OPERATIONS. ATOI, OBSERVED CONSTR. SITE UNDER PERMIT #B00637654-I1-GC. NOTED ONGOING MASONRY WORK AT EXP 4 ON UNSAFE SCAFFOLD, PALES OF STUCCO,

Issue date
July 1, 2026
Served date
July 1, 2026
Source violation type
Construction
Severity
CLASS - 1
Hearing status in source extract
PENDING
Infraction / law references in source extract:
  • 109 — BC 3301.2,27-1009(A) FAIL TO SAFEGUARD PERS/PROPERTY AFFECTED BY CONSTRUCTION OP

Record-specific focus: Before choosing a correction or hearing strategy, verify the source allegation concerning failure to safeguard public and property affected by construction operations. atoi, observed constr. site under permit #b00637654-i1-gc. noted ongoing masonry work at exp 4 on unsafe scaffold, pales of stucco.

What this violation means

The allegation concerns a sidewalk shed, scaffold, overhead protection or related temporary construction protection that DOB says did not meet required safety or maintenance conditions.

What may be required to correct the condition

The cited shed/scaffold condition should be inspected against the approved temporary-construction documents and Chapter 33 requirements. Correction may involve immediate repair, lighting, edge protection, anchorage, dimensions, housekeeping or permit/document updates depending on the allegation.

What the OATH hearing may involve

At OATH, dated site photographs, the approved shed/scaffold drawings or permit, inspection logs, contractor records and proof of prompt correction can help establish what condition existed and how it was addressed.

Possible defenses or factual issues worth investigating

Match the inspector's cited location and component to the approved temporary-construction setup, determine whether the condition was transient or ongoing, and verify permit/status information for the protection system. Because the description identifies several physical components or locations, photographs and records should be matched to those specific details rather than submitted as general property evidence.

Documents and evidence that may be useful

  • sidewalk-shed/scaffold permit and approved drawings
  • site photographs from the inspection period
  • daily/site-safety inspection logs
  • contractor repair records
  • DOB inspection/reinspection records
Violation 3

Summons 39194593X — Sidewalk shed / temporary construction protection

Normalized lookup key: 039194593X
OATH hearingNovember 6, 20268:30 AM

What DOB alleges

DOB alleges a defect or code-compliance problem involving sidewalk-shed/scaffold protection. The inspector's description specifically references exposure 4.

Specific record details: exposure 4.

Full violation description from the source extract

MISCELLANEOUS CHAPTER 33 VIOLATIONS. AT TIME OF INSPECTION, OBSERVED ONGOING CONSTR. UNDER NB PERMIT #B00637654-I1-GC. IMPROPER INSTALLATION/USE OF APPROX.12'FT HIGH SUPPORTED SCAFFOLDING AT EXP4. NOTED IMPROPE

Issue date
July 1, 2026
Served date
July 1, 2026
Source violation type
Unknown
Severity
CLASS - 1
Hearing status in source extract
PENDING
Infraction / law references in source extract:
  • 1P7

Record-specific focus: Before choosing a correction or hearing strategy, verify the source allegation concerning at the inspection OBSERVED ONGOING CONSTR. UNDER NB PERMIT #B00637654-I1-GC. IMPROPER INSTALLATION/USE OF APPROX.12'FT HIGH SUPPORTED SCAFFOLDING AT EXP4. NOTED IMPROPE.

What this violation means

The allegation concerns a sidewalk shed, scaffold, overhead protection or related temporary construction protection that DOB says did not meet required safety or maintenance conditions.

What may be required to correct the condition

The cited shed/scaffold condition should be inspected against the approved temporary-construction documents and Chapter 33 requirements. Correction may involve immediate repair, lighting, edge protection, anchorage, dimensions, housekeeping or permit/document updates depending on the allegation.

What the OATH hearing may involve

At OATH, dated site photographs, the approved shed/scaffold drawings or permit, inspection logs, contractor records and proof of prompt correction can help establish what condition existed and how it was addressed.

Possible defenses or factual issues worth investigating

Match the inspector's cited location and component to the approved temporary-construction setup, determine whether the condition was transient or ongoing, and verify permit/status information for the protection system.

Documents and evidence that may be useful

  • sidewalk-shed/scaffold permit and approved drawings
  • site photographs from the inspection period
  • daily/site-safety inspection logs
  • contractor repair records
  • DOB inspection/reinspection records
Property-specific resolution support

How Building Violation LLC may help at 308 14 Street, Brooklyn, NY 11215

For 308 14 Street, Brooklyn, NY 11215, the current source extract points to stop work order compliance, sidewalk shed / temporary construction protection. Because this property has multiple summonses, the practical advantage is coordinating record research, hearing preparation and correction work as one property matter while still tracking each summons separately. Building Violation LLC can scope the relevant record research, OATH hearing preparation/representation, permit or legal-use review, licensed-trade or registered-professional coordination, correction documentation and Certificate of Correction/closeout work where those steps actually apply. Detailed technical research and project work begin only after the applicable scope, authorization and payment are established.

Official government starting points

Verify the current OATH / DOB record

The source extract is a point-in-time record. Hearing dates, hearing status, penalties, correction status, permits and later agency filings can change. Use the official NYC systems below before making a decision or appearing at a hearing.