November 2026 NYC DOB / ECB / OATH public-record review

523-525 Myrtle Avenue, Brooklyn, NY 11205 — November 2026 NYC OATH Hearing & Violation Information

The resolved public-record dataset associates 2 DOB/ECB OATH summonses with 523-525 Myrtle Avenue, Brooklyn, NY 11205. The source records identify sidewalk shed / temporary construction protection and a hearing date of November 17, 2026. The sections below keep the source allegations separate from explanatory analysis so an owner, buyer, realtor, attorney, lender, property manager or contractor can see what the record says, what still needs verification, and what a practical next review could involve.

Sidewalk shed / temporary construction protection

Property and hearing summary

Actual property address
523-525 Myrtle Avenue, Brooklyn, NY 11205
Borough
Brooklyn
BIN
3421882
BBL
3018937505 (3/1893/7505)
Hearing month
November 2026
Violations on this page
2
Verified hearing date(s) in source extract
November 17, 2026
Source extract
September 18, 2026
Source information: This page was compiled from NYC DOB/ECB/OATH public-record information contained in the November 2026 resolved-property dataset and the associated DOB/ECB source extract dated September 18, 2026. Agency records may change after the source data was obtained. Hearing dates, status, penalties, correction status and agency records should be verified with NYC OATH and DOB before relying on this page.

November 2026 hearing summary

ECB/OATH summonsHearing date / timeSeverityRecord category
39543169J
Normalized: 039543169J
November 17, 2026
8:30 AM
CLASS - 2 Sidewalk shed / temporary construction protection
39543171Z
Normalized: 039543171Z
November 17, 2026
8:30 AM
CLASS - 2 Sidewalk shed / temporary construction protection

How the summonses fit together at this property

These summonses form a construction-site compliance cluster rather than a single generic violation. They address different safety, temporary-protection, approved-plan or work-control obligations at the same property. Site records should be organized by inspection date and cited condition so the correction and hearing response for one summons is not mistakenly used for another.

Violation-by-violation record and analysis

Each section first identifies what comes directly from the source extract, then separates general explanatory and strategic considerations that may require current-record research or professional review.

Violation 1

Summons 39543169J — Sidewalk shed / temporary construction protection

Normalized lookup key: 039543169J
OATH hearingNovember 17, 20268:30 AM

What DOB alleges

DOB alleges a defect or code-compliance problem involving sidewalk-shed/scaffold protection. The inspector's description specifically references lighting/illumination and exposure 1.

Specific record details: lighting/illumination, exposure 1.

Full violation description from the source extract

AT 4:50AM OBSERVED STORY 7 BUILDING WITH SWS INSTALLED AT EXP#1 THAT WAS NOT ILLUMINATED AS STIPULATED IN BC3307.6.4.8 CREATES HAZARDOUS CONDITIONS FOR PEDESTRIANS OF SLIPS AND TRIPS DUE TO INADEQUATE LIGHTING

Issue date
August 4, 2025
Served date
August 4, 2025
Source violation type
Construction
Severity
CLASS - 2
Hearing status in source extract
PENDING
Infraction / law references in source extract:
  • 223 — BC 3307.6,27-1021 SIDEWALK SHED DOES NOT MEET CODE SPECIFICATIONS

Record-specific focus: Before choosing a correction or hearing strategy, verify the source allegation concerning at 4:50am observed story 7 building with sws installed at exp#1 that was not illuminated as stipulated in bc3307.6.4.8 creates hazardous conditions for pedestrians of slips and trips due to inadequate lighting.

What this violation means

The allegation concerns a sidewalk shed, scaffold, overhead protection or related temporary construction protection that DOB says did not meet required safety or maintenance conditions.

What may be required to correct the condition

The cited shed/scaffold condition should be inspected against the approved temporary-construction documents and Chapter 33 requirements. Correction may involve immediate repair, lighting, edge protection, anchorage, dimensions, housekeeping or permit/document updates depending on the allegation.

What the OATH hearing may involve

At OATH, dated site photographs, the approved shed/scaffold drawings or permit, inspection logs, contractor records and proof of prompt correction can help establish what condition existed and how it was addressed.

Possible defenses or factual issues worth investigating

Match the inspector's cited location and component to the approved temporary-construction setup, determine whether the condition was transient or ongoing, and verify permit/status information for the protection system.

Documents and evidence that may be useful

  • sidewalk-shed/scaffold permit and approved drawings
  • site photographs from the inspection period
  • daily/site-safety inspection logs
  • contractor repair records
  • DOB inspection/reinspection records
Violation 2

Summons 39543171Z — Sidewalk shed / temporary construction protection

Normalized lookup key: 039543171Z
OATH hearingNovember 17, 20268:30 AM

What DOB alleges

DOB alleges a defect or code-compliance problem involving sidewalk-shed/scaffold protection. The inspector's description specifically references sidewalk shed and exposure 1.

Specific record details: sidewalk shed, exposure 1.

Full violation description from the source extract

OBSERVED SIDEWALK SHED INSTALLED AT EXP# 1 MISSING SIDEWALK SHED PARAPET INFORMATION PANEL CONTRARY TO BC 3301.9.2 MISSING INFORMATION PANEL CAN DELAY RESPONSE IN CASE OF AN EMERGENCY NOT HAVING THE ADDRESS POS

Issue date
August 4, 2025
Served date
August 4, 2025
Source violation type
Construction
Severity
CLASS - 2
Hearing status in source extract
PENDING
Infraction / law references in source extract:
  • 217 — BC 3301.9,27-10009(C) FAIL TO PROVIDE/POST SIGN(S) AT JB SITE PURSUANT TO SUBSEC

Record-specific focus: Before choosing a correction or hearing strategy, verify the source allegation concerning observed sidewalk shed installed at exp# 1 missing sidewalk shed parapet information panel contrary to bc 3301.9.2 missing information panel can delay response in case of an emergency not having the address pos.

What this violation means

The allegation concerns a sidewalk shed, scaffold, overhead protection or related temporary construction protection that DOB says did not meet required safety or maintenance conditions.

What may be required to correct the condition

The cited shed/scaffold condition should be inspected against the approved temporary-construction documents and Chapter 33 requirements. Correction may involve immediate repair, lighting, edge protection, anchorage, dimensions, housekeeping or permit/document updates depending on the allegation.

What the OATH hearing may involve

At OATH, dated site photographs, the approved shed/scaffold drawings or permit, inspection logs, contractor records and proof of prompt correction can help establish what condition existed and how it was addressed.

Possible defenses or factual issues worth investigating

Match the inspector's cited location and component to the approved temporary-construction setup, determine whether the condition was transient or ongoing, and verify permit/status information for the protection system.

Documents and evidence that may be useful

  • sidewalk-shed/scaffold permit and approved drawings
  • site photographs from the inspection period
  • daily/site-safety inspection logs
  • contractor repair records
  • DOB inspection/reinspection records
Property-specific resolution support

How Building Violation LLC may help at 523-525 Myrtle Avenue, Brooklyn, NY 11205

For 523-525 Myrtle Avenue, Brooklyn, NY 11205, the current source extract points to sidewalk shed / temporary construction protection. Because this property has multiple summonses, the practical advantage is coordinating record research, hearing preparation and correction work as one property matter while still tracking each summons separately. Building Violation LLC can scope the relevant record research, OATH hearing preparation/representation, permit or legal-use review, licensed-trade or registered-professional coordination, correction documentation and Certificate of Correction/closeout work where those steps actually apply. Detailed technical research and project work begin only after the applicable scope, authorization and payment are established.

Official government starting points

Verify the current OATH / DOB record

The source extract is a point-in-time record. Hearing dates, hearing status, penalties, correction status, permits and later agency filings can change. Use the official NYC systems below before making a decision or appearing at a hearing.