November 2026 NYC DOB / ECB / OATH public-record review

639-643 Grand Street, Brooklyn, NY 11211 — November 2026 NYC OATH Hearing & Violation Information

The resolved public-record dataset associates 3 DOB/ECB OATH summonses with 639-643 Grand Street, Brooklyn, NY 11211. The source records identify construction-site safety, sidewalk shed / temporary construction protection and a hearing date of November 16, 2026. The sections below keep the source allegations separate from explanatory analysis so an owner, buyer, realtor, attorney, lender, property manager or contractor can see what the record says, what still needs verification, and what a practical next review could involve.

Construction-site safetySidewalk shed / temporary construction protection

Property and hearing summary

Actual property address
639-643 Grand Street, Brooklyn, NY 11211
Borough
Brooklyn
BIN
3332294
BBL
3027810036 (3/2781/36)
Hearing month
November 2026
Violations on this page
3
Verified hearing date(s) in source extract
November 16, 2026
Source extract
September 18, 2026
Source information: This page was compiled from NYC DOB/ECB/OATH public-record information contained in the November 2026 resolved-property dataset and the associated DOB/ECB source extract dated September 18, 2026. Agency records may change after the source data was obtained. Hearing dates, status, penalties, correction status and agency records should be verified with NYC OATH and DOB before relying on this page.

November 2026 hearing summary

ECB/OATH summonsHearing date / timeSeverityRecord category
39556340N
Normalized: 039556340N
November 16, 2026
8:30 AM
CLASS - 1 Construction-site safety
39556341P
Normalized: 039556341P
November 16, 2026
8:30 AM
CLASS - 2 Construction-site safety
39556343Z
Normalized: 039556343Z
November 16, 2026
8:30 AM
CLASS - 2 Sidewalk shed / temporary construction protection

How the summonses fit together at this property

These summonses form a construction-site compliance cluster rather than a single generic violation. They address different safety, temporary-protection, approved-plan or work-control obligations at the same property. Site records should be organized by inspection date and cited condition so the correction and hearing response for one summons is not mistakenly used for another.

Violation-by-violation record and analysis

Each section first identifies what comes directly from the source extract, then separates general explanatory and strategic considerations that may require current-record research or professional review.

Violation 1

Summons 39556340N — Construction-site safety

Normalized lookup key: 039556340N
OATH hearingNovember 16, 20268:30 AM

What DOB alleges

DOB alleges a construction-site safety or safeguarding deficiency.

Record context: source category Construction, severity CLASS - 1, issued July 8, 2026.

Full violation description from the source extract

AT THE TIME OF MY INSPECTION OF ACTIVE SITE -UPON REVIEW OF DOB RECORDS PAA WAS FILLED (B01248951-P1) TO CHANGE FROM 6 STORY TO 11 STORY BUILDING-AND NO SITE SAFETY COORDINATOR/SITE SAFETY MANAGER DESIGNATION W

Issue date
July 8, 2026
Served date
July 8, 2026
Source violation type
Construction
Severity
CLASS - 1
Hearing status in source extract
PENDING
Infraction / law references in source extract:
  • 119 — BC 3310.5,27-1009(D) FAIL TO HAVE SITE SAFETY MGR/COORDINATOR PRESENT AS REQUIRED

Record-specific focus: Before choosing a correction or hearing strategy, verify the source allegation concerning at the time of my inspection of active site -upon review of DOB records paa was filled (b01248951-p1) to change from 6 story to 11 story building-and no site safety coordinator/site safety manager designation w.

What this violation means

This summons concerns construction-site safety, safeguarding or required temporary protections/documents. These cases are highly fact-specific because the cited condition usually relates to a particular phase of construction and location.

What may be required to correct the condition

The cited safety condition should be corrected immediately and checked against the approved site-safety/temporary-construction documents. Depending on the allegation, the responsible contractor, construction superintendent, site safety manager/coordinator, or design professional may need to document the correction.

What the OATH hearing may involve

Dated site photographs, approved safety drawings, logs, daily reports, permit status and records identifying the construction phase can be important at the hearing.

Possible defenses or factual issues worth investigating

Identify the exact construction operation, exposure/location, responsible permit/site-safety roles, and what approved protection was required at the time. Compare the inspector's description with contemporaneous site records.

Documents and evidence that may be useful

  • site-safety plans and temporary-construction drawings
  • daily logs and inspection reports
  • dated photographs/video
  • permit and superintendent/site-safety records
  • proof of correction/reinspection
Violation 2

Summons 39556341P — Construction-site safety

Normalized lookup key: 039556341P
OATH hearingNovember 16, 20268:30 AM

What DOB alleges

DOB alleges a construction-site safety or safeguarding deficiency.

Record context: source category Construction, severity CLASS - 2, issued July 8, 2026.

Full violation description from the source extract

AT THE TIME OF MY INSPECTION UPON CHECKING DOB RECORDS PAA WAS FILLED (B01248951-P1)-TO CHANGE FROM 6 STORY TO 11 STORY NEW BUILDING - NO APPROVED SITE SAFETY PLAN AVAILABLE ON SITE AS REQUIRED BY CODE-(SSP FOR

Issue date
July 8, 2026
Served date
July 8, 2026
Source violation type
Construction
Severity
CLASS - 2
Hearing status in source extract
PENDING
Infraction / law references in source extract:
  • 2F7 — BC 3301.7 (2014 CODE) FAILURE TO MAINTAIN/DISPLAY ON SITE DOCUMENTS REQUIRED BY BC CHAPTER 3

Record-specific focus: Before choosing a correction or hearing strategy, verify the source allegation concerning at the time of my inspection upon checking DOB records paa was filled (b01248951-p1)-to change from 6 story to 11 story new building - no approved site safety plan available on site as required by code-(ssp for.

What this violation means

This summons concerns construction-site safety, safeguarding or required temporary protections/documents. These cases are highly fact-specific because the cited condition usually relates to a particular phase of construction and location.

What may be required to correct the condition

The cited safety condition should be corrected immediately and checked against the approved site-safety/temporary-construction documents. Depending on the allegation, the responsible contractor, construction superintendent, site safety manager/coordinator, or design professional may need to document the correction.

What the OATH hearing may involve

Dated site photographs, approved safety drawings, logs, daily reports, permit status and records identifying the construction phase can be important at the hearing.

Possible defenses or factual issues worth investigating

Identify the exact construction operation, exposure/location, responsible permit/site-safety roles, and what approved protection was required at the time. Compare the inspector's description with contemporaneous site records.

Documents and evidence that may be useful

  • site-safety plans and temporary-construction drawings
  • daily logs and inspection reports
  • dated photographs/video
  • permit and superintendent/site-safety records
  • proof of correction/reinspection
Violation 3

Summons 39556343Z — Sidewalk shed / temporary construction protection

Normalized lookup key: 039556343Z
OATH hearingNovember 16, 20268:30 AM

What DOB alleges

DOB alleges a defect or code-compliance problem involving sidewalk-shed/scaffold protection. The inspector's description specifically references exposure 3.

Specific record details: exposure 3.

Full violation description from the source extract

AT THE TIME OF MY INSPECTION I OBSERVED NEW BUIDING APPROX. 16 FEET HIGH (FORM WORK)-AND NO ADJ PROPERTY PROTECTION/CONTROL ACCESS ZONE/OVERHEAD PROTECTION PROVIDED FOR YARD/PROPERTY AT EXP#3 -STOP ALL WORK 20

Issue date
July 8, 2026
Served date
July 8, 2026
Source violation type
Unknown
Severity
CLASS - 2
Hearing status in source extract
PENDING
Infraction / law references in source extract:
  • 2P3

Record-specific focus: Before choosing a correction or hearing strategy, verify the source allegation concerning observed NEW BUIDING APPROX. 16 FEET HIGH (FORM WORK)-AND NO ADJ PROPERTY PROTECTION/CONTROL ACCESS ZONE/OVERHEAD PROTECTION PROVIDED FOR YARD/PROPERTY AT EXP#3 -STOP ALL WORK 20.

What this violation means

The allegation concerns a sidewalk shed, scaffold, overhead protection or related temporary construction protection that DOB says did not meet required safety or maintenance conditions.

What may be required to correct the condition

The cited shed/scaffold condition should be inspected against the approved temporary-construction documents and Chapter 33 requirements. Correction may involve immediate repair, lighting, edge protection, anchorage, dimensions, housekeeping or permit/document updates depending on the allegation.

What the OATH hearing may involve

At OATH, dated site photographs, the approved shed/scaffold drawings or permit, inspection logs, contractor records and proof of prompt correction can help establish what condition existed and how it was addressed.

Possible defenses or factual issues worth investigating

Match the inspector's cited location and component to the approved temporary-construction setup, determine whether the condition was transient or ongoing, and verify permit/status information for the protection system.

Documents and evidence that may be useful

  • sidewalk-shed/scaffold permit and approved drawings
  • site photographs from the inspection period
  • daily/site-safety inspection logs
  • contractor repair records
  • DOB inspection/reinspection records
Property-specific resolution support

How Building Violation LLC may help at 639-643 Grand Street, Brooklyn, NY 11211

For 639-643 Grand Street, Brooklyn, NY 11211, the current source extract points to construction-site safety, sidewalk shed / temporary construction protection. Because this property has multiple summonses, the practical advantage is coordinating record research, hearing preparation and correction work as one property matter while still tracking each summons separately. Building Violation LLC can scope the relevant record research, OATH hearing preparation/representation, permit or legal-use review, licensed-trade or registered-professional coordination, correction documentation and Certificate of Correction/closeout work where those steps actually apply. Detailed technical research and project work begin only after the applicable scope, authorization and payment are established.

Official government starting points

Verify the current OATH / DOB record

The source extract is a point-in-time record. Hearing dates, hearing status, penalties, correction status, permits and later agency filings can change. Use the official NYC systems below before making a decision or appearing at a hearing.