Summons 39195311N — Work not conforming to approved documents
Normalized lookup key: 039195311NWhat DOB alleges
DOB alleges that field work did not conform to the approved construction documents.
The description also references Stop Work Order ISSUED.
Full violation description from the source extract
PSWO ISSUED FOR WORK DOES NOT CONFORM TO DOCUMENTED APPROVED PLANS ON SITE: ATOI OBSERVED APPROVED PROPOSED FLOOR PLANS WERE ON SITE AND IN COMPLIANCE . STRUCTURAL PLANS FOR THE OBSERVED STEEL BEAM JOIST AND ST
- Issue date
- July 8, 2026
- Served date
- July 8, 2026
- Source violation type
- Construction
- Severity
- CLASS - 1
- Hearing status in source extract
- PENDING
- 114 — 28-105.12.2 WK DOESN'T CONFORM TO APPRV CONST DOC/AMENDS IN MANUF DIST RES USE
Record-specific focus: Before choosing a correction or hearing strategy, verify the source allegation concerning pswo issued for work does not conform to documented approved plans on site: atoi observed approved proposed floor plans were on site and in compliance . structural plans for the observed steel beam joist and st.
What this violation means
DOB is alleging that work in progress did not match the approved construction documents or amendments. Even permitted work can be cited if the field condition departs materially from the approved plan set.
What may be required to correct the condition
The field condition should be compared line-by-line with the approved plans. Depending on what is found, the project may need to be restored to the approved design or the plans may need to be amended and re-approved before the work continues or is signed off.
What the OATH hearing may involve
Hearing evidence can include the approved plan sheets in effect on the inspection date, revision history, photographs of the field condition, professional reports and proof that the discrepancy was corrected or formally amended.
Possible defenses or factual issues worth investigating
Identify the exact plan sheet/detail DOB says was violated, confirm which approved set controlled on the inspection date, and determine whether the field condition was temporary, incomplete, or actually inconsistent with the approval. Cross-reference the other order/summons number cited in the inspector narrative rather than reviewing this record in isolation.
Documents and evidence that may be useful
- DOB-approved construction documents and amendments
- field photographs
- architect/engineer field reports
- permit and inspection history
- revised approvals or restoration evidence