Normalized ten-character lookup: 039547664P (infraction 2P7)
Source allegation and actual cited law
The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. The exact cited location/component should be confirmed against the original inspection record.
Inspector narrative as preserved in source data — potentially incomplete
BC 3303.3 AT TIME OF INSPECTION OF A 6 STORIES BUILDING UNDER DEMOLITION APPROXIMATELY 13,200 SQ FEET SITE WAS UNDER LOCK AND KEY AND THERE WAS NO CONSTRUCTION ACTIVITIES UPON SHOUTING AND BANGING ON DOORS AND
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
- 2P7
- Issue date
- December 6, 2025
- Service date
- December 6, 2025
- Source severity
- CLASS - 2
- Source violation type
- Unknown
- Hearing status in extract
- DEFAULT
- DOB/ECB status in extract
- ACTIVE
- Correction certification in extract
- NO COMPLIANCE RECORDED
- Penalty field in extract
- $2,530.00
- Balance field in extract
- $2,530.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
What the alleged violation means at 104 Boerum Place, Brooklyn, NY 11201
Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “BC 3303.3 AT TIME OF INSPECTION OF A 6 STORIES BUILDING UNDER DEMOLITION APPROXIMATELY 13,200 SQ FEET SITE WAS UNDER LOCK AND KEY AND THERE WAS NO CONSTRUC…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039547664P.
- Whether construction was underway and the cited safety duty applied at the relevant time
- Whether required postings, logs, plans or supervision were in place
- Whether the cited conditions or documents belonged to this job site and respondent
- Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
- Correct active site hazards immediately and involve the qualified site safety/contractor team.
- Update required plans, safety controls, postings, inspections or records and document remediation.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
- site safety plan, permits and approved construction documents
- daily inspection logs, toolbox talks and supervisory assignments
- dated job-site photos with exposure or floor
- contractor correction records and agency inspection reports
- property-matching review notes and the original summons image to reconcile identifiers
Default recorded in source: what to verify before acting
A DEFAULT entry can affect procedural options; determine when and how default was entered and consult official OATH rules about any available vacate-default application. Do not assume the source-listed December date is still a live hearing.
Need a summons-specific action plan? For 039547664P, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.
Request help with site safety / construction operations at 104 Boerum Place, Brooklyn, NY 11201