The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. Key locations/components named in the source: apartment or dwelling unit.
Inspector narrative as preserved in source data — potentially incomplete
AT TIME OF INSPECTION OBSERVED 5 STORY 10 UNIT ALTERATION WITH NO ACTIVE CONSTRUCTION SUPERINTENDENT. WORK BEING PERFORMED WITHOUT A CS CREATES UNSAFE WORK ENVIRONMENT AND HAZARDS. CS IS REQUIRED FOR OVERSEEING
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
- 1G6 — BC 3301.13.3 FAILURE TO DESIGNATE AND/OR HAVE A CONSTRUCTION SUPERINTENDENT PRESENT
- Issue date
- August 27, 2026
- Service date
- August 27, 2026
- Source severity
- CLASS - 1
- Source violation type
- Site Safety
- Hearing status in extract
- PENDING
- DOB/ECB status in extract
- ACTIVE
- Correction certification in extract
- Not recorded
- Penalty field in extract
- $10,000.00
- Balance field in extract
- $10,000.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.
What the alleged violation means at 1263 Park Avenue, Manhattan, NY 10029
Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. Key locations/components named in the source: apartment or dwelling unit. Record-specific inspection detail: Inspector text begins: “AT TIME OF INSPECTION OBSERVED 5 STORY 10 UNIT ALTERATION WITH NO ACTIVE CONSTRUCTION SUPERINTENDENT. WORK BEING PERFORMED WITHOUT A CS CREATES UNSAFE WORK…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039558445Z.
- Whether construction was underway and the cited safety duty applied at the relevant time
- Whether required postings, logs, plans or supervision were in place
- Whether the cited conditions or documents belonged to this job site and respondent
- Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
- Correct active site hazards immediately and involve the qualified site safety/contractor team.
- Update required plans, safety controls, postings, inspections or records and document remediation.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
- approved unit layout and relevant lawful occupancy records
- site safety plan, permits and approved construction documents
- daily inspection logs, toolbox talks and supervisory assignments
- dated job-site photos with exposure or floor
- contractor correction records and agency inspection reports
Pending in source: what to verify before acting
The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.
Need a summons-specific action plan? For 039558445Z, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.