The November 10, 2026 verified-property dataset associates 7 DOB/ECB/OATH summonses with 154 Penn Street, Brooklyn, NY 11211 and source-listed dates December 28, 2026, December 31, 2026. Recorded concerns include certificate of correction / order noncompliance, construction fence / site protection. Below are the exact source identifiers and allegations, followed by issue-specific defense checks, correction options and evidence needed for a responsible review.
Certificate of Correction / order noncomplianceConstruction fence / site protection
Verified premises, hearing and enforcement snapshot
Verified premises address
154 Penn Street, Brooklyn, NY 11211
Borough
Brooklyn
BIN
3060777
BBL
3022180027
Source summonses
7
Hearing dates in source
December 28, 2026, December 31, 2026
Source snapshot
November 10, 2026
Address verification method
PAD exact BIN
Official PAD aliases and building ranges: 154 PENN STREET
Source and authorship: Building Violation LLC prepared this independent property-record explanation using a November 10, 2026 DOB/OATH source extract and verified BIN/BBL property matching. The issue analysis is editorial guidance generated from source allegations and cited laws, not a new inspection or legal determination. The source sometimes abbreviates inspector text. This is not a live OATH calendar; verify dates, appearance instructions, dispositions, monetary fields and compliance directly with NYC.
What merits immediate verification: 7 default-status record(s) in the source; one or more Class 1 source allegations; one or more possibly shortened inspector narratives. Read the current OATH and DOB records before acting.
What is the December 2026 OATH hearing for at 154 Penn Street, Brooklyn, NY 11211?
The uploaded record lists 7 summonses, including 035649842K (certificate of correction / order noncompliance), 035649843M (certificate of correction / order noncompliance), 035449670R (certificate of correction / order noncompliance), 035449671Z (certificate of correction / order noncompliance) and additional tickets. The source-listed hearing dates: December 28, 2026, December 31, 2026. These are allegations and dated extract fields; the current official notices determine the actual appearance obligation and disposition.
What should the owner or respondent do first?
Verify the status of each normalized summons with OATH, obtain the complete inspector narrative and cited order/permit records, address immediate hazards, and assemble dated evidence matched to each allegation. A Certificate of Correction or other DOB closeout may remain necessary even after an OATH hearing or payment.
How the 7 recorded summonses relate at 154 Penn Street, Brooklyn, NY 11211
The verified property matching links 7 distinct summonses to 154 Penn Street, Brooklyn, NY 11211. They may share a property and documents, but the dataset does not establish that they arose from one inspection, one condition or one respondent. Review each summons independently.
Certificate of Correction / order noncompliance (5): source summons 035649842K, 035649843M, 035449670R, 035449671Z, 035449672K. These charges may share a single technical investigation or corrected condition only if the actual cited locations and inspection facts match.
Construction fence / site protection (2): source summons 039529092J, 039529093L. These charges may share a single technical investigation or corrected condition only if the actual cited locations and inspection facts match.
Shared source issue date: 3 summonses list November 6, 2020 as their issue date. Compare inspection times, sites and inspector observations before deciding whether they are factually connected.
Shared source issue date: 2 summonses list May 29, 2024 as their issue date. Compare inspection times, sites and inspector observations before deciding whether they are factually connected.
Shared source issue date: 2 summonses list August 27, 2024 as their issue date. Compare inspection times, sites and inspector observations before deciding whether they are factually connected.
More than one source-listed hearing date: December 28, 2026, December 31, 2026. Do not treat one appearance or adjournment as disposing of every summons; confirm each date separately.
Coordination checklist: build one property evidence folder with a separate subfolder, hearing/disposition verification and correction tracking sheet for each normalized summons number. Share drawings or photos across tickets only when the same physical facts are documented.
Each violation: allegation, defense issues, correction strategy and supporting documents
Source wording is distinguished from potential actions. These are investigatory prompts, not legal advice, guaranteed defenses or promises of DOB acceptance.
Summons 1 of the source-linked property
Certificate of Correction / order noncompliance — ECB/OATH summons 35649842K
DOB alleges noncompliance with an earlier order or a requirement to submit correction documentation. Key locations/components named in the source: cellar or basement area, windows.
Inspector narrative as preserved in source data — potentially incomplete
FAILURE TO COMPLY WORK PERFORMED WITHOUT PERMIT.WINDOW ENTED/UNINSPECTED UNDERPINNING INSTALLED AT EXPOSURES 2 AND 4.THE CELLAR AND YARD WERE EXCAVATED.THIS UNPERMITTED WORK POSES A HAZARD AND DEFAULTED IN THE
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
187 — 28-201.1 UNLAWFUL ACTS. FAILURE TO COMPLY WITH AN ORDER OF THE COMMISSIONER
Issue date
August 27, 2024
Service date
September 12, 2024
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
DEFAULT
DOB/ECB status in extract
ACTIVE
Correction certification in extract
NO COMPLIANCE RECORDED
Penalty field in extract
$25,000.00
Balance field in extract
$25,000.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 154 Penn Street, Brooklyn, NY 11211
Trace this charge to the underlying summons or commissioner’s directive. A repair or hearing disposition is not necessarily the same as DOB accepting a required Certificate of Correction. Key locations/components named in the source: cellar or basement area, windows. Record-specific inspection detail: Inspector text begins: “FAILURE TO COMPLY WORK PERFORMED WITHOUT PERMIT.WINDOW ENTED/UNINSPECTED UNDERPINNING INSTALLED AT EXPOSURES 2 AND 4.THE CELLAR AND YARD WERE EXCAVATED.THI…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 035649842K.
Whether a Certificate of Correction or other response was filed and accepted before the cited deadline
Whether the prior order references the correct premises and responsible party
Whether the earlier cited condition has been corrected and what current DOB closeout record shows
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Retrieve the original violation, deadline and agency compliance requirements.
Complete remaining physical remediation and submit the proper correction package with competent proof and required professional attestations.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
dated cellar/basement photos and approved basement floor plan
window photographs and approved facade or window work plans
underlying summons, order and deadline notice
DOB Certificate of Correction filings and acknowledgments
before/after dated photographs and signed affidavits where required
contractor or licensed-professional invoices and sign-offs
Default recorded in source: what to verify before acting
A DEFAULT entry can affect procedural options; determine when and how default was entered and consult official OATH rules about any available vacate-default application. Do not assume the source-listed December date is still a live hearing.
Need a summons-specific action plan? For 035649842K, Building Violation LLC can scope underlying-case research, correction paperwork and DOB compliance closeout after reviewing the actual notice and current DOB/OATH record.
DOB alleges noncompliance with an earlier order or a requirement to submit correction documentation. Key locations/components named in the source: roof or rooftop.
Inspector narrative as preserved in source data — potentially incomplete
FAILURE TO COMPLY WORK PERFORMED WITHOUT PERMIT.EXPOSURE 3 HAS BEEN COMPLETELY REMOVED EXISTING FRAMING REMOVED AT ALL LEVELS EXCEPT THE ROOF NEW UNDOCUMENTED/UNINSPECTED FRAMING INSTALLED AT LEVELS 1 AND 2.THI
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
187 — 28-201.1 UNLAWFUL ACTS. FAILURE TO COMPLY WITH AN ORDER OF THE COMMISSIONER
Issue date
August 27, 2024
Service date
September 12, 2024
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
DEFAULT
DOB/ECB status in extract
ACTIVE
Correction certification in extract
NO COMPLIANCE RECORDED
Penalty field in extract
$25,000.00
Balance field in extract
$25,000.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 154 Penn Street, Brooklyn, NY 11211
Trace this charge to the underlying summons or commissioner’s directive. A repair or hearing disposition is not necessarily the same as DOB accepting a required Certificate of Correction. Key locations/components named in the source: roof or rooftop. Record-specific inspection detail: Inspector text begins: “FAILURE TO COMPLY WORK PERFORMED WITHOUT PERMIT.EXPOSURE 3 HAS BEEN COMPLETELY REMOVED EXISTING FRAMING REMOVED AT ALL LEVELS EXCEPT THE ROOF NEW UNDOCUMEN…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 035649843M.
Whether a Certificate of Correction or other response was filed and accepted before the cited deadline
Whether the prior order references the correct premises and responsible party
Whether the earlier cited condition has been corrected and what current DOB closeout record shows
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Retrieve the original violation, deadline and agency compliance requirements.
Complete remaining physical remediation and submit the proper correction package with competent proof and required professional attestations.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
dated roof photographs and any roofing/equipment permit documents
underlying summons, order and deadline notice
DOB Certificate of Correction filings and acknowledgments
before/after dated photographs and signed affidavits where required
contractor or licensed-professional invoices and sign-offs
Default recorded in source: what to verify before acting
A DEFAULT entry can affect procedural options; determine when and how default was entered and consult official OATH rules about any available vacate-default application. Do not assume the source-listed December date is still a live hearing.
Need a summons-specific action plan? For 035649843M, Building Violation LLC can scope underlying-case research, correction paperwork and DOB compliance closeout after reviewing the actual notice and current DOB/OATH record.
DOB alleges noncompliance with an earlier order or a requirement to submit correction documentation. Key locations/components named in the source: cellar or basement area.
Inspector narrative as preserved in source data — potentially incomplete
FAILURE TO COMPLY WORK PERFORMED WITHOUT PERMIT UNDOCUMENTED/UN-INSPECTED UNDERPINNING INSTALLED AT EXPOSURES 2 AND 4.THE CELLAR AND YARD WERE EXCAVATED.THIS UNPERMITTED WORK POSES A HAZARD AND RESULTED IN THE
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
187 — 28-201.1 UNLAWFUL ACTS. FAILURE TO COMPLY WITH AN ORDER OF THE COMMISSIONER
Issue date
November 6, 2020
Service date
December 21, 2020
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
DEFAULT
DOB/ECB status in extract
ACTIVE
Correction certification in extract
NO COMPLIANCE RECORDED
Penalty field in extract
$12,500.00
Balance field in extract
$12,500.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 154 Penn Street, Brooklyn, NY 11211
Trace this charge to the underlying summons or commissioner’s directive. A repair or hearing disposition is not necessarily the same as DOB accepting a required Certificate of Correction. Key locations/components named in the source: cellar or basement area. Record-specific inspection detail: Inspector text begins: “FAILURE TO COMPLY WORK PERFORMED WITHOUT PERMIT UNDOCUMENTED/UN-INSPECTED UNDERPINNING INSTALLED AT EXPOSURES 2 AND 4.THE CELLAR AND YARD WERE EXCAVATED.TH…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 035449670R.
Whether a Certificate of Correction or other response was filed and accepted before the cited deadline
Whether the prior order references the correct premises and responsible party
Whether the earlier cited condition has been corrected and what current DOB closeout record shows
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Retrieve the original violation, deadline and agency compliance requirements.
Complete remaining physical remediation and submit the proper correction package with competent proof and required professional attestations.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
dated cellar/basement photos and approved basement floor plan
underlying summons, order and deadline notice
DOB Certificate of Correction filings and acknowledgments
before/after dated photographs and signed affidavits where required
contractor or licensed-professional invoices and sign-offs
Default recorded in source: what to verify before acting
A DEFAULT entry can affect procedural options; determine when and how default was entered and consult official OATH rules about any available vacate-default application. Do not assume the source-listed December date is still a live hearing.
Need a summons-specific action plan? For 035449670R, Building Violation LLC can scope underlying-case research, correction paperwork and DOB compliance closeout after reviewing the actual notice and current DOB/OATH record.
DOB alleges noncompliance with an earlier order or a requirement to submit correction documentation. Key locations/components named in the source: roof or rooftop.
Inspector narrative as preserved in source data — potentially incomplete
FAILURE TO COMPLY WORK PERFORMED ONSITE WITHOUT A PERMIT.EXPOSURE 3 HAS BEEN COMPLETELY REMOVED.EXISTING FRAMING REMOVAL AT ALL LEVELS EXCEPT ROOF NEW UNDERPINNING,UN-INSPECTED FRAMING INSTALLED AT LEVELS 1&2.T
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
187 — 28-201.1 UNLAWFUL ACTS. FAILURE TO COMPLY WITH AN ORDER OF THE COMMISSIONER
Issue date
November 6, 2020
Service date
December 21, 2020
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
DEFAULT
DOB/ECB status in extract
ACTIVE
Correction certification in extract
NO COMPLIANCE RECORDED
Penalty field in extract
$12,500.00
Balance field in extract
$12,500.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 154 Penn Street, Brooklyn, NY 11211
Trace this charge to the underlying summons or commissioner’s directive. A repair or hearing disposition is not necessarily the same as DOB accepting a required Certificate of Correction. Key locations/components named in the source: roof or rooftop. Record-specific inspection detail: Inspector text begins: “FAILURE TO COMPLY WORK PERFORMED ONSITE WITHOUT A PERMIT.EXPOSURE 3 HAS BEEN COMPLETELY REMOVED.EXISTING FRAMING REMOVAL AT ALL LEVELS EXCEPT ROOF NEW UNDE…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 035449671Z.
Whether a Certificate of Correction or other response was filed and accepted before the cited deadline
Whether the prior order references the correct premises and responsible party
Whether the earlier cited condition has been corrected and what current DOB closeout record shows
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Retrieve the original violation, deadline and agency compliance requirements.
Complete remaining physical remediation and submit the proper correction package with competent proof and required professional attestations.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
dated roof photographs and any roofing/equipment permit documents
underlying summons, order and deadline notice
DOB Certificate of Correction filings and acknowledgments
before/after dated photographs and signed affidavits where required
contractor or licensed-professional invoices and sign-offs
Default recorded in source: what to verify before acting
A DEFAULT entry can affect procedural options; determine when and how default was entered and consult official OATH rules about any available vacate-default application. Do not assume the source-listed December date is still a live hearing.
Need a summons-specific action plan? For 035449671Z, Building Violation LLC can scope underlying-case research, correction paperwork and DOB compliance closeout after reviewing the actual notice and current DOB/OATH record.
DOB alleges noncompliance with an earlier order or a requirement to submit correction documentation. Key locations/components named in the source: cellar or basement area.
Inspector narrative as preserved in source data — potentially incomplete
FAILURE TO COMPLY WORK PERFORMED ONSITE WITHOUT PERMIT.UNDOCUMENTED/UN-INSPECRED UNDERPINNING INSTALLED AT EXPOSURES 2 AND 4.THE CELLAR AND YARD WERE EXCAVATED.EXPOSURE 3 WAS COMPLETELY REMOVED.EXISITING FRAMIN
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
187 — 28-201.1 UNLAWFUL ACTS. FAILURE TO COMPLY WITH AN ORDER OF THE COMMISSIONER
Issue date
November 6, 2020
Service date
December 21, 2020
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
DEFAULT
DOB/ECB status in extract
ACTIVE
Correction certification in extract
NO COMPLIANCE RECORDED
Penalty field in extract
$12,500.00
Balance field in extract
$12,500.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 154 Penn Street, Brooklyn, NY 11211
Trace this charge to the underlying summons or commissioner’s directive. A repair or hearing disposition is not necessarily the same as DOB accepting a required Certificate of Correction. Key locations/components named in the source: cellar or basement area. Record-specific inspection detail: Inspector text begins: “FAILURE TO COMPLY WORK PERFORMED ONSITE WITHOUT PERMIT.UNDOCUMENTED/UN-INSPECRED UNDERPINNING INSTALLED AT EXPOSURES 2 AND 4.THE CELLAR AND YARD WERE EXCAV…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 035449672K.
Whether a Certificate of Correction or other response was filed and accepted before the cited deadline
Whether the prior order references the correct premises and responsible party
Whether the earlier cited condition has been corrected and what current DOB closeout record shows
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Retrieve the original violation, deadline and agency compliance requirements.
Complete remaining physical remediation and submit the proper correction package with competent proof and required professional attestations.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
dated cellar/basement photos and approved basement floor plan
underlying summons, order and deadline notice
DOB Certificate of Correction filings and acknowledgments
before/after dated photographs and signed affidavits where required
contractor or licensed-professional invoices and sign-offs
Default recorded in source: what to verify before acting
A DEFAULT entry can affect procedural options; determine when and how default was entered and consult official OATH rules about any available vacate-default application. Do not assume the source-listed December date is still a live hearing.
Need a summons-specific action plan? For 035449672K, Building Violation LLC can scope underlying-case research, correction paperwork and DOB compliance closeout after reviewing the actual notice and current DOB/OATH record.
The alleged condition involves a construction fence, site enclosure or required pedestrian protection. Key locations/components named in the source: construction fence or enclosure, structural framing.
Inspector narrative as preserved in source data — potentially incomplete
OBSERVED AT TIME OF INSPECTION OF A FULLY VACATE BUILDING WITH SEVERE STRUCTURAL ISSUES. CONSTRUCTION FENCE AT EXPOSURE 1 SIDES OF CONSTRUCTION FENCE FACING ADJACENT PROPERTIES ARE MISSING POSING A HAZARD TO TH
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
109 — BC 3301.2,27-1009(A) FAIL TO SAFEGUARD PERS/PROPERTY AFFECTED BY CONSTRUCTION OP
Issue date
May 29, 2024
Service date
May 29, 2024
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
DEFAULT
DOB/ECB status in extract
ACTIVE
Correction certification in extract
NO COMPLIANCE RECORDED
Penalty field in extract
$25,000.00
Balance field in extract
$25,000.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 154 Penn Street, Brooklyn, NY 11211
Compare the exact fence opening, location, dimensions or protection feature described with approved safety plans and site conditions at the time of inspection. Key locations/components named in the source: construction fence or enclosure, structural framing. Record-specific inspection detail: Inspector text begins: “OBSERVED AT TIME OF INSPECTION OF A FULLY VACATE BUILDING WITH SEVERE STRUCTURAL ISSUES. CONSTRUCTION FENCE AT EXPOSURE 1 SIDES OF CONSTRUCTION FENCE FACIN…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039529092J.
Whether the cited condition existed at the exact exposure or location alleged
Whether the protection system and permit met the requirements applicable to this site
Whether contemporaneous site or contractor records contradict or contextualize the alleged defect
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Address unsafe public access or exposed hazards immediately.
Repair or replace required fences, barriers, signage or site protection and secure any associated permits/inspection evidence.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
site-fence photos, dimensions and inspection log
approved framing plans and structural engineer assessment
site safety or construction fence drawings/permits
dated photographs showing the cited exposure and dimensions
daily inspection logs and contractor repair tickets
documented reinspection or sign-off where required
Default recorded in source: what to verify before acting
A DEFAULT entry can affect procedural options; determine when and how default was entered and consult official OATH rules about any available vacate-default application. Do not assume the source-listed December date is still a live hearing.
Need a summons-specific action plan? For 039529092J, Building Violation LLC can scope site-safety violation response and fence/protection correction coordination after reviewing the actual notice and current DOB/OATH record.
The alleged condition involves a construction fence, site enclosure or required pedestrian protection. Key locations/components named in the source: construction fence or enclosure.
Inspector narrative as preserved in source data
OBSERVED CONSTRUCTION FENCE AT EXPOSURE 1 INSTALLED WITH NO PERMIT ON RECORD. CONSTRUCTION FENCE MISSING SIDE OF FENCE NEXT TO 156 & 152 PENN STREET OF BUILDING
This is the narrative supplied in the dataset; verify it against the actual signed summons and inspector attachments.
Recorded infraction numbers and cited legal provisions:
2L1 — 28-105.1 FAILURE TO OBTAIN A TEMPORARY CONSTRUCTION PERMIT PRIOR TO INSTALLATIO
Issue date
May 29, 2024
Service date
May 29, 2024
Source severity
CLASS - 2
Source violation type
Unknown
Hearing status in extract
DEFAULT
DOB/ECB status in extract
ACTIVE
Correction certification in extract
NO COMPLIANCE RECORDED
Penalty field in extract
$6,250.00
Balance field in extract
$6,250.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 154 Penn Street, Brooklyn, NY 11211
Compare the exact fence opening, location, dimensions or protection feature described with approved safety plans and site conditions at the time of inspection. Key locations/components named in the source: construction fence or enclosure. Record-specific inspection detail: Inspector text begins: “OBSERVED CONSTRUCTION FENCE AT EXPOSURE 1 INSTALLED WITH NO PERMIT ON RECORD. CONSTRUCTION FENCE MISSING SIDE OF FENCE NEXT TO 156 & 152 PENN STREET OF BUI…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039529093L.
Whether the cited condition existed at the exact exposure or location alleged
Whether the protection system and permit met the requirements applicable to this site
Whether contemporaneous site or contractor records contradict or contextualize the alleged defect
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Address unsafe public access or exposed hazards immediately.
Repair or replace required fences, barriers, signage or site protection and secure any associated permits/inspection evidence.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
site-fence photos, dimensions and inspection log
site safety or construction fence drawings/permits
dated photographs showing the cited exposure and dimensions
daily inspection logs and contractor repair tickets
documented reinspection or sign-off where required
Default recorded in source: what to verify before acting
A DEFAULT entry can affect procedural options; determine when and how default was entered and consult official OATH rules about any available vacate-default application. Do not assume the source-listed December date is still a live hearing.
Need a summons-specific action plan? For 039529093L, Building Violation LLC can scope site-safety violation response and fence/protection correction coordination after reviewing the actual notice and current DOB/OATH record.
Resolve the actual issue at 154 Penn Street, Brooklyn, NY 11211 — not just the summons number
For this property, start with certificate of correction / order noncompliance and 1 additional issue categories. Building Violation LLC can assess an authorized paid scope for OATH hearing preparation/representation, source-record research and correction coordination appropriate to the individual allegations. A hearing defense and a DOB compliance closeout may both be necessary.
Certificate of Correction / order noncompliance (5 source summonses): Underlying-case research, correction paperwork and DOB compliance closeout.
Construction fence / site protection (2 source summonses): Site-safety violation response and fence/protection correction coordination.
What to send for an assessment: Bring the original summonses, current OATH notices, available DOB records and photos tied to the alleged condition. The source-listed hearing dates: December 28, 2026, December 31, 2026.
Services may require separate licensed-trade, architect/engineer or attorney involvement. No outcome, penalty reduction, permit or agency approval is guaranteed; professional fees and scope are confirmed before work.
This is a point-in-time source extract, not a live court calendar. Confirm the date, appearance method, hearing status, penalties and correction requirements directly with the government before taking action.
Important: This private-service page is not affiliated with NYC OATH or DOB, does not establish guilt or innocence and is not legal advice. Building Violation LLC may provide authorized non-attorney OATH representation and violation-resolution coordination within its permitted scope. Different proceedings can require an attorney or licensed professional. The source field named PENALITY_IMPOSED is shown for transparency but does not prove a presently payable adjudicated amount.