NYC DOB / ECB / OATH hearings · verified property resolution

168 State Street, Brooklyn, NY 11201 — Stop-work order / continued work and December 2026 OATH Hearing Details

The November 10, 2026 verified-property dataset associates 3 DOB/ECB/OATH summonses with 168 State Street, Brooklyn, NY 11201 and source-listed date December 9, 2026. Recorded concerns include stop-work order / continued work, site safety / construction operations. Below are the exact source identifiers and allegations, followed by issue-specific defense checks, correction options and evidence needed for a responsible review.

Stop-work order / continued workSite safety / construction operations

Verified premises, hearing and enforcement snapshot

Verified premises address
168 State Street, Brooklyn, NY 11201
Borough
Brooklyn
BIN
3002783
BBL
3002760029
Source summonses
3
Hearing dates in source
December 9, 2026
Source snapshot
November 10, 2026
Address verification method
PAD exact BIN

Official PAD aliases and building ranges: 168 STATE STREET

Source and authorship: Building Violation LLC prepared this independent property-record explanation using a November 10, 2026 DOB/OATH source extract and verified BIN/BBL property matching. The issue analysis is editorial guidance generated from source allegations and cited laws, not a new inspection or legal determination. The source sometimes abbreviates inspector text. This is not a live OATH calendar; verify dates, appearance instructions, dispositions, monetary fields and compliance directly with NYC.

What merits immediate verification: one or more Class 1 source allegations. Read the current OATH and DOB records before acting.

What is the December 2026 OATH hearing for at 168 State Street, Brooklyn, NY 11201?

The uploaded record lists 3 summonses, including 039206674N (site safety / construction operations), 039206675P (stop-work order / continued work), 039206691P (stop-work order / continued work). The source-listed hearing date: December 9, 2026. These are allegations and dated extract fields; the current official notices determine the actual appearance obligation and disposition.

What should the owner or respondent do first?

Verify the status of each normalized summons with OATH, obtain the complete inspector narrative and cited order/permit records, address immediate hazards, and assemble dated evidence matched to each allegation. A Certificate of Correction or other DOB closeout may remain necessary even after an OATH hearing or payment.

December 2026 summonses and listed hearing times

Summons / lookupSource hearing date / timeSeverityRecorded subjectSource disposition
39206674N
039206674N
8:30 AM
CLASS - 1Site safety / construction operationsPENDING
39206675P
039206675P
9:30 AM
CLASS - 1Stop-work order / continued workPENDING
39206691P
039206691P
9:30 AM
CLASS - 2Stop-work order / continued workPENDING

How the 3 recorded summonses relate at 168 State Street, Brooklyn, NY 11201

The verified property matching links 3 distinct summonses to 168 State Street, Brooklyn, NY 11201. They may share a property and documents, but the dataset does not establish that they arose from one inspection, one condition or one respondent. Review each summons independently.

Stop-work order / continued work (2): source summons 039206675P, 039206691P. These charges may share a single technical investigation or corrected condition only if the actual cited locations and inspection facts match.

Site safety / construction operations (1): source summons 039206674N. Check this charge separately, even when its documents can be gathered with other property records.

Shared source issue date: 3 summonses list October 5, 2026 as their issue date. Compare inspection times, sites and inspector observations before deciding whether they are factually connected.

Coordination checklist: build one property evidence folder with a separate subfolder, hearing/disposition verification and correction tracking sheet for each normalized summons number. Share drawings or photos across tickets only when the same physical facts are documented.

Each violation: allegation, defense issues, correction strategy and supporting documents

Source wording is distinguished from potential actions. These are investigatory prompts, not legal advice, guaranteed defenses or promises of DOB acceptance.

Summons 1 of the source-linked property

Site safety / construction operations — ECB/OATH summons 39206674N

Normalized ten-character lookup: 039206674N (infraction 115)

November 10 source-listed hearing8:30 AM

Source allegation and actual cited law

The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. Key locations/components named in the source: cellar or basement area, stairs or landings.

Inspector narrative as preserved in source data

ATOI OBSERVED REMOVAL OF 1ST-FLR-TO-CELLAR STAIRCASE, NO GUARDRAILS INSTALLED AT OPENING LEADING TO REMOVED STAIRCASE, CREATING APRX. 8-FT FALL HAZARD. VIOLATION ISSUED., PROVIDE GUARD RAILS

This is the narrative supplied in the dataset; verify it against the actual signed summons and inspector attachments.

Recorded infraction numbers and cited legal provisions:
  • 115 — BC 3301.2,27-1009(A) FAILURE TO INSTITUTE/MAINTAIN SAFETY EQUIPMENT MEASURES OR TEMPORARY
Issue date
October 5, 2026
Service date
October 5, 2026
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$5,000.00
Balance field in extract
$5,000.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.

What the alleged violation means at 168 State Street, Brooklyn, NY 11201

Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. Key locations/components named in the source: cellar or basement area, stairs or landings. Record-specific inspection detail: Inspector text begins: “ATOI OBSERVED REMOVAL OF 1ST-FLR-TO-CELLAR STAIRCASE, NO GUARDRAILS INSTALLED AT OPENING LEADING TO REMOVED STAIRCASE, CREATING APRX. 8-FT FALL HAZARD. VIO…”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 039206674N.

  • Whether construction was underway and the cited safety duty applied at the relevant time
  • Whether required postings, logs, plans or supervision were in place
  • Whether the cited conditions or documents belonged to this job site and respondent
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Correct active site hazards immediately and involve the qualified site safety/contractor team.
  • Update required plans, safety controls, postings, inspections or records and document remediation.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • dated cellar/basement photos and approved basement floor plan
  • stair/landing measurements and dated photos or approved egress plans
  • site safety plan, permits and approved construction documents
  • daily inspection logs, toolbox talks and supervisory assignments
  • dated job-site photos with exposure or floor
  • contractor correction records and agency inspection reports

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 039206674N, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.

Request help with site safety / construction operations at 168 State Street, Brooklyn, NY 11201
Summons 2 of the source-linked property

Stop-work order / continued work — ECB/OATH summons 39206675P

Normalized ten-character lookup: 039206675P (infraction 101)

November 10 source-listed hearing9:30 AM

Source allegation and actual cited law

The record concerns an alleged stop-work-order violation, continued work or interference with a posted stop-work notice. Key locations/components named in the source: cellar or basement area, stairs or landings.

Inspector narrative as preserved in source data

ATOI OBSERVED REMOVAL OF 1ST-FLOOR-TO-CELLAR STAIRCASE, ENTIRE CELLAR CONCRETE SLAB, AND PARTIAL CELLAR EXTERIOR STAIRCASE. WORK APRX.50% COMPLETE. NO PERMIT FOUND IN DOB RECORDS. PSWO ISSUED., OBTAIN PERMIT

This is the narrative supplied in the dataset; verify it against the actual signed summons and inspector attachments.

Recorded infraction numbers and cited legal provisions:
  • 101 — 28-105.1 WORK WITHOUT A PERMIT
Issue date
October 5, 2026
Service date
October 5, 2026
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$2,500.00
Balance field in extract
$2,500.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.

What the alleged violation means at 168 State Street, Brooklyn, NY 11201

Find the specific stop-work order, its geographic and work-scope restrictions, and the inspection dates. A partial stop-work order may not affect all work equally; the actual written order governs. Key locations/components named in the source: cellar or basement area, stairs or landings. Record-specific inspection detail: Inspector text begins: “ATOI OBSERVED REMOVAL OF 1ST-FLOOR-TO-CELLAR STAIRCASE, ENTIRE CELLAR CONCRETE SLAB, AND PARTIAL CELLAR EXTERIOR STAIRCASE. WORK APRX.50% COMPLETE. NO PERM…”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 039206675P.

  • Whether the work observed was covered by the order
  • Whether a rescission, partial lift, or approved authorization existed at the relevant time
  • Whether the cited act was construction activity, safety work permitted by the agency, or a different event
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Follow the operative stop-work order immediately and avoid unapproved work.
  • Identify underlying permit and safety defects; coordinate required corrective filings/inspections and a formal DOB lift where appropriate.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • dated cellar/basement photos and approved basement floor plan
  • stair/landing measurements and dated photos or approved egress plans
  • stop-work order and posted notice photographs
  • DOB permit and stop-work records including lift history
  • dated work logs, contractor schedules and site photos
  • approved corrective plans, L2/other DOB submission evidence where applicable

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 039206675P, Building Violation LLC can scope stop-work-order research, hearing support and permit/lift coordination after reviewing the actual notice and current DOB/OATH record.

Request help with stop-work order / continued work at 168 State Street, Brooklyn, NY 11201
Summons 3 of the source-linked property

Stop-work order / continued work — ECB/OATH summons 39206691P

Normalized ten-character lookup: 039206691P (infraction 201)

November 10 source-listed hearing9:30 AM

Source allegation and actual cited law

The record concerns an alleged stop-work-order violation, continued work or interference with a posted stop-work notice. Key locations/components named in the source: cellar or basement area.

Inspector narrative as preserved in source data

ATOI OBSERVED IN CELLAR LEVEL, A CUT WASTE LINE NOT COVERED UNDER LAA PERMIT #B01441244, EXP. 08/05/2027. PSWO ISSUED., OBTAIN ALL PERMITS

This is the narrative supplied in the dataset; verify it against the actual signed summons and inspector attachments.

Recorded infraction numbers and cited legal provisions:
  • 201 — 28-105.1 WORK WITHOUT A PERMIT
Issue date
October 5, 2026
Service date
October 5, 2026
Source severity
CLASS - 2
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

What the alleged violation means at 168 State Street, Brooklyn, NY 11201

Find the specific stop-work order, its geographic and work-scope restrictions, and the inspection dates. A partial stop-work order may not affect all work equally; the actual written order governs. Key locations/components named in the source: cellar or basement area. Record-specific inspection detail: Inspector text begins: “ATOI OBSERVED IN CELLAR LEVEL, A CUT WASTE LINE NOT COVERED UNDER LAA PERMIT #B01441244, EXP. 08/05/2027. PSWO ISSUED., OBTAIN ALL PERMITS”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 039206691P.

  • Whether the work observed was covered by the order
  • Whether a rescission, partial lift, or approved authorization existed at the relevant time
  • Whether the cited act was construction activity, safety work permitted by the agency, or a different event
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Follow the operative stop-work order immediately and avoid unapproved work.
  • Identify underlying permit and safety defects; coordinate required corrective filings/inspections and a formal DOB lift where appropriate.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • dated cellar/basement photos and approved basement floor plan
  • stop-work order and posted notice photographs
  • DOB permit and stop-work records including lift history
  • dated work logs, contractor schedules and site photos
  • approved corrective plans, L2/other DOB submission evidence where applicable

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 039206691P, Building Violation LLC can scope stop-work-order research, hearing support and permit/lift coordination after reviewing the actual notice and current DOB/OATH record.

Request help with stop-work order / continued work at 168 State Street, Brooklyn, NY 11201
Focused NYC DOB and OATH resolution services

Resolve the actual issue at 168 State Street, Brooklyn, NY 11201 — not just the summons number

For this property, start with stop-work order / continued work and 1 additional issue categories. Building Violation LLC can assess an authorized paid scope for OATH hearing preparation/representation, source-record research and correction coordination appropriate to the individual allegations. A hearing defense and a DOB compliance closeout may both be necessary.

  • Stop-work order / continued work (2 source summonses): Stop-work-order research, hearing support and permit/lift coordination.
  • Site safety / construction operations (1 source summons): Construction safety hearing preparation and contractor/site-safety coordination.

What to send for an assessment: Bring the original summonses, current OATH notices, available DOB records and photos tied to the alleged condition. The source-listed hearing date: December 9, 2026.

Services may require separate licensed-trade, architect/engineer or attorney involvement. No outcome, penalty reduction, permit or agency approval is guaranteed; professional fees and scope are confirmed before work.

Official NYC verification resources

Verify the current OATH / DOB record

This is a point-in-time source extract, not a live court calendar. Confirm the date, appearance method, hearing status, penalties and correction requirements directly with the government before taking action.