NYC DOB / ECB / OATH hearings · verified property resolution

241 Conselyea Street, Brooklyn, NY 11211 — Sidewalk shed / scaffolding and December 2026 OATH Hearing Details

The November 10, 2026 verified-property dataset associates 3 DOB/ECB/OATH summonses with 241 Conselyea Street, Brooklyn, NY 11211 and source-listed dates December 16, 2026, December 23, 2026. Recorded concerns include sidewalk shed / scaffolding, site safety / construction operations, work contrary to approved plans. Below are the exact source identifiers and allegations, followed by issue-specific defense checks, correction options and evidence needed for a responsible review.

Sidewalk shed / scaffoldingSite safety / construction operationsWork contrary to approved plans

Verified premises, hearing and enforcement snapshot

Verified premises address
241 Conselyea Street, Brooklyn, NY 11211
Borough
Brooklyn
BIN
3070218
BBL
3028930055
Source summonses
3
Hearing dates in source
December 16, 2026, December 23, 2026
Source snapshot
November 10, 2026
Address verification method
OATH normalized summons
Source and authorship: Building Violation LLC prepared this independent property-record explanation using a November 10, 2026 DOB/OATH source extract and verified BIN/BBL property matching. The issue analysis is editorial guidance generated from source allegations and cited laws, not a new inspection or legal determination. The source sometimes abbreviates inspector text. This is not a live OATH calendar; verify dates, appearance instructions, dispositions, monetary fields and compliance directly with NYC.

What merits immediate verification: one or more possibly shortened inspector narratives. Read the current OATH and DOB records before acting.

What is the December 2026 OATH hearing for at 241 Conselyea Street, Brooklyn, NY 11211?

The uploaded record lists 3 summonses, including 039560368R (sidewalk shed / scaffolding), 039560366N (site safety / construction operations), 035730556H (work contrary to approved plans). The source-listed hearing dates: December 16, 2026, December 23, 2026. These are allegations and dated extract fields; the current official notices determine the actual appearance obligation and disposition.

What should the owner or respondent do first?

Verify the status of each normalized summons with OATH, obtain the complete inspector narrative and cited order/permit records, address immediate hazards, and assemble dated evidence matched to each allegation. A Certificate of Correction or other DOB closeout may remain necessary even after an OATH hearing or payment.

December 2026 summonses and listed hearing times

Summons / lookupSource hearing date / timeSeverityRecorded subjectSource disposition
39560368R
039560368R
8:30 AM
CLASS - 2Sidewalk shed / scaffoldingPENDING
39560366N
039560366N
10:30 AM
CLASS - 2Site safety / construction operationsPENDING
35730556H
035730556H
8:30 AM
CLASS - 2Work contrary to approved plansPENDING

How the 3 recorded summonses relate at 241 Conselyea Street, Brooklyn, NY 11211

The verified property matching links 3 distinct summonses to 241 Conselyea Street, Brooklyn, NY 11211. They may share a property and documents, but the dataset does not establish that they arose from one inspection, one condition or one respondent. Review each summons independently.

Sidewalk shed / scaffolding (1): source summons 039560368R. Check this charge separately, even when its documents can be gathered with other property records.

Site safety / construction operations (1): source summons 039560366N. Check this charge separately, even when its documents can be gathered with other property records.

Work contrary to approved plans (1): source summons 035730556H. Check this charge separately, even when its documents can be gathered with other property records.

Shared source issue date: 2 summonses list October 8, 2026 as their issue date. Compare inspection times, sites and inspector observations before deciding whether they are factually connected.

More than one source-listed hearing date: December 16, 2026, December 23, 2026. Do not treat one appearance or adjournment as disposing of every summons; confirm each date separately.

Coordination checklist: build one property evidence folder with a separate subfolder, hearing/disposition verification and correction tracking sheet for each normalized summons number. Share drawings or photos across tickets only when the same physical facts are documented.

Each violation: allegation, defense issues, correction strategy and supporting documents

Source wording is distinguished from potential actions. These are investigatory prompts, not legal advice, guaranteed defenses or promises of DOB acceptance.

Summons 1 of the source-linked property

Sidewalk shed / scaffolding — ECB/OATH summons 39560368R

Normalized ten-character lookup: 039560368R (infraction 2P6)

November 10 source-listed hearing8:30 AM

Source allegation and actual cited law

DOB cites a sidewalk shed, scaffolding or overhead pedestrian-protection condition. The exact cited location/component should be confirmed against the original inspection record.

Inspector narrative as preserved in source data — potentially incomplete

DURING MY INSPECTION. I OBSERVED EXPOSURE 2: PIPE SCAFFOLD IN PLACE, NOT MAINTAINED, NOT FULLY PLANKED, AND MISSING GUARDRAIL SYSTEM. PROVIDE FULLY PLANKED LEVELS AND THE REQUIRED GUARDRAIL SYSTEM AND/ OR REMOV

The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.

Recorded infraction numbers and cited legal provisions:
  • 2P6
Issue date
October 8, 2026
Service date
October 8, 2026
Source severity
CLASS - 2
Source violation type
Unknown
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$2,500.00
Balance field in extract
$2,500.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

What the alleged violation means at 241 Conselyea Street, Brooklyn, NY 11211

Identify the shed location, permit status, structural or dimensional defect and any underlying facade or construction work that makes protection necessary. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “DURING MY INSPECTION. I OBSERVED EXPOSURE 2: PIPE SCAFFOLD IN PLACE, NOT MAINTAINED, NOT FULLY PLANKED, AND MISSING GUARDRAIL SYSTEM. PROVIDE FULLY PLANKED…”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 039560368R.

  • Whether the cited structure was installed, permitted or maintained as described
  • Whether the alleged defect existed at the stated location and date
  • Whether the shed was required to remain because of a separate unresolved condition
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Have dangerous installations assessed and secured promptly by a qualified contractor or professional.
  • Coordinate shed repair/removal permits and any underlying unsafe facade or construction closeout before requesting final removal.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • sidewalk shed/rigging permits and approved drawings
  • dated exposure-level photographs and inspection logs
  • scaffold or shed contractor maintenance and repair records
  • underlying facade notices, permits and DOB sign-offs where relevant

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 039560368R, Building Violation LLC can scope sidewalk-shed/scaffold hearing support and corrective work coordination after reviewing the actual notice and current DOB/OATH record.

Request help with sidewalk shed / scaffolding at 241 Conselyea Street, Brooklyn, NY 11211
Summons 2 of the source-linked property

Site safety / construction operations — ECB/OATH summons 39560366N

Normalized ten-character lookup: 039560366N (infraction 212)

November 10 source-listed hearing10:30 AM

Source allegation and actual cited law

The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. Key locations/components named in the source: rear exposure or yard.

Inspector narrative as preserved in source data — potentially incomplete

DURING MY INSPECTION OF AN ACTIVE PROPOSED 6-STORY NB. I OBSERVED INADEQUATE HOUSEKEEPING. MULTIPLE AREAS WHERE CONCRETE CLEANOUT WAS PLACED ON THE GROUND; EXPOSURE 3 REAR YARD NOT AS PER BC 3303.15. COMPLY WIT

The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.

Recorded infraction numbers and cited legal provisions:
  • 212 — BC 3303.4,27-1018 FAIL TO MAINTAIN ADEQUATE HSEKEEPING PER SECTIONS REQUIREMENTS
Issue date
October 8, 2026
Service date
October 8, 2026
Source severity
CLASS - 2
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

What the alleged violation means at 241 Conselyea Street, Brooklyn, NY 11211

Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. Key locations/components named in the source: rear exposure or yard. Record-specific inspection detail: Inspector text begins: “DURING MY INSPECTION OF AN ACTIVE PROPOSED 6-STORY NB. I OBSERVED INADEQUATE HOUSEKEEPING. MULTIPLE AREAS WHERE CONCRETE CLEANOUT WAS PLACED ON THE GROUND…”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 039560366N.

  • Whether construction was underway and the cited safety duty applied at the relevant time
  • Whether required postings, logs, plans or supervision were in place
  • Whether the cited conditions or documents belonged to this job site and respondent
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Correct active site hazards immediately and involve the qualified site safety/contractor team.
  • Update required plans, safety controls, postings, inspections or records and document remediation.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • rear-exposure photos tied to the inspection date
  • site safety plan, permits and approved construction documents
  • daily inspection logs, toolbox talks and supervisory assignments
  • dated job-site photos with exposure or floor
  • contractor correction records and agency inspection reports

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 039560366N, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.

Request help with site safety / construction operations at 241 Conselyea Street, Brooklyn, NY 11211
Summons 3 of the source-linked property

Work contrary to approved plans — ECB/OATH summons 35730556H

Normalized ten-character lookup: 035730556H (infraction 282)

November 10 source-listed hearing8:30 AM

Source allegation and actual cited law

The record alleges work that differs from DOB-approved documents or amendments. The exact cited location/component should be confirmed against the original inspection record.

Inspector narrative as preserved in source data — potentially incomplete

WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROVED AMENDMENTS. AS NOTED: AT TIME OF INSPECTION AT AN ACTIVE JOB SITE OF A PROPOSED 6 STORY BUILDING CURRENTLY POURING CONCRETE FOR 5TH FLOOR

The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.

Recorded infraction numbers and cited legal provisions:
  • 282 — 28-105.12.2 WRK DOESN'T CONFORM TO APPROV DOCS AND/OR APPROV AMENDMENTS
Issue date
October 15, 2026
Service date
October 16, 2026
Source severity
CLASS - 2
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

What the alleged violation means at 241 Conselyea Street, Brooklyn, NY 11211

Identify the application number, approval set, revision history and exactly which constructed conditions the inspector says differ. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROVED AMENDMENTS. AS NOTED: AT TIME OF INSPECTION AT AN ACTIVE JOB SITE OF A PROPOSED 6…”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 035730556H.

  • Whether the cited plans were the operative approved set on the inspection date
  • Whether an approved amendment, phased work or as-built record covers the observed condition
  • Whether the alleged difference is accurately described and located
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Compare field conditions with approved documents through a registered design professional.
  • Where necessary, amend plans, correct nonconforming work and arrange required permits/inspections before DOB closeout.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • approved plans, amendments and application history
  • current as-built measurements or professional field report
  • dated construction photographs and contractor records
  • inspection and sign-off documents

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 035730556H, Building Violation LLC can scope approved-plan discrepancy review and amendment/permit coordination after reviewing the actual notice and current DOB/OATH record.

Request help with work contrary to approved plans at 241 Conselyea Street, Brooklyn, NY 11211
Focused NYC DOB and OATH resolution services

Resolve the actual issue at 241 Conselyea Street, Brooklyn, NY 11211 — not just the summons number

For this property, start with sidewalk shed / scaffolding and 2 additional issue categories. Building Violation LLC can assess an authorized paid scope for OATH hearing preparation/representation, source-record research and correction coordination appropriate to the individual allegations. A hearing defense and a DOB compliance closeout may both be necessary.

  • Sidewalk shed / scaffolding (1 source summons): Sidewalk-shed/scaffold hearing support and corrective work coordination.
  • Site safety / construction operations (1 source summons): Construction safety hearing preparation and contractor/site-safety coordination.
  • Work contrary to approved plans (1 source summons): Approved-plan discrepancy review and amendment/permit coordination.

What to send for an assessment: Bring the original summonses, current OATH notices, available DOB records and photos tied to the alleged condition. The source-listed hearing dates: December 16, 2026, December 23, 2026.

Services may require separate licensed-trade, architect/engineer or attorney involvement. No outcome, penalty reduction, permit or agency approval is guaranteed; professional fees and scope are confirmed before work.

Official NYC verification resources

Verify the current OATH / DOB record

This is a point-in-time source extract, not a live court calendar. Confirm the date, appearance method, hearing status, penalties and correction requirements directly with the government before taking action.