NYC DOB / ECB / OATH hearings · verified property resolution

30-42 14 Street, Queens, NY 11102 — Stop-work order / continued work and December 2026 OATH Hearing Details

The November 10, 2026 verified-property dataset associates 3 DOB/ECB/OATH summonses with 30-42 14 Street, Queens, NY 11102 and source-listed date December 29, 2026. Recorded concerns include stop-work order / continued work, site safety / construction operations. Below are the exact source identifiers and allegations, followed by issue-specific defense checks, correction options and evidence needed for a responsible review.

Stop-work order / continued workSite safety / construction operations

Verified premises, hearing and enforcement snapshot

Verified premises address
30-42 14 Street, Queens, NY 11102
Borough
Queens
BIN
4005665
BBL
4005160003
Source summonses
3
Hearing dates in source
December 29, 2026
Source snapshot
November 10, 2026
Address verification method
PAD exact BIN

Official PAD aliases and building ranges: 30-42 14 STREET

Source and authorship: Building Violation LLC prepared this independent property-record explanation using a November 10, 2026 DOB/OATH source extract and verified BIN/BBL property matching. The issue analysis is editorial guidance generated from source allegations and cited laws, not a new inspection or legal determination. The source sometimes abbreviates inspector text. This is not a live OATH calendar; verify dates, appearance instructions, dispositions, monetary fields and compliance directly with NYC.

What merits immediate verification: one or more Class 1 source allegations; one or more possibly shortened inspector narratives. Read the current OATH and DOB records before acting.

What is the December 2026 OATH hearing for at 30-42 14 Street, Queens, NY 11102?

The uploaded record lists 3 summonses, including 039209110L (stop-work order / continued work), 039209108M (stop-work order / continued work), 039209109Y (site safety / construction operations). The source-listed hearing date: December 29, 2026. These are allegations and dated extract fields; the current official notices determine the actual appearance obligation and disposition.

What should the owner or respondent do first?

Verify the status of each normalized summons with OATH, obtain the complete inspector narrative and cited order/permit records, address immediate hazards, and assemble dated evidence matched to each allegation. A Certificate of Correction or other DOB closeout may remain necessary even after an OATH hearing or payment.

December 2026 summonses and listed hearing times

Summons / lookupSource hearing date / timeSeverityRecorded subjectSource disposition
39209110L
039209110L
8:30 AM
CLASS - 1Stop-work order / continued workPENDING
39209108M
039209108M
9:30 AM
CLASS - 1Stop-work order / continued workPENDING
39209109Y
039209109Y
10:30 AM
CLASS - 1Site safety / construction operationsPENDING

How the 3 recorded summonses relate at 30-42 14 Street, Queens, NY 11102

The verified property matching links 3 distinct summonses to 30-42 14 Street, Queens, NY 11102. They may share a property and documents, but the dataset does not establish that they arose from one inspection, one condition or one respondent. Review each summons independently.

Stop-work order / continued work (2): source summons 039209110L, 039209108M. These charges may share a single technical investigation or corrected condition only if the actual cited locations and inspection facts match.

Site safety / construction operations (1): source summons 039209109Y. Check this charge separately, even when its documents can be gathered with other property records.

Shared source issue date: 3 summonses list October 23, 2026 as their issue date. Compare inspection times, sites and inspector observations before deciding whether they are factually connected.

Coordination checklist: build one property evidence folder with a separate subfolder, hearing/disposition verification and correction tracking sheet for each normalized summons number. Share drawings or photos across tickets only when the same physical facts are documented.

Each violation: allegation, defense issues, correction strategy and supporting documents

Source wording is distinguished from potential actions. These are investigatory prompts, not legal advice, guaranteed defenses or promises of DOB acceptance.

Summons 1 of the source-linked property

Stop-work order / continued work — ECB/OATH summons 39209110L

Normalized ten-character lookup: 039209110L (infraction 101)

November 10 source-listed hearing8:30 AM

Source allegation and actual cited law

The record concerns an alleged stop-work-order violation, continued work or interference with a posted stop-work notice. Key locations/components named in the source: apartment or dwelling unit, commercial space.

Inspector narrative as preserved in source data

WORK WITHOUT A PERMIT. ATOI OBSERVED DEMOLITION WORK IN APT 3F, 3R AND 1ST FLOOR COMMERCIAL SPACE HAS BEEN PERFORMED WITHOUT DOB APPROVED PERMITS FOR THE SCOPE OF WORK. PSWO PO-71-26-11316, OBTAIN PERMIT

This is the narrative supplied in the dataset; verify it against the actual signed summons and inspector attachments.

Recorded infraction numbers and cited legal provisions:
  • 101 — 28-105.1 WORK WITHOUT A PERMIT
Issue date
October 23, 2026
Service date
October 23, 2026
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$2,500.00
Balance field in extract
$2,500.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.

What the alleged violation means at 30-42 14 Street, Queens, NY 11102

Find the specific stop-work order, its geographic and work-scope restrictions, and the inspection dates. A partial stop-work order may not affect all work equally; the actual written order governs. Key locations/components named in the source: apartment or dwelling unit, commercial space. Record-specific inspection detail: Inspector text begins: “WORK WITHOUT A PERMIT. ATOI OBSERVED DEMOLITION WORK IN APT 3F, 3R AND 1ST FLOOR COMMERCIAL SPACE HAS BEEN PERFORMED WITHOUT DOB APPROVED PERMITS FOR THE S…”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 039209110L.

  • Whether the work observed was covered by the order
  • Whether a rescission, partial lift, or approved authorization existed at the relevant time
  • Whether the cited act was construction activity, safety work permitted by the agency, or a different event
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Follow the operative stop-work order immediately and avoid unapproved work.
  • Identify underlying permit and safety defects; coordinate required corrective filings/inspections and a formal DOB lift where appropriate.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • approved unit layout and relevant lawful occupancy records
  • approved commercial use/occupancy and relevant interior photos
  • stop-work order and posted notice photographs
  • DOB permit and stop-work records including lift history
  • dated work logs, contractor schedules and site photos
  • approved corrective plans, L2/other DOB submission evidence where applicable

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 039209110L, Building Violation LLC can scope stop-work-order research, hearing support and permit/lift coordination after reviewing the actual notice and current DOB/OATH record.

Request help with stop-work order / continued work at 30-42 14 Street, Queens, NY 11102
Summons 2 of the source-linked property

Stop-work order / continued work — ECB/OATH summons 39209108M

Normalized ten-character lookup: 039209108M (infraction 101)

November 10 source-listed hearing9:30 AM

Source allegation and actual cited law

The record concerns an alleged stop-work-order violation, continued work or interference with a posted stop-work notice. Key locations/components named in the source: apartment or dwelling unit.

Inspector narrative as preserved in source data — potentially incomplete

WORK WITHOUT A PERMIT. ATOI OBSERVED PLUMBING WORK IN APT 3F AND 3R HAS BEEN PERFORMED WITHOUT DOB PERMITS FOR THE SCOPE OF WORK. PSWO OP-71-26-11315, OBTAIN PERMIT; OBTAIN PLUMBING PERMIT FOR THE SCOPE OF WORK

The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.

Recorded infraction numbers and cited legal provisions:
  • 101 — 28-105.1 WORK WITHOUT A PERMIT
Issue date
October 23, 2026
Service date
October 23, 2026
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$2,500.00
Balance field in extract
$2,500.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.

What the alleged violation means at 30-42 14 Street, Queens, NY 11102

Find the specific stop-work order, its geographic and work-scope restrictions, and the inspection dates. A partial stop-work order may not affect all work equally; the actual written order governs. Key locations/components named in the source: apartment or dwelling unit. Record-specific inspection detail: Inspector text begins: “WORK WITHOUT A PERMIT. ATOI OBSERVED PLUMBING WORK IN APT 3F AND 3R HAS BEEN PERFORMED WITHOUT DOB PERMITS FOR THE SCOPE OF WORK. PSWO OP-71-26-11315, OBTA…”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 039209108M.

  • Whether the work observed was covered by the order
  • Whether a rescission, partial lift, or approved authorization existed at the relevant time
  • Whether the cited act was construction activity, safety work permitted by the agency, or a different event
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Follow the operative stop-work order immediately and avoid unapproved work.
  • Identify underlying permit and safety defects; coordinate required corrective filings/inspections and a formal DOB lift where appropriate.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • approved unit layout and relevant lawful occupancy records
  • stop-work order and posted notice photographs
  • DOB permit and stop-work records including lift history
  • dated work logs, contractor schedules and site photos
  • approved corrective plans, L2/other DOB submission evidence where applicable

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 039209108M, Building Violation LLC can scope stop-work-order research, hearing support and permit/lift coordination after reviewing the actual notice and current DOB/OATH record.

Request help with stop-work order / continued work at 30-42 14 Street, Queens, NY 11102
Summons 3 of the source-linked property

Site safety / construction operations — ECB/OATH summons 39209109Y

Normalized ten-character lookup: 039209109Y (infraction 181)

November 10 source-listed hearing10:30 AM

Source allegation and actual cited law

The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. Key locations/components named in the source: apartment or dwelling unit, commercial space.

Inspector narrative as preserved in source data — potentially incomplete

FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS. ATOI OBSERVE EXCESSIVE COMBUSTIBLE CONSTRUCTION DEBRIS IN APT 1ST FLOOR COMMERCIAL SPACE, 3F AND 3R PRODUCING A HAZARDOUS CONDITION., MAINTAIN

The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.

Recorded infraction numbers and cited legal provisions:
  • 181 — BC 3303.4 & 27-1018 FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS
Issue date
October 23, 2026
Service date
October 23, 2026
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$2,500.00
Balance field in extract
$2,500.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.

What the alleged violation means at 30-42 14 Street, Queens, NY 11102

Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. Key locations/components named in the source: apartment or dwelling unit, commercial space. Record-specific inspection detail: Inspector text begins: “FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS. ATOI OBSERVE EXCESSIVE COMBUSTIBLE CONSTRUCTION DEBRIS IN APT 1ST FLOOR COMMERCIAL SPAC…”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 039209109Y.

  • Whether construction was underway and the cited safety duty applied at the relevant time
  • Whether required postings, logs, plans or supervision were in place
  • Whether the cited conditions or documents belonged to this job site and respondent
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Correct active site hazards immediately and involve the qualified site safety/contractor team.
  • Update required plans, safety controls, postings, inspections or records and document remediation.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • approved unit layout and relevant lawful occupancy records
  • approved commercial use/occupancy and relevant interior photos
  • site safety plan, permits and approved construction documents
  • daily inspection logs, toolbox talks and supervisory assignments
  • dated job-site photos with exposure or floor
  • contractor correction records and agency inspection reports

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 039209109Y, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.

Request help with site safety / construction operations at 30-42 14 Street, Queens, NY 11102
Focused NYC DOB and OATH resolution services

Resolve the actual issue at 30-42 14 Street, Queens, NY 11102 — not just the summons number

For this property, start with stop-work order / continued work and 1 additional issue categories. Building Violation LLC can assess an authorized paid scope for OATH hearing preparation/representation, source-record research and correction coordination appropriate to the individual allegations. A hearing defense and a DOB compliance closeout may both be necessary.

  • Stop-work order / continued work (2 source summonses): Stop-work-order research, hearing support and permit/lift coordination.
  • Site safety / construction operations (1 source summons): Construction safety hearing preparation and contractor/site-safety coordination.

What to send for an assessment: Bring the original summonses, current OATH notices, available DOB records and photos tied to the alleged condition. The source-listed hearing date: December 29, 2026.

Services may require separate licensed-trade, architect/engineer or attorney involvement. No outcome, penalty reduction, permit or agency approval is guaranteed; professional fees and scope are confirmed before work.

Official NYC verification resources

Verify the current OATH / DOB record

This is a point-in-time source extract, not a live court calendar. Confirm the date, appearance method, hearing status, penalties and correction requirements directly with the government before taking action.