Work contrary to approved plans — ECB/OATH summons 39169388M
Normalized ten-character lookup: 039169388M (infraction 382)
Source allegation and actual cited law
The record alleges work that differs from DOB-approved documents or amendments. Key locations/components named in the source: roof or rooftop.
Inspector narrative as preserved in source data — potentially incomplete
WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROVED AMENDMENTS. ATOI OF THE ROOF LEVEL, I OBSERVED THE RS BULKHEAD WITHFLASHING AT AN ANGLE DIRECTING WATER ON TO THE ADJOINING PROPERTY ROOM
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
- 382 — 28-105.12.2 WRK DOESN'T CONFORM TO APPROV DOCS AND/OR APPROV AMENDMENTS
- Issue date
- December 3, 2025
- Service date
- December 4, 2025
- Source severity
- CLASS - 3
- Source violation type
- Construction
- Hearing status in extract
- ADMIT/IN-VIO
- DOB/ECB status in extract
- ACTIVE
- Correction certification in extract
- Not recorded
- Penalty field in extract
- $500.00
- Balance field in extract
- $0.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
What the alleged violation means at 42 Douglass Street, Brooklyn, NY 11231
Identify the application number, approval set, revision history and exactly which constructed conditions the inspector says differ. Key locations/components named in the source: roof or rooftop. Record-specific inspection detail: Inspector text begins: “WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROVED AMENDMENTS. ATOI OF THE ROOF LEVEL, I OBSERVED THE RS BULKHEAD WITHFLASHING AT AN…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039169388M.
- Whether the cited plans were the operative approved set on the inspection date
- Whether an approved amendment, phased work or as-built record covers the observed condition
- Whether the alleged difference is accurately described and located
- Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
- Compare field conditions with approved documents through a registered design professional.
- Where necessary, amend plans, correct nonconforming work and arrange required permits/inspections before DOB closeout.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
- dated roof photographs and any roofing/equipment permit documents
- approved plans, amendments and application history
- current as-built measurements or professional field report
- dated construction photographs and contractor records
- inspection and sign-off documents
Outcome-style status in source: what to verify before acting
The extract records an in-violation/admission or similar disposition entry. Verify the written decision, payment and compliance obligations; do not treat the December date as proof of an upcoming contested hearing.
Need a summons-specific action plan? For 039169388M, Building Violation LLC can scope approved-plan discrepancy review and amendment/permit coordination after reviewing the actual notice and current DOB/OATH record.
Request help with work contrary to approved plans at 42 Douglass Street, Brooklyn, NY 11231