Stop-work order / continued work — ECB/OATH summons 39206390L
Normalized ten-character lookup: 039206390L (infraction 1C9)
Source allegation and actual cited law
The record concerns an alleged stop-work-order violation, continued work or interference with a posted stop-work notice. Key locations/components named in the source: electrical installation.
Inspector narrative as preserved in source data — potentially incomplete
PSWO AND VIOLATION ISSUED FOR ELECTRICAL WORK WITHOUT A PERMIT. ATOI OBSERVED ELECTRICAL WORK IN PROGRESS ON THE FIRST FLOOR WITH HANGING AND EXPOSED WIRING PROTRUDING FROM THE WALLS AND CEILING,AND EXPOSED ELE
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
- 1C9 — 27-3018(B) ELECTRICAL WORK WITHOUT A PERMIT
- Issue date
- October 1, 2026
- Service date
- October 1, 2026
- Source severity
- CLASS - 1
- Source violation type
- Unknown
- Hearing status in extract
- ADMIT/IN-VIO
- DOB/ECB status in extract
- ACTIVE
- Correction certification in extract
- Not recorded
- Penalty field in extract
- $2,500.00
- Balance field in extract
- $0.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.
What the alleged violation means at 454 Nostrand Avenue, Brooklyn, NY 11216
Find the specific stop-work order, its geographic and work-scope restrictions, and the inspection dates. A partial stop-work order may not affect all work equally; the actual written order governs. Key locations/components named in the source: electrical installation. Record-specific inspection detail: Inspector text begins: “PSWO AND VIOLATION ISSUED FOR ELECTRICAL WORK WITHOUT A PERMIT. ATOI OBSERVED ELECTRICAL WORK IN PROGRESS ON THE FIRST FLOOR WITH HANGING AND EXPOSED WIRIN…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039206390L.
- Whether the work observed was covered by the order
- Whether a rescission, partial lift, or approved authorization existed at the relevant time
- Whether the cited act was construction activity, safety work permitted by the agency, or a different event
- Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
- Follow the operative stop-work order immediately and avoid unapproved work.
- Identify underlying permit and safety defects; coordinate required corrective filings/inspections and a formal DOB lift where appropriate.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
- licensed electrician report and electrical filing history
- stop-work order and posted notice photographs
- DOB permit and stop-work records including lift history
- dated work logs, contractor schedules and site photos
- approved corrective plans, L2/other DOB submission evidence where applicable
Outcome-style status in source: what to verify before acting
The extract records an in-violation/admission or similar disposition entry. Verify the written decision, payment and compliance obligations; do not treat the December date as proof of an upcoming contested hearing.
Need a summons-specific action plan? For 039206390L, Building Violation LLC can scope stop-work-order research, hearing support and permit/lift coordination after reviewing the actual notice and current DOB/OATH record.
Request help with stop-work order / continued work at 454 Nostrand Avenue, Brooklyn, NY 11216