50 John Street, Manhattan, NY 10038 — Site safety / construction operations and December 2026 OATH Hearing Details
The November 10, 2026 verified-property dataset associates 8 DOB/ECB/OATH summonses with 50 John Street, Manhattan, NY 10038 and source-listed date December 3, 2026. Recorded concerns include site safety / construction operations. Below are the exact source identifiers and allegations, followed by issue-specific defense checks, correction options and evidence needed for a responsible review.
Site safety / construction operations
Verified premises, hearing and enforcement snapshot
Verified premises address
50 John Street, Manhattan, NY 10038
Borough
Manhattan
BIN
1079043
BBL
1000670001
Source summonses
8
Hearing dates in source
December 3, 2026
Source snapshot
November 10, 2026
Address verification method
PAD exact BIN
Official PAD aliases and building ranges: 101 through 105 WILLIAM STREET; 41 through 65 MAIDEN LANE; 50 through 68 JOHN STREET; 85 through 99 WILLIAM STREET
Premises precision: Official building range; low endpoint shown; multiple aliases. A verified building-level match does not prove an exact apartment or entrance.
Source and authorship: Building Violation LLC prepared this independent property-record explanation using a November 10, 2026 DOB/OATH source extract and verified BIN/BBL property matching. The issue analysis is editorial guidance generated from source allegations and cited laws, not a new inspection or legal determination. The source sometimes abbreviates inspector text. This is not a live OATH calendar; verify dates, appearance instructions, dispositions, monetary fields and compliance directly with NYC.
What merits immediate verification: one or more Class 1 source allegations; one or more possibly shortened inspector narratives. Read the current OATH and DOB records before acting.
What is the December 2026 OATH hearing for at 50 John Street, Manhattan, NY 10038?
The uploaded record lists 8 summonses, including 039205366R (site safety / construction operations), 039205373P (site safety / construction operations), 039205382R (site safety / construction operations), 039205367Z (site safety / construction operations) and additional tickets. The source-listed hearing date: December 3, 2026. These are allegations and dated extract fields; the current official notices determine the actual appearance obligation and disposition.
What should the owner or respondent do first?
Verify the status of each normalized summons with OATH, obtain the complete inspector narrative and cited order/permit records, address immediate hazards, and assemble dated evidence matched to each allegation. A Certificate of Correction or other DOB closeout may remain necessary even after an OATH hearing or payment.
How the 8 recorded summonses relate at 50 John Street, Manhattan, NY 10038
The verified property matching links 8 distinct summonses to 50 John Street, Manhattan, NY 10038. They may share a property and documents, but the dataset does not establish that they arose from one inspection, one condition or one respondent. Review each summons independently.
Site safety / construction operations (8): source summons 039205366R, 039205373P, 039205382R, 039205367Z, 039205377M, 039205387X and others. These charges may share a single technical investigation or corrected condition only if the actual cited locations and inspection facts match.
Shared source issue date: 8 summonses list September 21, 2026 as their issue date. Compare inspection times, sites and inspector observations before deciding whether they are factually connected.
Coordination checklist: build one property evidence folder with a separate subfolder, hearing/disposition verification and correction tracking sheet for each normalized summons number. Share drawings or photos across tickets only when the same physical facts are documented.
Each violation: allegation, defense issues, correction strategy and supporting documents
Source wording is distinguished from potential actions. These are investigatory prompts, not legal advice, guaranteed defenses or promises of DOB acceptance.
Summons 1 of the source-linked property
Site safety / construction operations — ECB/OATH summons 39205366R
The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. The exact cited location/component should be confirmed against the original inspection record.
Inspector narrative as preserved in source data — potentially incomplete
EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCORRECT SERIAL #'S THAT DID NOT CORRESPOND WITH CN#10825,
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
279 — AC 1RCNY-MISC,RS-MISC MISCELLANEOUS VIOLATIONS
Issue date
September 21, 2026
Service date
September 24, 2026
Source severity
CLASS - 2
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 50 John Street, Manhattan, NY 10038
Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCO…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039205366R.
Whether construction was underway and the cited safety duty applied at the relevant time
Whether required postings, logs, plans or supervision were in place
Whether the cited conditions or documents belonged to this job site and respondent
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Correct active site hazards immediately and involve the qualified site safety/contractor team.
Update required plans, safety controls, postings, inspections or records and document remediation.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
site safety plan, permits and approved construction documents
daily inspection logs, toolbox talks and supervisory assignments
dated job-site photos with exposure or floor
contractor correction records and agency inspection reports
Pending in source: what to verify before acting
The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.
Need a summons-specific action plan? For 039205366R, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.
The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. The exact cited location/component should be confirmed against the original inspection record.
Inspector narrative as preserved in source data — potentially incomplete
EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCORRECT SERIAL #'S THAT DID NOT CORRESPOND WITH CN#11225,
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
279 — AC 1RCNY-MISC,RS-MISC MISCELLANEOUS VIOLATIONS
Issue date
September 21, 2026
Service date
September 24, 2026
Source severity
CLASS - 2
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 50 John Street, Manhattan, NY 10038
Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCO…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039205373P.
Whether construction was underway and the cited safety duty applied at the relevant time
Whether required postings, logs, plans or supervision were in place
Whether the cited conditions or documents belonged to this job site and respondent
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Correct active site hazards immediately and involve the qualified site safety/contractor team.
Update required plans, safety controls, postings, inspections or records and document remediation.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
site safety plan, permits and approved construction documents
daily inspection logs, toolbox talks and supervisory assignments
dated job-site photos with exposure or floor
contractor correction records and agency inspection reports
Pending in source: what to verify before acting
The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.
Need a summons-specific action plan? For 039205373P, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.
The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. The exact cited location/component should be confirmed against the original inspection record.
Inspector narrative as preserved in source data — potentially incomplete
EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCORRECT SERIAL #'S THAT DID NOT CORRESPOND WITH CN#11525,
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
279 — AC 1RCNY-MISC,RS-MISC MISCELLANEOUS VIOLATIONS
Issue date
September 21, 2026
Service date
September 24, 2026
Source severity
CLASS - 2
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 50 John Street, Manhattan, NY 10038
Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCO…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039205382R.
Whether construction was underway and the cited safety duty applied at the relevant time
Whether required postings, logs, plans or supervision were in place
Whether the cited conditions or documents belonged to this job site and respondent
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Correct active site hazards immediately and involve the qualified site safety/contractor team.
Update required plans, safety controls, postings, inspections or records and document remediation.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
site safety plan, permits and approved construction documents
daily inspection logs, toolbox talks and supervisory assignments
dated job-site photos with exposure or floor
contractor correction records and agency inspection reports
Pending in source: what to verify before acting
The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.
Need a summons-specific action plan? For 039205382R, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.
The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. The exact cited location/component should be confirmed against the original inspection record.
Inspector narrative as preserved in source data — potentially incomplete
EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCORRECT SERIAL #'S THAT DID NOT CORRESPOND WITH CN#10925,
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
279 — AC 1RCNY-MISC,RS-MISC MISCELLANEOUS VIOLATIONS
Issue date
September 21, 2026
Service date
September 24, 2026
Source severity
CLASS - 2
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 50 John Street, Manhattan, NY 10038
Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCO…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039205367Z.
Whether construction was underway and the cited safety duty applied at the relevant time
Whether required postings, logs, plans or supervision were in place
Whether the cited conditions or documents belonged to this job site and respondent
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Correct active site hazards immediately and involve the qualified site safety/contractor team.
Update required plans, safety controls, postings, inspections or records and document remediation.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
site safety plan, permits and approved construction documents
daily inspection logs, toolbox talks and supervisory assignments
dated job-site photos with exposure or floor
contractor correction records and agency inspection reports
Pending in source: what to verify before acting
The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.
Need a summons-specific action plan? For 039205367Z, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.
The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. The exact cited location/component should be confirmed against the original inspection record.
Inspector narrative as preserved in source data — potentially incomplete
EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCORRECT SERIAL #'S THAT DID NOT CORRESPOND WITH CN#11325,
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
279 — AC 1RCNY-MISC,RS-MISC MISCELLANEOUS VIOLATIONS
Issue date
September 21, 2026
Service date
September 24, 2026
Source severity
CLASS - 2
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 50 John Street, Manhattan, NY 10038
Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCO…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039205377M.
Whether construction was underway and the cited safety duty applied at the relevant time
Whether required postings, logs, plans or supervision were in place
Whether the cited conditions or documents belonged to this job site and respondent
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Correct active site hazards immediately and involve the qualified site safety/contractor team.
Update required plans, safety controls, postings, inspections or records and document remediation.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
site safety plan, permits and approved construction documents
daily inspection logs, toolbox talks and supervisory assignments
dated job-site photos with exposure or floor
contractor correction records and agency inspection reports
Pending in source: what to verify before acting
The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.
Need a summons-specific action plan? For 039205377M, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.
The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. The exact cited location/component should be confirmed against the original inspection record.
Inspector narrative as preserved in source data — potentially incomplete
EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE MAST CLIMBER DOCUMENTS/LOGS. PRESHIFT INSP. RECORDS FOR CN#11625, CD#5908, POS. 8 CONTAINED INCORRECT SERIAL #S. REQUIRED LOGS, INCL. USER INFO, PREIN
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
179 — AC 1RCNY-MISC,RS-MISC MISCELLANEOUS VIOLATIONS
Issue date
September 21, 2026
Service date
September 24, 2026
Source severity
CLASS - 1
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$2,500.00
Balance field in extract
$2,500.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Safety priority: Class 1 in source — treat any alleged immediately hazardous condition as urgent; verify specific DOB correction requirements.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 50 John Street, Manhattan, NY 10038
Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE MAST CLIMBER DOCUMENTS/LOGS. PRESHIFT INSP. RECORDS FOR CN#11625, CD#5908, POS. 8 CONTAINED INC…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039205387X.
Whether construction was underway and the cited safety duty applied at the relevant time
Whether required postings, logs, plans or supervision were in place
Whether the cited conditions or documents belonged to this job site and respondent
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Correct active site hazards immediately and involve the qualified site safety/contractor team.
Update required plans, safety controls, postings, inspections or records and document remediation.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
site safety plan, permits and approved construction documents
daily inspection logs, toolbox talks and supervisory assignments
dated job-site photos with exposure or floor
contractor correction records and agency inspection reports
Pending in source: what to verify before acting
The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.
Need a summons-specific action plan? For 039205387X, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.
The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. The exact cited location/component should be confirmed against the original inspection record.
Inspector narrative as preserved in source data — potentially incomplete
EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCORRECT SERIAL #'S THAT DID NOT CORRESPOND WITH CN#11125,
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
279 — AC 1RCNY-MISC,RS-MISC MISCELLANEOUS VIOLATIONS
Issue date
September 21, 2026
Service date
September 24, 2026
Source severity
CLASS - 2
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 50 John Street, Manhattan, NY 10038
Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCO…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039205369M.
Whether construction was underway and the cited safety duty applied at the relevant time
Whether required postings, logs, plans or supervision were in place
Whether the cited conditions or documents belonged to this job site and respondent
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Correct active site hazards immediately and involve the qualified site safety/contractor team.
Update required plans, safety controls, postings, inspections or records and document remediation.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
site safety plan, permits and approved construction documents
daily inspection logs, toolbox talks and supervisory assignments
dated job-site photos with exposure or floor
contractor correction records and agency inspection reports
Pending in source: what to verify before acting
The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.
Need a summons-specific action plan? For 039205369M, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.
The cited item concerns safety practices, documentation, supervision or housekeeping at a construction site. The exact cited location/component should be confirmed against the original inspection record.
Inspector narrative as preserved in source data — potentially incomplete
EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCORRECT SERIAL #'S THAT DID NOT CORRESPOND WITH CN#11425,
The supplied record stops at its extract limit and may omit the rest of the inspector narrative. Obtain the complete original summons before making a factual or legal decision.
Recorded infraction numbers and cited legal provisions:
279 — AC 1RCNY-MISC,RS-MISC MISCELLANEOUS VIOLATIONS
Issue date
September 21, 2026
Service date
September 24, 2026
Source severity
CLASS - 2
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
Record-specific resolution analysis — not an OATH finding
What the alleged violation means at 50 John Street, Manhattan, NY 10038
Identify the exact construction operation, site location, plan, log, posting, supervision or housekeeping requirement the inspector lists. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “EQUIPMENT USER NEW ROC FAILED TO MAINTAIN COMPLETE/ACCURATE REQUIRED DOCUMENTS/LOGS FOR THE MAST CLIMBERS ON SITE. PRE-SHIFT INSP. DOCUMENTS CONTAINED INCO…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039205380N.
Whether construction was underway and the cited safety duty applied at the relevant time
Whether required postings, logs, plans or supervision were in place
Whether the cited conditions or documents belonged to this job site and respondent
Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
Correct active site hazards immediately and involve the qualified site safety/contractor team.
Update required plans, safety controls, postings, inspections or records and document remediation.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
site safety plan, permits and approved construction documents
daily inspection logs, toolbox talks and supervisory assignments
dated job-site photos with exposure or floor
contractor correction records and agency inspection reports
Pending in source: what to verify before acting
The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.
Need a summons-specific action plan? For 039205380N, Building Violation LLC can scope construction safety hearing preparation and contractor/site-safety coordination after reviewing the actual notice and current DOB/OATH record.
Resolve the actual issue at 50 John Street, Manhattan, NY 10038 — not just the summons number
For this property, start with site safety / construction operations. Building Violation LLC can assess an authorized paid scope for OATH hearing preparation/representation, source-record research and correction coordination appropriate to the individual allegations. A hearing defense and a DOB compliance closeout may both be necessary.
Site safety / construction operations (8 source summonses): Construction safety hearing preparation and contractor/site-safety coordination.
What to send for an assessment: Bring the original summonses, current OATH notices, available DOB records and photos tied to the alleged condition. The source-listed hearing date: December 3, 2026.
Services may require separate licensed-trade, architect/engineer or attorney involvement. No outcome, penalty reduction, permit or agency approval is guaranteed; professional fees and scope are confirmed before work.
This is a point-in-time source extract, not a live court calendar. Confirm the date, appearance method, hearing status, penalties and correction requirements directly with the government before taking action.
Important: This private-service page is not affiliated with NYC OATH or DOB, does not establish guilt or innocence and is not legal advice. Building Violation LLC may provide authorized non-attorney OATH representation and violation-resolution coordination within its permitted scope. Different proceedings can require an attorney or licensed professional. The source field named PENALITY_IMPOSED is shown for transparency but does not prove a presently payable adjudicated amount.