Sidewalk shed / scaffolding — ECB/OATH summons 39559456Z
Normalized ten-character lookup: 039559456Z (infraction 207)
Source allegation and actual cited law
DOB cites a sidewalk shed, scaffolding or overhead pedestrian-protection condition. Key locations/components named in the source: sidewalk shed.
Inspector narrative as preserved in source data
THE SIDEWALK SHED IN PLACE PERMIT EXPIRED ON 08/05/2025 WITHOUT A RENEWAL IN PROCESS. PERMITS MUST BE MAINTAINED AS REQUIRED BY CODE.OBTAIN AND MAINTAIN THE SHED PERMIT AS PER CODE OR REMOVE THE SHED.
This is the narrative supplied in the dataset; verify it against the actual signed summons and inspector attachments.
- 207 — BC 105.8.2 TEMPORARY CONSTRUCTION EQUIPMENT ON SITE-EXPIRED PERMIT
- Issue date
- September 22, 2026
- Service date
- September 22, 2026
- Source severity
- CLASS - 2
- Source violation type
- Construction
- Hearing status in extract
- PENDING
- DOB/ECB status in extract
- ACTIVE
- Correction certification in extract
- Not recorded
- Penalty field in extract
- $1,250.00
- Balance field in extract
- $1,250.00
Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.
What the alleged violation means at 575 Herkimer Street, Brooklyn, NY 11213
Identify the shed location, permit status, structural or dimensional defect and any underlying facade or construction work that makes protection necessary. Key locations/components named in the source: sidewalk shed. Record-specific inspection detail: Inspector text begins: “THE SIDEWALK SHED IN PLACE PERMIT EXPIRED ON 08/05/2025 WITHOUT A RENEWAL IN PROCESS. PERMITS MUST BE MAINTAINED AS REQUIRED BY CODE.OBTAIN AND MAINTAIN TH…”
Possible defense questions and factual disputes to investigate
The following are issues to verify, not assurances that a defense applies to summons 039559456Z.
- Whether the cited structure was installed, permitted or maintained as described
- Whether the alleged defect existed at the stated location and date
- Whether the shed was required to remain because of a separate unresolved condition
- Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.
Correction and DOB closeout strategy
- Have dangerous installations assessed and secured promptly by a qualified contractor or professional.
- Coordinate shed repair/removal permits and any underlying unsafe facade or construction closeout before requesting final removal.
Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.
Evidence and documents tailored to this allegation
- shed permit and contractor maintenance report
- sidewalk shed/rigging permits and approved drawings
- dated exposure-level photographs and inspection logs
- scaffold or shed contractor maintenance and repair records
- underlying facade notices, permits and DOB sign-offs where relevant
Pending in source: what to verify before acting
The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.
Need a summons-specific action plan? For 039559456Z, Building Violation LLC can scope sidewalk-shed/scaffold hearing support and corrective work coordination after reviewing the actual notice and current DOB/OATH record.
Request help with sidewalk shed / scaffolding at 575 Herkimer Street, Brooklyn, NY 11213