61-20 Madison Street, Queens, NY 11385 — Boiler / gas / plumbing compliance and December 2026 OATH Hearing Details

The November 10, 2026 verified-property dataset associates 3 DOB/ECB/OATH summonses with 61-20 Madison Street, Queens, NY 11385 and source-listed dates December 1, 2026, December 10, 2026. Recorded concerns include boiler / gas / plumbing compliance, work without a permit, unsafe condition / maintenance. Below are the exact source identifiers and allegations, followed by issue-specific defense checks, correction options and evidence needed for a responsible review.

Boiler / gas / plumbing complianceWork without a permitUnsafe condition / maintenance

Verified premises, hearing and enforcement snapshot

Verified premises address
61-20 Madison Street, Queens, NY 11385
Borough
Queens
BIN
4087884
BBL
4036190027
Source summonses
3
Hearing dates in source
December 1, 2026, December 10, 2026
Source snapshot
November 10, 2026
Address verification method
Prior verified BIN

Official PAD aliases and building ranges: 61-20 MADISON STREET

Source and authorship: Building Violation LLC prepared this independent property-record explanation using a November 10, 2026 DOB/OATH source extract and verified BIN/BBL property matching. The issue analysis is editorial guidance generated from source allegations and cited laws, not a new inspection or legal determination. The source sometimes abbreviates inspector text. This is not a live OATH calendar; verify dates, appearance instructions, dispositions, monetary fields and compliance directly with NYC.

What is the December 2026 OATH hearing for at 61-20 Madison Street, Queens, NY 11385?

The uploaded record lists 3 summonses, including 039205504X (boiler / gas / plumbing compliance), 039179396L (work without a permit), 039179397N (unsafe condition / maintenance). The source-listed hearing dates: December 1, 2026, December 10, 2026. These are allegations and dated extract fields; the current official notices determine the actual appearance obligation and disposition.

What should the owner or respondent do first?

Verify the status of each normalized summons with OATH, obtain the complete inspector narrative and cited order/permit records, address immediate hazards, and assemble dated evidence matched to each allegation. A Certificate of Correction or other DOB closeout may remain necessary even after an OATH hearing or payment.

December 2026 summonses and listed hearing times

Summons / lookupSource hearing date / timeSeverityRecorded subjectSource disposition
39205504X
039205504X
8:30 AM
CLASS - 3Boiler / gas / plumbing compliancePENDING
39179396L
039179396L
8:30 AM
CLASS - 2Work without a permitPENDING
39179397N
039179397N
8:30 AM
CLASS - 2Unsafe condition / maintenancePENDING

How the 3 recorded summonses relate at 61-20 Madison Street, Queens, NY 11385

The verified property matching links 3 distinct summonses to 61-20 Madison Street, Queens, NY 11385. They may share a property and documents, but the dataset does not establish that they arose from one inspection, one condition or one respondent. Review each summons independently.

Boiler / gas / plumbing compliance (1): source summons 039205504X. Check this charge separately, even when its documents can be gathered with other property records.

Unsafe condition / maintenance (1): source summons 039179397N. Check this charge separately, even when its documents can be gathered with other property records.

Work without a permit (1): source summons 039179396L. Check this charge separately, even when its documents can be gathered with other property records.

Shared source issue date: 2 summonses list March 6, 2026 as their issue date. Compare inspection times, sites and inspector observations before deciding whether they are factually connected.

More than one source-listed hearing date: December 1, 2026, December 10, 2026. Do not treat one appearance or adjournment as disposing of every summons; confirm each date separately.

Coordination checklist: build one property evidence folder with a separate subfolder, hearing/disposition verification and correction tracking sheet for each normalized summons number. Share drawings or photos across tickets only when the same physical facts are documented.

Each violation: allegation, defense issues, correction strategy and supporting documents

Source wording is distinguished from potential actions. These are investigatory prompts, not legal advice, guaranteed defenses or promises of DOB acceptance.

Summons 1 of the source-linked property

Boiler / gas / plumbing compliance — ECB/OATH summons 39205504X

Normalized ten-character lookup: 039205504X (infraction 354)

November 10 source-listed hearing8:30 AM

Source allegation and actual cited law

The citation relates to gas, plumbing, boiler or mechanical equipment, permits or inspections. Key locations/components named in the source: cellar or basement area, rear exposure or yard, gas or boiler equipment, apartment or dwelling unit.

Inspector narrative as preserved in source data

AMERICAN BOILER HAS POOR FLAME FROM OIL BURNER+WATER LEAKING FROM CELLAR CEILING BELOW APT 1R+3 CELLAR WINDOWS ARE BROKEN+2 HOLES IN CELLAR CEILING@REAR;CORRECT VIOLATION+SUBMIT CERTIFICATE OF CORRECTION

This is the narrative supplied in the dataset; verify it against the actual signed summons and inspector attachments.

Recorded infraction numbers and cited legal provisions:
  • 354 — 28-301.1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: SERVICE EQUIPME
Issue date
September 24, 2026
Service date
September 24, 2026
Source severity
CLASS - 3
Source violation type
Boilers
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$500.00
Balance field in extract
$500.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

What the alleged violation means at 61-20 Madison Street, Queens, NY 11385

Identify the cited installation, system or report cycle and compare it with the building’s approved equipment and trade filings. Key locations/components named in the source: cellar or basement area, rear exposure or yard, gas or boiler equipment, apartment or dwelling unit. Record-specific inspection detail: Inspector text begins: “AMERICAN BOILER HAS POOR FLAME FROM OIL BURNER+WATER LEAKING FROM CELLAR CEILING BELOW APT 1R+3 CELLAR WINDOWS ARE BROKEN+2 HOLES IN CELLAR CEILING@REAR;CO…”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 039205504X.

  • Whether a required permit, inspection or periodic filing actually applied at that time
  • Whether licensed-trade repairs, test results or sign-offs already address the cited item
  • Whether the exact equipment and property location match the notice
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Have potentially dangerous gas or boiler conditions checked by a properly licensed professional promptly.
  • Arrange the correct mechanical/plumbing/gas filing, inspection, repairs or report submission and closeout.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • dated cellar/basement photos and approved basement floor plan
  • rear-exposure photos tied to the inspection date
  • licensed-trade test results and equipment/permit records
  • plumbing/gas/boiler permit and inspection history
  • licensed contractor reports, tests and paid invoices
  • equipment photographs, serials or specifications
  • DOB/utility correspondence and accepted sign-offs

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 039205504X, Building Violation LLC can scope mechanical/plumbing violation research and licensed-trade correction coordination after reviewing the actual notice and current DOB/OATH record.

Request help with boiler / gas / plumbing compliance at 61-20 Madison Street, Queens, NY 11385
Summons 2 of the source-linked property

Work without a permit — ECB/OATH summons 39179396L

Normalized ten-character lookup: 039179396L (infraction 201)

November 10 source-listed hearing8:30 AM

Source allegation and actual cited law

DOB alleges construction, alteration, demolition or installation work without a required permit. The exact cited location/component should be confirmed against the original inspection record.

Inspector narrative as preserved in source data

OBSERVED TWO 275 GALLON UL-80 OIL TANKS INSTALLED WITHOUT A PERMIT. OBTAIN THE PROPER PERMIT AND SUBMIT A CERTIFICATE OF CORRECTION.

This is the narrative supplied in the dataset; verify it against the actual signed summons and inspector attachments.

Recorded infraction numbers and cited legal provisions:
  • 201 — 28-105.1 WORK WITHOUT A PERMIT
Issue date
March 6, 2026
Service date
March 6, 2026
Source severity
CLASS - 2
Source violation type
Construction
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

What the alleged violation means at 61-20 Madison Street, Queens, NY 11385

Determine which physical work is alleged, when it was performed and whether an approved filing/permit covered that scope at inspection. A permit issued after the inspection does not by itself establish that the charge was invalid when issued. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “OBSERVED TWO 275 GALLON UL-80 OIL TANKS INSTALLED WITHOUT A PERMIT. OBTAIN THE PROPER PERMIT AND SUBMIT A CERTIFICATE OF CORRECTION.”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 039179396L.

  • Whether the work identified in the summons actually took place at the cited premises
  • Whether the work was exempt, previously permitted, or covered by approved plans at the relevant time
  • Whether the named respondent or owner had the responsibility alleged under the cited provision
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Confirm which work can lawfully remain and whether legalization, permits or removal/restoration is necessary.
  • Have a registered architect, engineer or licensed trade assess design, safety, permitting and inspection requirements as appropriate.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • historical DOB NOW/BIS permits, applications, approvals and sign-offs
  • approved architectural or engineering plans and amendments
  • dated photographs of the exact cited work or area
  • contracts, invoices and contractor or tenant work records
  • permit or restoration evidence and final inspections

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 039179396L, Building Violation LLC can scope work-without-permit hearing review and legalization/removal scope after reviewing the actual notice and current DOB/OATH record.

Request help with work without a permit at 61-20 Madison Street, Queens, NY 11385
Summons 3 of the source-linked property

Unsafe condition / maintenance — ECB/OATH summons 39179397N

Normalized ten-character lookup: 039179397N (infraction 254)

November 10 source-listed hearing8:30 AM

Source allegation and actual cited law

DOB alleges a failure to maintain a building component in code-compliant or safe condition. The exact cited location/component should be confirmed against the original inspection record.

Inspector narrative as preserved in source data

CONTROLS ARE MISSING COVERS, MISSING HANDLE ON OIL LINE SHUTOFF VALVE AT BURNER. CORRECT VIOLATING CONDITIONS AND SUBMIT A CERTIFICATE OF CORRECTION.

This is the narrative supplied in the dataset; verify it against the actual signed summons and inspector attachments.

Recorded infraction numbers and cited legal provisions:
  • 254 — 28-301.1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: SERVICE EQUIPME
Issue date
March 6, 2026
Service date
March 6, 2026
Source severity
CLASS - 2
Source violation type
Boilers
Hearing status in extract
PENDING
DOB/ECB status in extract
ACTIVE
Correction certification in extract
Not recorded
Penalty field in extract
$1,250.00
Balance field in extract
$1,250.00

Penalty and balance are fields in the supplied November 10 extract—not independently verified current fines, final adjudications or amounts presently owed.

What the alleged violation means at 61-20 Madison Street, Queens, NY 11385

A general maintenance law citation is not the actual defect: the condition is the specific item described in the inspector narrative, which must be examined with photographs and repair records. The exact cited location/component should be confirmed against the original inspection record. Record-specific inspection detail: Inspector text begins: “CONTROLS ARE MISSING COVERS, MISSING HANDLE ON OIL LINE SHUTOFF VALVE AT BURNER. CORRECT VIOLATING CONDITIONS AND SUBMIT A CERTIFICATE OF CORRECTION.”

Possible defense questions and factual disputes to investigate

The following are issues to verify, not assurances that a defense applies to summons 039179397N.

  • Whether the exact physical condition and location existed on the inspection date
  • Whether the cited component and applicable maintenance standard were correctly identified
  • Whether repairs, inspections or other contemporaneous records change the factual assessment
  • Compare the original summons, issue/service dates and the complete inspector narrative with each document; do not assume any potential defense is established without proof.

Correction and DOB closeout strategy

  • Correct unsafe conditions and protect affected occupants or the public without waiting for a hearing.
  • Choose appropriate repair professionals/permits, verify whether reinspection or Certificate of Correction is needed, and retain proof.

Determine whether DOB requires a Certificate of Correction, a separate reinspection, application/permit sign-off or an order-lift. An OATH outcome, a paid fine and physical correction are separate issues.

Evidence and documents tailored to this allegation

  • time-stamped photographs of the specific alleged condition
  • maintenance and repair tickets, invoices and professional findings
  • prior complaints, reports and permit history where relevant
  • dated post-correction photographs and agency compliance records

Pending in source: what to verify before acting

The November 10 extract lists the hearing as PENDING. Confirm its present scheduling, appearance method, adjournment/settlement rules and evidence deadlines directly with OATH.

Need a summons-specific action plan? For 039179397N, Building Violation LLC can scope building-maintenance hearing review and documented correction closeout after reviewing the actual notice and current DOB/OATH record.

Request help with unsafe condition / maintenance at 61-20 Madison Street, Queens, NY 11385
Focused NYC DOB and OATH resolution services

Resolve the actual issue at 61-20 Madison Street, Queens, NY 11385 — not just the summons number

For this property, start with boiler / gas / plumbing compliance and 2 additional issue categories. Building Violation LLC can assess an authorized paid scope for OATH hearing preparation/representation, source-record research and correction coordination appropriate to the individual allegations. A hearing defense and a DOB compliance closeout may both be necessary.

  • Boiler / gas / plumbing compliance (1 source summons): Mechanical/plumbing violation research and licensed-trade correction coordination.
  • Work without a permit (1 source summons): Work-without-permit hearing review and legalization/removal scope.
  • Unsafe condition / maintenance (1 source summons): Building-maintenance hearing review and documented correction closeout.

What to send for an assessment: Bring the original summonses, current OATH notices, available DOB records and photos tied to the alleged condition. The source-listed hearing dates: December 1, 2026, December 10, 2026.

Services may require separate licensed-trade, architect/engineer or attorney involvement. No outcome, penalty reduction, permit or agency approval is guaranteed; professional fees and scope are confirmed before work.

Official NYC verification resources

Verify the current OATH / DOB record

This is a point-in-time source extract, not a live court calendar. Confirm the date, appearance method, hearing status, penalties and correction requirements directly with the government before taking action.