The AHV is tied to authorized construction activity.
Construction outside normal NYC hours generally requires an After Hours Variance. The filing has to match the underlying job and should be planned before the intended work date.
DOB requires AHVs for construction before 7:00 AM, after 6:00 PM, or on Saturday/Sunday and says applications should be filed at least two business days before the first intended work day.
The AHV is tied to authorized construction activity.
DEP construction-noise requirements and mitigation planning may also apply.
AHVs have advance submission deadlines and renewal rules.